Questions and Answers 6 July 2017

View the file

Other files for this federal contract opportunity

Other files attached to Repair Hangar Doors and Heat, newest first.
File Type Posted
Q37_&_Info.pdf PDF
Att_16_Changes.pdf PDF
Att_15_-_Asbestos_report.pdf PDF
FA4608-17-R-0017_Amd3.pdf PDF
Att_13_-_Subcontractor_Consent_Letter.pdf PDF
Att_14_-_Lead_Paint_Report.pdf PDF
Orig_Drawings.pdf PDF
Roof_Warranty_Info_.pdf PDF
Questions_4_-36__.pdf PDF
Lead_Paint_Report.pdf PDF
Asbestos_report.pdf PDF
Att_Sheet_SV2_6Jul17.pdf PDF
FA460817R0017_Amd_0002.pdf PDF
Additional_Photos.pdf PDF
Att_Sheet_Preproposal_Site_Visit.pdf PDF
FA460817R0017_Amd__1.pdf PDF
Att_5_Gas_Heat_-_Drawings.pdf PDF
Att_3_Doors_-_Specifications.pdf PDF
Att_2_Doors_-_Electrical_Drawings.pdf PDF
Att_8_-_AF66.pdf PDF
FA4608-17-R-0017.pdf PDF
Photos_Doors.pdf PDF
Att_10_Wage_Determination_LA170034_14_Apr_17.pdf PDF
Att_7_-_Environmental_Req'ts_(Jun_16).pdf PDF
Att_12_-_Past_Performance_Questionnaire.pdf PDF
Att_11___-_PPQ_Cover_Letter.pdf PDF
Att_1_Doors_-_Drawings.pdf PDF
Att_9_Insurance_Form.pdf PDF
Att_4_Gas_Heat_-_Specifications.pdf PDF
Att_6_ADDITIONAL_SOW_INFO.pdf PDF
Att_Sheet_Preproposal_Site_Visit.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4608-17-R-0017 Repair Hangar 1 Doors and Heat

Questions and Answers

Q1. The solicitation indicates an offer guarantee is not required. Can you please confirm?

A1. The offer guarantee has been waived by the contracting officer however, we do ask that the proposal be valid for 180 calendar days.

Q2. When obtaining a view of the pipe per the camera and encounter a collapsed pipe, which will be an unseen scope of work, will this be a mod to the contract or how will this be handled in regards to repair of the area or areas of collapse?

A2. A determination will be made at that time, depending on size, magnitude of issues and funding available. The Contractor will not be liable for repairing the issue under the existing contract unless they were somehow responsible for causing the obstruction.

Q3. For Spec Section 084500 - Translucent Fiberglass Sandwich Panels, there are two manufacturers listed, Kalwall and CPI. In Paragraph 2.2. it states, "Thermoplastics (eg.

Polycarbonate, acrylic) faces are not acceptable."

Kalwall uses only fiberglass but CPI only uses polycarbonate. The spec is copied directly from Kalwall so it includes language to attempt eliminating competition. Is it your intent to not allow CPI or other translucent manufacturers using polycarbonate to bid?

A3. There are actually 3 vendors listed in the specifications and are as follows:

1. Kalwall Corporation, Tel: (800) 258-9777 - Fax: (603) 627-7905 - Email: info@kalwall.com

2. Muhler, Tel: (843) 572-9727

3. CPI Daylighting, Inc, Tel: (800) 759-6985 - Fax: (847) 816-0425 - Email: info@cpidaylighting.com

Our intent is not to specifically exclude anyone, but product must meet the specifications as published.