This amendment modifies a solicitation for a pre-engineered building from the Department of the Air Force Global Strike Command. The amendment extends the quote submittal deadline from July 7, 2020 to July 13, 2020 at 2:00 PM MST. It also changes the delivery date in the specifications to 150 days from contract award in accordance with the modified submittal schedule. The submittal schedule was updated to require structural steel delivery, including relevant inventory lists and installation guides, no later than 7 weeks after award, with the remaining steel to be delivered no later than 150 days after award.

View the file

Other files for this federal contract opportunity

Other files attached to RHS Vehicle Maintenance Pre-Engineered Building, newest first.
File Type Posted
QnA Sheet_Revised_Cumulative.pdf PDF
Atch_1_RH Maintenance Facility PEB Specs_Amend 1_2July 2020.pdf PDF
Conformed_COMBO.pdf PDF
Atch_3_AF Form 66 Submittal Schedule_Amend 1_2 July 2020.xls XLS spreadsheet
QnA Sheet.pdf PDF
Revised RH Maintenance Facility PEB Specs.pdf PDF
Atch_1_Maintenance Facility PEB Specs.pdf PDF
Atch_3_AF Form 66 Submittal Schedule 20200124.pdf PDF
Atch_2_Maintenance_Facility_PEB_30_20200129.pdf PDF
COMBO.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 341st Missile Wing (AFGSC)

2 July 2020

SUBJECT: Amendment 001 to FA4626-20-Q-0031

1. The purpose of this memorandum is to document three changes made to the original combined synopsis/solicitation.

2. The quote submittal date and time will be extended by six (6) calendar days, from Tuesday 7 July 2020 at 2:00PM MST, to Monday 13 July 2020 at 2:00PM MST.

3. A change was made to the specifications reflecting a new delivery date of 150 days after date of contract and requiring it to be in accordance with the new submittal schedule.

4. Changes were made to the submittal schedule with the addition of a Structural Steel delivery, with relevant inventory lists, and installation guides to be delivered no later than 7 weeks after award and the remaining steel to be delivered no later than 150 days after award.

Erik M. Hallberg, A1C, USAF Contracting Specialist