Roofing IDC Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4416-08-R-0008-P0002.doc | DOC document | |
| Attachment 7 -Roof IDC Schedule of Material Submittals.xls | XLS spreadsheet | |
| Attachment 4a - Updated WD No MD080057 Construction type Building Prince George's County.doc | DOC document | |
| FA4416-08-R-0008-P0001.doc | DOC document | |
| Attachment 2 - Pricing Schedule B.xls | XLS spreadsheet | |
| Attachment 5 - WD No MD080021 Construction Type Building Anne Arundel County.doc | DOC document | |
| Attachment 2 - Pricing Schedule B.xls | XLS spreadsheet | |
| Attachment 6 - Visitor Information.doc | DOC document | |
| Attachment 3 - Past Performance Questionnaire.doc | DOC document | |
| Attachment 4 - WD No MD080057 Construction type Building Prince George's County.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 9,999 |
| Each |
Base Year
FFP
Roofing
Project Name: Roofing IDC
Project Number: AJXF 08-1552
The contractor will provide all plant, labor, supervision, equipment, materials, transportation and perform all operations required to repair and replace various roofing systems to include, but not limited to, Built-Up Roofing (BURS), Standing Seam Metal Roofing (SSMR), Strip Shingles Roofing (SSR), and Modified Bitumen Sheet Roofing (MBSR).
THE CONTRACTOR SHALL INSERT PRICES ON SECTION B PRICING SCHEDULE, SECTION J, ATTACHMENT 2. The contractor will provide the following according to the Statement Of Work and specifications located in Section J, Attachment 1: Roofing IDC.
The intended award will be an indefinite delivery requirements contract with specifics to be provided in each Delivery Order.
FOB: Destination
SIGNAL CODE: A
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 9,999 |
| Each |
| OPTION |
| Option Year 1 |
FFP
Roofing
Project Name: Roofing IDC
Project Number: AJXF 08-1552
The contractor will provide all plant, labor, supervision, equipment, materials, transportation and perform all operations required to repair, replace, and/or construct various roofing systems to include, but not limited to, Built-Up Roofing (BURS), Standing Seam Metal Roofing (SSMR), Strip Shingles Roofing (SSR), and Modified Bitumen Sheet Roofing (MBSR).
THE CONTRACTOR SHALL INSERT PRICES ON SECTION B PRICING SCHEDULE, SECTION J, ATTACHMENT 2. The contractor will provide the following according to the Statement Of Work and specifications located in Section J, Attachment 1: Roofing IDC.
The intended award will be an indefinite delivery requirements contract with specifics to be provided in each Delivery Order.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 9,999 |
| Each |
| OPTION |
| Option Year 2 |
FFP
Roofing
Project Name: Roofing IDC
Project Number: AJXF 08-1552
The contractor will provide all plant, labor, supervision, equipment, materials, transportation and perform all operations required to repair, replace, and/or construct various roofing systems to include, but not limited to, Built-Up Roofing (BURS), Standing Seam Metal Roofing (SSMR), Strip Shingles Roofing (SSR), and Modified Bitumen Sheet Roofing (MBSR).
THE CONTRACTOR SHALL INSERT PRICES ON SECTION B PRICING SCHEDULE, SECTION J, ATTACHMENT 2. The contractor will provide the following according to the Statement Of Work and specifications located in Section J, Attachment 1: Roofing IDC.
The intended award will be an indefinite delivery requirements contract with specifics to be provided in each Delivery Order.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 9,999 |
| Each |
| OPTION |
| Option Year 3 |
FFP
Roofing
Project Name: Roofing IDC
Project Number: AJXF 08-1552
The contractor will provide all plant, labor, supervision, equipment, materials, transportation and perform all operations required to repair, replace, and/or construct various roofing systems to include, but not limited to, Built-Up Roofing (BURS), Standing Seam Metal Roofing (SSMR), Strip Shingles Roofing (SSR), and Modified Bitumen Sheet Roofing (MBSR).
THE CONTRACTOR SHALL INSERT PRICES ON SECTION B PRICING SCHEDULE, SECTION J, ATTACHMENT 2. The contractor will provide the following according to the Statement Of Work and specifications located in Section J, Attachment 1: Roofing IDC.
The intended award will be an indefinite delivery requirements contract with specifics to be provided in each Delivery Order.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 9,999 |
| Each |
| OPTION |
| Option Year 4 |
FFP
Roofing
Project Name: Roofing IDC
Project Number: AJXF 08-1552
The contractor will provide all plant, labor, supervision, equipment, materials, transportation and perform all operations required to repair, replace, and/or construct various roofing systems to include, but not limited to, Built-Up Roofing (BURS), Standing Seam Metal Roofing (SSMR), Strip Shingles Roofing (SSR), and Modified Bitumen Sheet Roofing (MBSR).
THE CONTRACTOR SHALL INSERT PRICES ON SECTION B PRICING SCHEDULE, SECTION J, ATTACHMENT 2. The contractor will provide the following according to the Statement Of Work and specifications located in Section J, Attachment 1: Roofing IDC.
The intended award will be an indefinite delivery requirements contract with specifics to be provided in each Delivery Order.
NET AMT
PRICE PROPOSAL TOTAL
Total Amount (Base year plus the four (4) Option Years) $_________________________
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| Destination |
| Government |
| Destination |
| Government |
| 1001 |
| Destination |
| Government |
| Destination |
| Government |
| 2001 |
| Destination |
| Government |
| Destination |
| Government |
| 3001 |
| Destination |
| Government |
| Destination |
| Government |
| 4001 |
| Destination |
| Government |
| Destination |
| Government |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| UIC |
| 0001 |
| 365 dys. ADC |
| 9,999 |
| 316TH CIVIL ENGINEERING SQUADRON |
CHARLOTTE ARMSTRONG
316 CES/CEC
3710 FETCHET AVENUE
ANDREWS AFB MD 20743-4803
301-981-1198
F1D326
| 1001 |
| 365 dys. ADC |
| 9,999 |
| (SAME AS PREVIOUS LOCATION) |
F1D326
| 2001 |
| 365 dys. ADC |
| 9,999 |
| (SAME AS PREVIOUS LOCATION) |
F1D326
| 3001 |
| 365 dys. ADC |
| 9,999 |
| (SAME AS PREVIOUS LOCATION) |
F1D326
| 4001 |
| 365 dys. ADC |
| 9,999 |
| (SAME AS PREVIOUS LOCATION) |
F1D326
Section G - Contract Administration Data
THE SCHEDULE
Part 1 The Schedule
PART 1 – THE SCHEDULE
SECTION G
CONTRACT ADMINISTRATION
SECTION G
ACCOUNTING AND APPROPRIATION DATA
Accounting and Appropriation data will be cited on each individual delivery order issued under the contract.
Section H - Special Contract Requirements
SPECIAL CONTRACT REQUIREMENTS
INSURANCE
H-109
REQUIRED INSURANCE
(IAW FAR 28.306(b)
Reference FAR Clause entitled “Insurance” … the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
(a) Workers’ compensation and employer’s liability. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers. (See 28.305(c) for treatment of contracts subject to the Defense Base Act.)
(b) General liability.
(1) The contracting officer shall require bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.
(2) Property damage liability insurance shall be required only in special circumstances as determined by the agency.
(c) Automobile liability. The contracting officer shall require automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
H-1000
PROGRESS SCHEDULES FOR DELIVERY ORDERS
For Delivery Orders with performance periods of 60 calendar days or longer, contractor shall be required to provide a progress schedule and progress reports as specified in each Delivery Order.
H-1001
PERFORMANCE PERIOD FOR INDIVIDUAL DELIVERY ORDERS
The performance period for Individual Delivery Orders will be estimated by Government and negotiated with the contractor before issuance of the delivery order.
EXCLUSION OF PAYMENT FOR MATERIALS STORED ON SITE
Payment for materials stored on site, in advance of installation, will not be considered under this contract.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
| 52.202-1 |
| Definitions |
| JUL 2004 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| APR 1984 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| SEP 2006 |
| 52.203-7 |
| Anti-Kickback Procedures |
| JUL 1995 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| JAN 1997 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| JAN 1997 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| SEP 2007 |
| 52.204-4 |
| Printed or Copied Double-Sided on Recycled Paper |
| AUG 2000 |
| 52.204-7 |
| Central Contractor Registration |
| JUL 2006 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| SEP 2006 |
| 52.211-13 |
| Time Extensions |
| SEP 2000 |
| 52.211-18 |
| Variation in Estimated Quantity |
| APR 1984 |
| 52.215-2 |
| Audit and Records--Negotiation |
| JUN 1999 |
| 52.215-8 |
| Order of Precedence--Uniform Contract Format |
| OCT 1997 |
| 52.219-3 |
| Notice of Total HUBZone Set-Aide |
| JAN 1999 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| MAY 2004 |
| 52.219-9 |
| Small Business Subcontracting Plan |
| NOV 2007 |
| 52.219-14 |
| Limitations On Subcontracting |
| DEC 1996 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards Act - Overtime Compensation |
| JUL 2005 |
| 52.222-6 |
| Davis Bacon Act |
| JUL 2005 |
| 52.222-7 |
| Withholding of Funds |
| FEB 1988 |
| 52.222-8 |
| Payrolls and Basic Records |
| FEB 1988 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| JUL 2005 |
| 52.222-12 |
| Contract Termination-Debarment |
| FEB 1988 |
| 52.222-13 |
| Compliance with Davis-Bacon and Related Act Regulations. |
| FEB 1988 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| FEB 1988 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| FEB 1999 |
| 52.222-23 |
| Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction |
| FEB 1999 |
| 52.222-26 |
| Equal Opportunity |
| MAR 2007 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| FEB 1999 |
| 52.222-30 |
| Davis-Bacon Act--Price Adjustment (None or Separately Specified Method) |
| DEC 2001 |
| 52.222-35 |
| Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans |
| SEP 2006 |
| 52.222-36 |
| Affirmative Action For Workers With Disabilities |
| JUN 1998 |
| 52.222-37 |
| Employment Reports On Special Disabled Veterans, Veterans Of The Vietnam Era, and Other Eligible Veterans |
| SEP 2006 |
| 52.222-50 |
| Combating Trafficking in Persons |
| AUG 2007 |
| 52.223-3 |
| Hazardous Material Identification And Material Safety Data |
| JAN 1997 |
| 52.223-4 |
| Recovered Material Certification |
| OCT 1997 |
| 52.223-5 |
| Pollution Prevention and Right-to-Know Information |
| AUG 2003 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-14 |
| Toxic Chemical Release Reporting |
| AUG 2003 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| FEB 2006 |
| 52.227-1 |
| Authorization and Consent |
| DEC 2007 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| DEC 2007 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-1 |
| Bid Guarantee |
| SEP 1996 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.228-11 |
| Pledges Of Assets |
| FEB 1992 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| OCT 1995 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| DEC 1999 |
| 52.228-15 |
| Performance and Payment Bonds--Construction |
| NOV 2006 |
| 52.229-3 |
| Federal, State And Local Taxes |
| APR 2003 |
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| SEP 2002 |
| 52.232-23 |
| Assignment Of Claims |
| JAN 1986 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| SEP 2005 |
| 52.233-1 |
| Disputes |
| JUL 2002 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-21 |
| Specifications and Drawings for Construction |
| FEB 1997 |
| 52.236-21 Alt I |
| Specifications and Drawings for Construction (Feb 1997) - Alternate I |
| APR 1984 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.236-28 |
| Preparation of Proposals--Construction |
| OCT 1997 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.244-5 |
| Competition In Subcontracting |
| DEC 1996 |
| 52.246-21 |
| Warranty of Construction |
| MAR 1994 |
| 52.249-2 |
| Termination For Convenience Of The Government (Fixed-Price) |
| MAY 2004 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (May 2004) - Alternate I |
| SEP 1996 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2004 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7004 Alt A |
| Central Contractor Registration (52.204-7) Alternate A |
| SEP 2007 |
| 252.205-7000 |
| Provision Of Information To Cooperative Agreement Holders |
| DEC 1991 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country |
| DEC 2006 |
| 252.223-7006 |
| Prohibition On Storage And Disposal Of Toxic And Hazardous Materials |
| APR 1993 |
| 252.225-7005 |
| Identification Of Expenditures In The United States |
| JUN 2005 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| MAR 2008 |
| 252.225-7031 |
| Secondary Arab Boycott Of Israel |
| JUN 2005 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| MAR 2008 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.236-7001 |
| Contract Drawings, and Specifications |
| AUG 2000 |
| 252.236-7008 |
| Contract Prices-Bidding Schedules |
| DEC 1991 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| MAR 1998 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| MAY 2002 |
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than as cited on each delivery order. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $129.82 and $150.12 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price Indefinite Delivery Requirements Contract resulting from this solicitation.
(End of provision)
52.216-18 Ordering. (OCT 1995)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from the tentative dates below. Dates are subject to change depending upon the award date of the contract:
27 June 2008 - 26 June 2009 -- Base Year
27 June 2009 - 26 June 2010 -- Option Year I
27 June 2010 - 26 June 2011 -- Option Year II
27 June 2011 - 26 June 2012 -- Option Year III
27 June 2012 - 26 June 2013 -- Option Year IV
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.
(End of clause)
52.216-19 Order Limitations. (OCT 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,000.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor:
(1) Any order for a single item in excess of $1,000,000.00;
(2) Any order for a combination of items in excess of $2,000,000.00; or
(3) A series of orders from the same ordering office within three (3) days that together call for quantities exceeding the limitation in subparagraph (1) or (2) above.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) above.
(d) Notwithstanding paragraphs (b) and (c) above, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within three (3) days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of clause)
52.216-21 REQUIREMENTS (OCT 1995)
(a) This is a requirements contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government's requirements do not result in orders in the quantities described as "estimated'' or "maximum" in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(c) Except as this contract otherwise provides, the Government shall order from the Contractor all the supplies or services specified in the Schedule that are required to be purchased by the Government activity or activities specified in the Schedule.
(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.
(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing for the accelerated delivery, the Government may acquire the urgently required goods or services from another source.
(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after completion of delivery orders issued during the contract period.
(End of clause)
In accordance with 52.216-21, paragraph C, the Government reserves the right to exclude the following work from this contract:
(1) Any roof work provided in other contracts where the repair work is incidental to other replacement, repair, or construction work.
(2) Any roof repair work or service obtained for any organization other than the 316th Air Wing.
(3) Any roof repair work performed by Government employees (Appropriated and/or Non-appropriated).
(4) Any roof repair work performed in military family housing areas or using military housing funds.
(5) Any roof repair work covered within the existing family housing.
(6) Any roor repair work done by other roofing contractors performing under existing warranty periods.
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 10 days prior to contract expiration.
(End of clause)
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 15 days provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 66 months.
(End of clause)
52.225-11 BUY AMERICAN ACT--CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (AUG 2007)
(a) Definitions. As used in this clause--
Caribbean Basin country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement country (Aruba, Austria, Belgium, Bulgaria, Canada, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, or United Kingdom);
(2) Free Trade Agreement country (Australia, Bahrain, Canada, Chile, Dominican Republic, El Salvador, Guatemala, Honduras, Mexico, Morocco, Nicaragua, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Cape Verde, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, East Timor, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Madagascar, Malawi, Maldives, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, Tanzania, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, British Virgin Islands, Costa Rica, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Netherlands Antilles, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.
Foreign construction material means a construction material other than a domestic construction material.
Least developed country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials. (1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American Act restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to the construction materials or components listed by the Government as follows: NONE
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that--
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) \1\
Item 1:
Foreign construction material
Domestic construction material
Item 2:
Foreign construction material
Domestic construction material
\1\ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from SF 1442, Block 7.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by a physical site viste and a reference to the best available existing construction drawings which are available for examination at Bldg. 3710, Andrews AFB.
(b) Weather conditions. See climactic factors, Specification section.
(c) Transportation facilities. Motor carrier services are available within the D.C. metropolitan area. The nearest freight railroad yard, in Alexandria, VA is approximately 11 miles from Andrews AFB, MD.
(d) Other pertinent information: N/A.
(End of clause)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) A site visit will be held on 12 June 2008, 10:00 A.M.. EST:
Name: Charlotte Armstrong
Address: 316 CES/CECE, Bldg 3710, Andrews AFB, MD 20762
Telephone: 301-981-1198 or DSN: 858-1198
All contractors planning to visit the site must submit, via fax at (301) 981-6776, the attached “Visitor Information” form (Attachment 6) to Ms. Charlotte Armstrong three days prior to ensure entry to the base. There will be no exceptions.
(End of provision)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.arnet.gov/ http://farsite.hill.af.mil/ (End of clause)
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
252.223-7001 HAZARD WARNING LABELS (DEC 1991)
(a) "Hazardous material," as used in this clause, is defined in the Hazardous Material Identification and Material Safety Data clause of this contract.
(b) The Contractor shall label the item package (unit container) of any hazardous material to be delivered under this contract in accordance with the Hazard Communication Standard (29 CFR 1910.1200 et seq). The Standard requires that the hazard warning label conform to the requirements of the standard unless the material is otherwise subject to the labeling requirements of one of the following statutes:
(1) Federal Insecticide, Fungicide and Rodenticide Act;
(2) Federal Food, Drug and Cosmetics Act;
(3) Consumer Product Safety Act;
(4) Federal Hazardous Substances Act; or
(5) Federal Alcohol Administration Act.
(c) The Offeror shall list which hazardous material listed in the Hazardous Material Identification and Material Safety Data clause of this contract will be labeled in accordance with one of the Acts in paragraphs (b)(1) through
(5) of this clause instead of the Hazard Communication Standard. Any hazardous material not listed will be interpreted to mean that a label is required in accordance with the Hazard Communication Standard.
MATERIAL (If None, Insert "None.")
ACT
(d) The apparently successful Offeror agrees to submit, before award, a copy of the hazard warning label for all hazardous materials not listed in paragraph (c) of this clause. The Offeror shall submit the label with the Material Safety Data Sheet being furnished under the Hazardous Material Identification and Material Safety Data clause of this contract.
(e) The Contractor shall also comply with MIL-STD-129, Marking for Shipment and Storage (including revisions adopted during the term of this contract).
(End of clause)
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title* File* Drawing No.*
* Individual drawings will be provided with each individual delivery order.
(End of clause)
5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS) (Apr 2003)
(a) Unless the requiring activity has obtained prior Senior Acquisition Official (SAO) approval, contractors may not:
(1) Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or
(2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS.
[Note: This prohibition does not apply to manufacturing.]
(b) For the purposes of Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32-7086) are Class I ODSs:
(1) Halons: 1011, 1202, 1211, 1301, and 2402;
(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and
(3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.
[NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Air Force definition of a Class I ODS.]
(c) The requiring activity has obtained SAO approval to permit the contractor to use the following Class I ODS(s):
Class I ODS/ Application or Use/Quantity (lbs.) per contract period of performance
NONE
(d) The offeror/contractor is required to notify the contracting officer if any Class I ODS that is not specifically listed above is required in the test, operation, or maintenance of any system, subsystem, item, component, or process.
(End of clause)
5352.223-9001 HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS (JUN 1997)
(a) In performing work under this contract on a Government installation, the contractor shall:
(1) Comply with the specific health and safety requirements established by this contract;
(2) Comply with the health and safety rules of the Government installation that concern related activities not directly addressed in this contract;
(3) Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(4) Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.
(c) The contracting officer may, by written order, direct Air Force Occupational Safety and Health Standards (AFOSH) and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.
(d) Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.
5352.242-9000 Contractor access to Air Force installations (Jun 2002)
(a) The contractor shall obtain base identification and vehicle passes for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or security police for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and Social Security Number to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Volume 1, The Air Force Installation Security Program, and AFI 31-501, Personnel Security Program Management, as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
(End of clause)
316 CONS-001
IAW AFDWI 90-1, The Contractor shall be required to observe quiet hours during outdoor ceremonial events. Quiet hours shall be in effect 30 minutes prior to commencement and one hour after the start of all outdoor ceremonial events.
316 CONS-004
AAFB Environmental Standards (19 Oct 2006)
Environmental Compliance. Offerors are reminded of the environmental requirements contained in the solicitation to comply with all applicable federal, state, and local environmental statutes and regulations. In addition to the scrutiny of civil environmental regluatory and enforcement agencies, environmental compliance incidental to Air Force activities or on Air Force property is subject to Air Force scrutiny. The Air Force routinely investigates environmental violations and cooperates fully with civil authorities to secure remedies and discourage future violations. Failure to comply with environmental statutes and regulations can subject the contractor to criminal and civil penalties and/or contractual sanctions including, but not limited to, termination, suspension, and debarment, and adverse past performance assessment. Contractors can obtain specific information regarding environmental compliance mandates in 316 WG/CC Memo "Andrews AFB Environmental Standards" dated 19 Oct 2006. Additional information can be obtained by contacting the base environmental flight.
316 CONS-007
PERSONNEL SECURITY REQUIREMENTS
AFI 31-501 (1 Aug 2000)
The contractor shall not employ any person for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well being or operational mission of the installation and its population, nor shall the contractor employ any person under this contract who has an outstanding criminal warrant as identified by the National Crime Information Center (NCIC). NCIC checks will verify if a person is wanted by local, state, and federal agencies. All contractor personnel must consent to NCIC background checks. Contractor personnel who do not consent to an NCIC check will be denied access to the installation. Information required to conduct an NCIC check includes: full name, driver's license number/state issued/expiration date, social security number, and date of birth of the person entering the installation and shall be submitted in conjunction with the contractor's request for vehicle passes. Completion of a successful NCIC check does not invalidate the requirement for an escort when contractor personnel are working within controlled or restricted areas.
Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Persons later found to be undocumented or illegal aliens will be remanded to the proper authorities.
The contractor shall not be entitled to any compensation for delays or expenses associated with complying with the provisions of this clause. Furthermore, nothing in this clause shall excuse the contractor from proceeding with the contract as required. The contractor shall flow this clause down to all subcontracts.
WIDE AREA WORKFLOW – RECEIPT AND ACCEPTANCE (WAWF-RA)
ELECTRONIC RECEIVING REPORT AND INVOICING INSTRUCTIONS
IN ACCORDANCE WITH DFARS 232.7002, USE OF ELECTRONIC PAYMENT REQUESTS IS MANDATORY. USE OF WAWF WILL SPEED UP YOUR PAYMENT PROCESSING TIME AND ALLOW YOU TO MONITOR YOUR PAYMENT STATUS ONLINE. THERE ARE NO CHARGES OR FEES TO USE WAWF.
Requests for payments must be submitted electronically via the Internet through the Wide Area WorkFlow – Receipt and Acceptance (WAWF-RA) system at https://wawf.eb.mil.
Questions concerning payment should be directed to the Defense Finance Accounting Services (DFAS) Limestone through the DFAS Centralized Customer Service number (800) 756-4571 (select option 2) or faxed to (866) 392-7091. Please have your order number and invoice number ready when contacting DFAS about payment status. You can also access payment information using the DFAS myInvoice web site at http://www.dod.mil/dfas/contractorpay/myinvoice.html.
THE FOLLOWING CODES WILL BE REQUIRED TO ROUTE YOUR RECEIVING REPORTS, INVOICES AND ADDITIONAL E-MAILS CORRECTLY THROUGH WAWF.
CONTRACT NUMBER:
DELIVERY ORDER NUMBER:
| TYPE OF DOCUMENT: |
| Combo |
CAGE CODE:
| ISSUE BY DODAAC: |
| FA4416 |
ADMIN DODAAC:
| INSPECT BY DODAAC: |
| F1D326 |
| SERVICE ACCEPTOR / SHIP TO: |
| F1D326 |
| LOCAL PROCESSING OFFICE: |
| F1D290 |
| PAY OFFICE DODAAC: |
| F67100 |
SEND MORE E-MAIL NOTIFICATIONS:
| CONTRACT ADMINISTRATOR: |
| ryan.battad@us.af.mil |
| CONTRACTING OFFICER: |
| eric.obergfell@us.af.mil |
ADDITIONAL NOTIFICATION:
ADDITIONAL NOTIFICATION:
ADDITIONAL NOTIFICATION:
BPN ver 05.21.2006
5352.201-9101 Ombudsman.
As prescribed in 5301-9103, insert the following clause:
OMBUDSMAN (AUG 2005)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the…