Pre-proposal_Site_Visit_slides.pdf

PDF 146 KB Posted

Attached to
Repair Underground Electrical Feeders "F" Branches
Solicitation number
FA4621-14-R-0008
Issued by

About this file

Attached are the power point slides that were discussed in the pre-proposal conference and site visit.

View the file

Other files

File Type Posted
PRQE_10-0175_SOW_(Revised)_8_Aug_2014.pdf PDF
PRQE_10-0175_Revised_Drawings.pdf PDF
PRQE_10-0175_Questions_and_Answers.pdf PDF
FA4621-14-R-0008_0001_Amendment__1.pdf PDF
EMF-100.pdf PDF
EMF-110.pdf PDF
TF-850.pdf PDF
TF-1171.pdf PDF
EMF-030.pdf PDF
TF-840.pdf PDF
TF-1107.pdf PDF
TF-1170.pdf PDF
TF-1186.pdf PDF
TF-1091.pdf PDF
TF-1169.pdf PDF
TF-1166.pdf PDF
EMF-050.pdf PDF
TF-1104.pdf PDF
TF-852.pdf PDF
TF-1185.pdf PDF
TF-1183.pdf PDF
EMF-020.pdf PDF
EMF-090.pdf PDF
EMF-010.pdf PDF
EMF-040.pdf PDF
EMF-070.pdf PDF
EMF-080.pdf PDF
EMF-060.pdf PDF
Atch_1_-_PRQE_10-0175_SOW.pdf PDF
Atch_5_-_Wage_Determination.pdf PDF
Atch_6_-_PAST_AND_PRESENT_PERFORMANCE_SURVEY.pdf PDF
Atch_2_-_PRQE_10-0175_33_70_02.00_10.pdf PDF
Atch_3_-_General_Requirements.pdf PDF
FA4621-14-R-0008.pdf PDF
Atch_4_-_PRQE_10-0175_Drawings.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Conference for

Repair Underground Electrical Feeders “F”

Branches

McConnell AFB, KS 30 July 2014

Early Exchanges of Information

• This conference facilitates the prudent exchange of information between the Government and prospective Offerors.

• Any questions or concerns that may be discussed at this time are specifically non-binding as only the CO can enter into obligations on behalf of the Government.

• If you have any questions concerning this notice, please feel free to ask the contract administrator.

Overview

• Identify key personnel and their responsibilities

• Define the requirements

• Detail unique Government considerations

• Explain proposal requirements (CES)

• Discuss amendments

• Conduct site visit

• Invite questions and answers

Key Personnel & Their Responsibilities

• CO – The only person who can bind the Government-Ms.

Valerie Brown

• CA – CO’s assistant-Ms. Bridgette Donley

• Project engineer – Technical expert-Mr. Albert Seemayer

• Quality assurance-Inspector will be assigned after award

Define the Requirements

• Solicitation Package:

• SF 1442/Bid Schedule/Provisions/Clauses

• Attachment 1 – Statement of Work

• Attachment 2 - Specifications

• Attachment 3 – General Requirements

• Attachment 4 – Drawings

• Attachment 5 – Wage Determination

• Attachment 6 – Past and Present Performance Survey

Define the Requirements

• Solicitation to Small Businesses

• Davis-Bacon Act

• Wage Determination KS140016, dated 3 Jan 14

• Weekly Payroll

• Schedule of Materials Submittal

• Contract award contingent on funding

• Period of Performance (PoP) – 300 days after notice to proceed (NTP)

• NAICS - 237130

Unique Considerations

• System for Award Management (SAM)

• Wide Area Workflow (WAWF)

• Base Access Requests (formerly MCCON Form 114)

• Bonds

• Availability of Funds - Funds are not presently available for this project. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the RFP closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse any offerors for any costs.

Proposal Requirements

• Proposal Preparation/Instructions-use Solicitation

• Proposals are due to this office

• NLT 2:00 PM, 15 Aug 2014

• Late proposals not accepted

• Proposal Evaluations

• Past Performance Tradeoff – past performance significantly more important than price

Proposal Requirements (cont’d)

• Amendments

• Only an amendment from the CO changes the solicitation

• Acknowledgement procedures-(contractor must acknowledge to be binding)

• Requirement (CES)

• SOW

• Specifications

• Drawings

• Site visit to facilities

Conclusion

• Proposals are due to this office

• NLT 2:00 PM, Fri 15 Aug 2014

• Proposal conference meeting minutes along with questions/answers will be provided via FBO

• Questions? Written questions are due to this office

• NLT 3:00 PM, Wed 6 Aug 2014

Pre-Proposal Conference �for�Repair Underground Electrical Feeders “F” Branches
Early Exchanges of Information
Overview
Key Personnel & Their Responsibilities
Define the Requirements�
Define the Requirements
Unique Considerations
Proposal Requirements
Proposal Requirements (cont’d)
Conclusion