Atch 3 Schedule SONET 2 DWDM Migration.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Vandenberg SONET to DWDM Migration
Solicitation number
FA461023Q0036
Issued by

About this file

This spreadsheet outlines a schedule for migrating from SONET to DWDM network technologies. It lays out key activities over a five month timeframe, including establishing site priorities, designing deployment scenarios, ordering needed materials, and executing practice deployments. Participants include Ciena consultants, 30 SCS project management and central office staff. The related federal contract opportunity is a solicitation from the Air Force Space Command to conduct a SONET to DWDM migration at Vandenberg Air Force Base. It provides solicitation number FA461023Q0036 and identifies the opportunity type and procuring agency.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Schedule: SONET 2 DWDM Migration Part 1
TimeframeActivityParticipantsComments
NTP = Award
ER = Equip RcptCE = Ciena Consulting Engineer

SCXP = 30 SCS Project Management CO = 30 SCS Central Office & Cyber Transport

NTPContract Award and Notice To Proceed (NTP)n/a
NTP + 1 moDecide circuit or site approach to migrationSCXP, CO
NTP + 1 moReview and Update Part 1 ScheduleCE, SCXP, CO
NTP + 2 moID ALL Materials Req'd to complete a MigrationCE, SCXP, COBeyond equipment ordered through SONEQT to DQWDM Migration Part 1,

we're missing some things. What are they?

NTP + 2 moCreate DWDM Spur Template ConfigurationCE
NTP + 3 moEstablish Site or Circuit Priorities for Migration, Establish Top 10SCXP, CO
NTP + 3 moReview Top 10CE, SCXP, CO
NTP + 3 moDesign Practice Deployment ScenariosCE, CO
site survey ea top 10 for rack space and DC power capacity
reserve rack space
NTP + 4 moFor ea. of Top 10 Site/Circuit, Create List of Req'd MaterialsCO
NTP + 4 moFor ea. of Top 10 Site/Circuit, Determine not-already-ordered-or-on-hand MaterialsSCXP, CO
NTP + 4 moConsolidate not-on-hand Materials List for Top 10SCXP, CO
NTP + 4 moEstimate & Obtain Funds needed to Acquire Needed Materials for Top 10SCXP, CO
NTP + 5 moOrder Needed Materials for Top 10SCXP, CO
ER - 3 moExecute 1st Practice DeploymentCE, CO3 months prior to equipment receipt
ER - 2 moExecute 2nd Practice DeploymentCO2 months prior to equipment receipt
ER - 1 moExecute 3rd Practice DeploymentCO1 month prior to equipment receipt
ER - 1 moEstablish Top 10 Migration ScheduleSCXP, CO
ERReceive Needed Materials for Top 10n/aequipment received
ER + 1 moStage all Materials for ea. Top 10 Site/Circuit to be MigratedSCXP, CO
ER + 1 moBegin execution of Top 10 MigrationCO