Attch 8 Technical Evaluation Project.pdf
PDF 45 KB Posted
- Attached to
- Roofing IDIQ - Hurlburt Field, FL Federal contract opportunity
- Solicitation number
- FA4417-10-R-0012
About this file
Roof IDIQ FA4417-10-R-0012 Technical Evaluation Project SOW
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4417-10-R-0012, Attachment 8 HURLBURT FIELD ROOF IDIQ 31 March 2010 Roof IDIQ Evaluation Building 90326 STATEMENT OF WORK
PART 1 GENERAL
1.01 WORK INCLUDED
1. The contractor shall furnish all labor, materials, tools, supervision and equipment and perform all operations necessary to accomplish all work complete in place, as shown on the contract drawings, specified herein, or as needed to replace the built up roof system of building 90326.The work shall be fully complete in accordance with the Contract Documents. The project is located on Hurlburt Field, FL.
1.02 RELATED CONTRACT DOCUMENT
1. Roofing IDIQ Specifications.
1.03 WORK DESCRIPTION
1. The work to be performed includes, but is not necessarily limited to, the following principal features:
A. Tear off built up roof system.
B. Haul away and dispose of built up roof system and insulation down to the wooden deck to include all curbing, pitch pans and equipment curbs.
C. Tear off and replace standing seam metal roof systems that are located anywhere on building 90326 and particularly above entry ways.
D. Install new built up roof system in accordance with IDIQ and Hurlburt Field specifications to include but not limited to insulation, curbs, pitch pans and drains and/or diverters as necessary.
E. Period of Performance – 159 calendar days F. Liquidated Damages Amount Per Day: Reserved
1.04 SUBMITTALS
1. The Specifications are the governing document in determining the required submittal items.
1.05 CONTRACTOR USE OF SITE AND PREMISES
1. The construction site shall be kept neat and orderly at all times. The contractor shall remove debris from the site on a daily basis.
1.06 DISPOSAL
1. All demolition materials and debris shall be loaded onto trucks immediately for removal from site as required. It shall be the responsibility of the contractor to provide the trucks and for the selection of the dumpsite. Provide Contracting Officer with name of approved dumpsite, if requested.
1.07 STORAGE AREA
1. Storage area or areas will be coordinated at the Pre-Construction conference.
2. The Contractor is solely responsible for the security of materials located within the storage area.
1.08 SAFETY
1. The pertinent sections of the following publications are applicable to all work on this project.
A. U.S. Army Corps of Engineers: EM 385-1-1, Safety and Health Requirements Manual.
B. Air Force Instruction (AFI) 91-301.
2. The Contractor shall safety barricade as necessary all excavations and hazards.
1.09 HAUL ROUTE
1. The Contractor shall utilize the most direct route to the delivery point.
1.010 PERMITS
1. AF Form 103, Civil Engineering Work Clearance Request
2. ERP 62-346, Environmental Resource Permit if project does not meet exemption criteria.
1.011 PHASING AND TRAFFIC CONTROL
1. The Contractor shall work continuously and sequentially on this project.
2. The Contractor will submit a proposed project schedule for approval within 5 calendar days of the Notice to Proceed.
PART 2 PRODUCTS
2.01 ACCEPTABLE MATERIALS
1. Contractor shall refer to the IDIQ specifications for guidance in selecting appropriate materials to accomplish the work.
2.02 ALTERNATIVE MATERIALS
1. If Contractor suggests the use of a specific material not listed in the specifications, which the Government might consider to lessen the cost or increase the utility or appearance of the facility, the contractor may submit that material listed as a substitution for the Government to evaluate.
FA4417-10-R-0012, Attachment 8 HURLBURT FIELD ROOF IDIQ 31 March 2010 Roof IDIQ Evaluation Building 90326 STATEMENT OF WORK
PART 3 EXECUTION
3.01 INSPECTION
1. The contractor shall make a representative available to the Government on site to answer questions, which may arise.
2. The Government representatives will be allowed free access to the site in its entirety.
3.02 HOURS OF WORK
1. The normal hours of a workday shall be between 8:00 A.M. and 4:00 P.M., Monday through Friday, except holidays. The contractor may elect, at his option, to work hours other than normal duty hours if approved by the Contracting Officer. All work time, other than normal working days, shall be requested in writing, 3 days in advance.
3.03 PHOTOGRAPHS
1. Photographs are not required to be submitted but are highly recommended.
3.04 QUALITY CONTROL
1. The contractor shall establish and maintain quality control to assure compliance with Contract
Documents, and provide records of his quality control for materials, equipment and construction operations.
2. The Contractor is solely responsible for quality control on this project. A quality control representative will be appointed by the Contractor and will be on-site daily to assure the work accomplished meets the specifications.
3.05 AS-BUILT DRAWINGS
1. Prior to final inspection the contractor shall:
A. Submit original record drawings to Contracting Officer. Contractor is advised to have a reproduced copy of the original record drawings made for their records.
B. Obtain Disc copies of the contract drawings in AUTOCAD 2004 format. Correct drawing files (sheets) to reflect all as-built conditions based on the changes made as per item C. above. Add the words “AS BUILT” to the revision block of each sheet title block, the date the drawings were changed and the initials of the person making the change.
C. Submit one set of full-size prints of the corrected contract drawing files to allow Base Civil engineer to verify accuracy of the corrected drawings against the record documents.
D. Upon review and approval of the corrected contract drawing files, provide disc copies to the government for their records.
END OF DELIVERY ORDER