The document is a Questions and Answers file for the B3323 Fire Riser project at Goodfellow Air Force Base. Key details include a project scope to remove and replace the existing pre-action fire-riser system, with the contractor responsible for removing existing piping, pipe stands, and sensors, and installing a new pre-action valve with associated components. The project is set aside for Service Disabled Veteran Owned Small Businesses, has a budget under $25,000, and falls under NAICS code 236220.
Critical dates include Base Access Letters due by 6 March 2025 at 4:00 PM CST, a site visit on 12 March 2025 at 9:00 AM CST, and questions due by 19 March 2025 at 4:00 PM CST. The contract involves the Department of the Air Force Air Education and Training Command, with the government intending to make an award without discussions. Contractors must maintain active SAM registration, and the project requires a 1-year labor warranty and minimum 5-year parts/manufacturer warranty. No specific manufacturer preferences were indicated for the fire riser components.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers:
1. What role will the government have in the recertification of the fire alarm panel? (SOW: System will need to be recertified and fire alarm panel will need to be reset.)
(Fire Protection will need to be notified and present to re-certify the panel. This can be coordinated through 17 CES)
2. Will a government point of contact be assigned to coordinate the deactivation of the fire alarm panel?
(Yes, 17 CES will coordinate de-activation of the panel. I can be your POC Garret Emmons 654-6060.)
3. Has the supply valve for the 4” inch pipe been tested to ensure that the system can be shut down before removing the existing pre-action fire-riser valve? (SOW: Remove and dispose pre-action fire-riser valve and associated piping and stands from the Victaulic elbow to the 2” union.)
4. Is there a preferred manufacturer for the preaction valve and the sensors (if required)?(None)
5. Is Nitrogen Generator System required? (No)
6. Is a Pre-Action Panel required? (No)
7. Does the quote have to remain under $25K? (Yes)
8. I understand the manufacturer’s warranty however, can you please clarify the warranty period for labor? (SOW 1.12: Warranty shall be 1 year labor and minimum 5 year warranty for parts/manufacturer, if we have an issue with the system as a result of the contractor’s work, we will ask the contractor to come back out and fix the issue if it occurs within one year of completing the contract. Standard warranty that we put in almost every SOW.)
9. Is there an action fire-riser located on the exterior of the building or is the fire-riser located in the Mech Rm 131 as specified on document; B3323 Floor Plans? (No exterior fire riser but entrance to the mechanical room 131 is exterior)
10. I revied the SOW and TE-1. Does the government have a preferred manufacturer?
(None)