PRQE_10-0175_Questions_and_Answers.pdf
PDF 11 KB Posted
- Solicitation number
- FA4621-14-R-0008
About this file
Questions and Answers that were submitted for this project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PRQE_10-0175_SOW_(Revised)_8_Aug_2014.pdf | ||
| PRQE_10-0175_Revised_Drawings.pdf | ||
| FA4621-14-R-0008_0001_Amendment__1.pdf | ||
| Pre-proposal_Site_Visit_slides.pdf | ||
| EMF-100.pdf | ||
| EMF-110.pdf | ||
| TF-850.pdf | ||
| TF-1171.pdf | ||
| EMF-030.pdf | ||
| TF-840.pdf | ||
| TF-1107.pdf | ||
| TF-1170.pdf | ||
| TF-1186.pdf | ||
| TF-1091.pdf | ||
| TF-1169.pdf | ||
| TF-1166.pdf | ||
| EMF-050.pdf | ||
| TF-1104.pdf | ||
| TF-852.pdf | ||
| TF-1185.pdf | ||
| TF-1183.pdf | ||
| EMF-020.pdf | ||
| EMF-090.pdf | ||
| EMF-010.pdf | ||
| EMF-040.pdf | ||
| EMF-070.pdf | ||
| EMF-080.pdf | ||
| EMF-060.pdf | ||
| Atch_1_-_PRQE_10-0175_SOW.pdf | ||
| Atch_5_-_Wage_Determination.pdf | ||
| Atch_6_-_PAST_AND_PRESENT_PERFORMANCE_SURVEY.pdf | ||
| Atch_2_-_PRQE_10-0175_33_70_02.00_10.pdf | ||
| Atch_3_-_General_Requirements.pdf | ||
| FA4621-14-R-0008.pdf | ||
| Atch_4_-_PRQE_10-0175_Drawings.pdf |
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRQE 10-0175 Repair Underground Electrical Feeders “F” Branches
Questions and Answers
Q1. Is the spare duct serviceable?
A1. Assume any spare duct is serviceable. If conduit is collapsed, a contract modification will be issued to repair conduit.
Q2. Will “ALL” the work need to be performed on Weekends and evenings?
A2. No, only work that requires a building power outage. Any available spare duct should be utilized to minimize outages. In some cases and outage may take longer than Friday night to Monday morning. This type of outage will need extensive coordination. The contract shall make every effort to minimize the outages outside of normal duty hours.
Q3. Some of the work is in the Maintenance Complex. Will a free zone be required?
A3. Yes, a free zone will need to be established. The contractor shall be responsible for providing red rope and stations enclosing the work area where workers are permitted. Contractor shall post a sign every 100 YDS along the perimeter of the free zone; and where fencing makes abrupt changes in direction (i.e. corners). Contractor is responsible for signage. Signage is a sticker applied to a metal or plastic sign and hung on the fence or rope. Sign backing SPEC. IS 18"X18" square sheet metal or hard plastic panel. Control sign for point of VEHICULAR and PEDESTRIAN access are 36"X30", one sign on side of access control point, same type of installation. 22 SFS will provide sign stickers for contractor to apply to backing.
Q4. Para 1.13 of Atch_3_ General Conditions refers to Geospatial Data. Since this project involves no new structures and is only replacement of cable will there be any need for any geospatial needed on this project?
A4. No geospatial Required.
Q5. Para 1.14 of Atch_3_ General Conditions refers to Equipment Barcoding Requirements.
Will anything on this project require barcodes?
A5. No Barcoding Required. All cables will be tagged and labeled/tagged with the circuit number and destination of cable.
Q6. Based on most of the buildings being occupied and the unknown on spare ducts I assume we will have to do most or the replacements on off hours or weekends?
A6. Only work that requires a building power outage shall be done on weekends and off hours.
Any available spare duct should be utilized to minimize outages.
Q7. Do concentric neutral one for one cables exist in the feeders?
A7. It may or may not.
Q8. Should all scrap metal be submitted to CE?
A8. Yes
Q9. How many past performance surveys does contracting require?
A9. No more than 5. Information is contained in section L of the solicitation.