Question_and_Answer_1.pdf

PDF 9 KB Posted

Attached to
Grounds Maintenance Federal contract opportunity
Solicitation number
FA4484-13-R-0003
Issued by
Department of the Air Force Air Mobility Command

About this file

Question and Answer 1 13 Feb 2013

View the file

Other files for this federal contract opportunity

Other files attached to Grounds Maintenance, newest first.
File Type Posted
Solicitation_FA4484-13-R-0003_amend_4.pdf PDF
TE-4.pdf PDF
GROUNDS_MAINTENANCE_(AF)_PWS_(JOINT_BASE)_REV_5__21_FEB_13.pdf PDF
TE-1.pdf PDF
Question_and_Answer_2.pdf PDF
Solicitation_FA4484-13-R-0003_amend_3.pdf PDF
Solicitation_FA4484-13-R-0003_amend_2.pdf PDF
GROUNDS_MAINTENANCE_(AF)_PWS_(JOINT_BASE)_REV_4__8_FEB_13.pdf PDF
Solicitation_FA4484-13-R-0003_Conformed_Copy.pdf PDF
Question_and_Answer.pdf PDF
Site_Visit_FA4484-13-R-0003.pdf PDF
FA4484-13-R-0003-0001.pdf PDF
Past_Perf_Questionnaire.doc DOC document
TE-10.pdf PDF
TE-5.pdf PDF
TE-9.pdf PDF
TE-3.pptx PPTX presentation
Executive_summary_sheet.pdf PDF
Past_Pef_Cover_Letter.pdf PDF
TE-1.pdf PDF
GROUNDS_MAINTENANCE_(AF)_PWS_(JOINT_BASE)_REV_3__7_DEC_12.pdf PDF
Burlington_County_Wage_Determination_Rev_12_-_13_Jun_2012.pdf PDF
TE-2.pptx PPTX presentation
GROUNDS_MAINTENANCE_(AF)_QASP_(JOINT_BASE)_REV_2__14_AUG_12.pdf PDF
Solicitation_FA4484-13-R-0003.pdf PDF
Ocean_County__WAGE_DETERMINATIONS_6-2012.pdf PDF
TE-7.pdf PDF
TE-11.pdf PDF
TE-13.doc DOC document
TE-6.ppt PPT presentation
TE-12.pptx PPTX presentation
TE-14.pdf PDF
TE4.doc DOC document
TE-8.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JB MDL Grounds Maintenance Solicitation

FA4484-13-R-0003

Questions and Answers

13 February 2013

1. Question: Could you please advise as to which CLIN we are to price the following? We see it referenced in the PWS Workload Estimates as item 1.1.12 and in the PWS as 1.1.11. Also, we do not see it referenced in the Price Schedule in the SF1449?

Answer: The workload estimate should reference 1.1.11 not 1.1.12. The offeror is responsible for determining where to allocate the cost.