Attachment 10 03CS-3-CS-3 - General Notes, Staging, Coordination and Safety
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA303018B00010005.pdf | ||
| 02CS-2-CS-2_09Mar18.pdf | ||
| 05C-2-C-2_09Mar18.pdf | ||
| Memo_for_Record_Site_Visit_Notes.pdf | ||
| GAFB_Sanitary_Sewerage_System_drawing.pdf | ||
| 18B0001-0004.pdf | ||
| FA303018B0001-0003.pdf | ||
| 08C-5-C-2 - Survey Benchmarks.pdf | ||
| 05C-2-C-2 - Plan Sheet.pdf | ||
| 02CS-2-CS-2 - Abbreviations, Notes and Localized Site Plan.pdf | ||
| 06C-3-C-3 - Base Utilities.pdf | ||
| 01CS-1-CS-1 - Cover Sheet.pdf | ||
| 04C-1-C-1 - Plan Sheet.pdf | ||
| FA303018B0001- Amendment 0002.pdf | ||
| 07C-4-C-2 - Construction Sewer Man Hole Details.pdf | ||
| Amendment_0001.pdf | ||
| Repair_Sanitary_Sewer_Outfall_AF_Form_66.pdf | ||
| B700_-_B900_Drawing_2.pdf | ||
| Repair_Sanitary_Sewer_SOW_27Oct17.pdf | ||
| B100_-B500_Drawing_1.pdf | ||
| FA303018B0001.pdf | ||
| BAL_Request.pdf | ||
| Heavy_Highway_TX180007.pdf | ||
| Insurance_Requirements.pdf | ||
| SOW_Attachments_A_and_B_Occupants.pdf |
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
READY WILLING ABLE
17th
CIVIL ENGINEER SQUADRON
AutoCAD SHX Text Symbol
AutoCAD SHX Text Description
AutoCAD SHX Text Date
AutoCAD SHX Text Appr
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text Symbol
AutoCAD SHX Text Description
AutoCAD SHX Text Date
AutoCAD SHX Text Appr
AutoCAD SHX Text A-E Seal:
AutoCAD SHX Text A. GENERAL NOTES 1A. CONSTRUCTION ACCESS TO THE SITE SHALL BE THROUGH THE EXISTING GATE LOCATED ON SOUTH CHADBOURNE STREET. ALL CONSTRUCTION TRAFFIC ENTERING THE BASE IS REQUIRED TO PASS THROUGH THE COMMERCIAL VEHICLE SEARCH AREA LOCATED TO THE EAST OF KEARNEY BOULEVARD. HOURS OF OPERATION ARE FROM 6:00 A.M. TO 6:00 P.M. MONDAY THROUGH FRIDAY. 2A. CONTRACTORS SHALL KEEP ALL PUBLIC ROADS AND STREETS CLEAN OF CONSTRUCTION DEBRIS, MUD, ETC. AT ALL TIMES. CONTRACTOR SHALL PROVIDE EQUIPMENT AND PERSONNEL TO CLEAN ANY STREETS AS REQUESTED BY 17CES. CONTRACTOR IS RESPONSIBLE FOR ALL REPAIRS TO STREETS, PARKING AREAS AND BASE OR GOVERNMENT PROPERTY DAMAGED FROM THEIR CONSTRUCTION ACTIVITIES. 3A. AREAS DAMAGED BY THE CONTRACTOR, FROM CONSTRUCTION ACTIVITIES SHALL BE RESTORED TO IT'S ORIGINAL OR BETTER CONDITION. THIS SHALL INCLUDE BUT IS NOT LIMITED TO LANDSCAPE, TURFING, UTILITIES, AND PAVEMENTS. 4A. CONTRACTORS SHALL MAINTAIN A CONSTRUCTION SITE NEAT AND CLEAN OF DEBRIS AS DIRECTED BY CONTRACTING OFFICER. CONTRACTOR WASTE DUMPSTERS SHALL BE EMPTIED ON A REGULAR BASIS. 5A. PEDESTRIAN AND VEHICULAR ACCESS TO ALL BUILDINGS MUST BE MAINTAINED AT ALL TIMES. 6A. CONTRACTOR SHALL FIELD VERIFY; ALL DIMENSIONS ARE APPROXIMATE AND SHALL BE VERIFIED ON SITE. B. STAGING NOTES 1B. CONTRACTOR SHALL INSTALL AND MAINTAIN A TEMPORARY CONSTRUCTION CHAIN LINK FENCE, 6 CONTRACTOR SHALL INSTALL AND MAINTAIN A TEMPORARY CONSTRUCTION CHAIN LINK FENCE, 6 FEET HIGH, AROUND THE LIMITS OF WORK NOT INCLUDING THE CONSTRUCTION ACCESS ROAD. COORDINATE CHAIN AND PADLOCKS ON GATES WITH GOODFELLOW FIRE DEPARTMENT. EACH GATE SHALL BE NUMBERED FOR EMERGENCY ACCESS, SHALL HAVE ENTRY/EGRESS SIGNAGE AND AREA LIGHTING. CONTRACTORS SHALL MAINTAIN FIRE ACCESS THROUGH EACH INDIVIDUAL CONSTRUCTION SITE AT ALL TIMES. 2B. IF A TRUCK TRUCK WASHOUT AREA IS NEEDED IT SHALL BE CONSTRUCTED, MAINTAINED AND IF A TRUCK TRUCK WASHOUT AREA IS NEEDED IT SHALL BE CONSTRUCTED, MAINTAINED AND CLEANED IN ACCORDANCE WITH TCEQ REGULATIONS. PROVIDE DETAILS AND MAINTENANCE PLAN AS PART OF THE STORMWATER POLLUTION PREVENTION PLAN. STORMWATER PERMITS ARE REQUIRED PRIOR TO THE START OF CONSTRUCTION. 3B. ALL CONTRACTORS SHALL STOCKPILE REQUIRED MATERIALS AND EQUIPMENT WITHIN LIMITS OF ALL CONTRACTORS SHALL STOCKPILE REQUIRED MATERIALS AND EQUIPMENT WITHIN LIMITS OF RESPECTIVE PROJECT AREAS OR STAGING AREAS AS INDICATED ON THE DRAWINGS. 4B. CONTRACTOR SHALL CONNECT TO EXISTING OR NEW FIRE HYDRANTS FOR TEMPORARY CONTRACTOR SHALL CONNECT TO EXISTING OR NEW FIRE HYDRANTS FOR TEMPORARY CONSTRUCTION WATER. INSTALL QUICK DISCONNECT, BACK FLOW PREVENTER AND SHUT-OFF VALVE ON 2 1/2" HOSE CONNECTION ONLY. PRIOR TO MAKING ANY CONNECTIONS TO BASE WATER SYSTEMS, THE CONTRACTOR MUST NOTIFY AND COORDINATE WITH 17CES. A FIRE PLUG USAGE PERMIT IS REQUIRED AND USAGE SHALL BE METERED AT ALL TIMES. 5B. ALL TEMPORARY ELECTRIC POWER FACILITIES SHALL MEET OR EXCEED NESC AND NEC REQUIREMENTS AS APPLICABLE FOR PRIMARY AND SECONDARY FACILITIES. 6B THE CONTRACTOR SHALL STORE ALL FLAMMABLE MATERIALS IN A FLAMMABLE STORAGE LOCKER THE CONTRACTOR SHALL STORE ALL FLAMMABLE MATERIALS IN A FLAMMABLE STORAGE LOCKER WHICH IMUST BE LOCKED 50 FEET OR MORE AWAY FROM ANY BUILDING. C. ACCESS AND VEHICLE PARKING 1C. ACCESS TO THE PROJECT FOR ALL CONSTRUCTION PERSONNEL, VEHICLES AND EQUIPMENT IS ACCESS TO THE PROJECT FOR ALL CONSTRUCTION PERSONNEL, VEHICLES AND EQUIPMENT IS ILLUSTRATED ON THE STAGING/LAYDOWN AND ACCESS PLAN. ACCESS ROUTES MAY BE SUBJECT TO CHANGE BASED ON OPERATIONAL REQUIREMENTS. POTENTIAL SCHEDULE IMPACTS SHALL BE COORDINATED WITH 17CES. 2C. LOCATION OF ACCESS/ HAUL ROADS ARE AS INDICATED ON THE STAGING/LAYDOWN AND ACCESS LOCATION OF ACCESS/ HAUL ROADS ARE AS INDICATED ON THE STAGING/LAYDOWN AND ACCESS PLAN. 3C. ALL HAUL ROADS SHALL BE MAINTAINED SUCH THAT UNOBSTRUCTED ACCESS WILL BE PROVIDED ALL HAUL ROADS SHALL BE MAINTAINED SUCH THAT UNOBSTRUCTED ACCESS WILL BE PROVIDED AT ALL TIMES FROM THE ROAD TO THE STAGING AREA AND FROM THE STAGING AREA TO THE WORK SITE AND FACILITATE GOVERNMENT ACCESS TO THE BASE AT ALL TIMES. THE MAINTENANCE OF HAUL ROADS SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AT NO ADDITIONAL COST TO THE GOVERNMENT. THE HAUL ROAD LOCATIONS SHALL BE AS INDICATED ON THE STAGING/LAYDOWN AND ACCESS PLAN OR BY 17CES. 4C. CONTRACTOR SHALL COORDINATE ACTIVITIES THROUGHOUT THE PROJECT IN A MANNER THAT CONTRACTOR SHALL COORDINATE ACTIVITIES THROUGHOUT THE PROJECT IN A MANNER THAT ALLOWS EMERGENCY ACCESS TO ALL EXISTING ROADWAYS AT ALL TIMES WITHOUT DELAYS TO EMERGENCY VEHICLES RESPONSE TIME. 5C. ALL CONTRACTOR VEHICLES AND PERSONNEL MAY BE SEARCHED BY SECURITY FORCES WHEN ALL CONTRACTOR VEHICLES AND PERSONNEL MAY BE SEARCHED BY SECURITY FORCES WHEN ENTERING THE BASE AND MAY EXPERIENCE DELAYS. ALL CONTRACTOR VEHICLES AND PERSONNEL MAY BE SEARCHED BY SECURITY FORCES DURING THEIR STAY ON BASE. ALL PERSONNEL ENTERING GOODFELLOW A.F.B. MUST HAVE A VALID PHOTO ID PER BASE SECURITY REQUIREMENTS. ALL VEHICLES ENTERING THE BASE MUST HAVE CURRENT/ VALID REGISTRATION, CURRENT/ VALID INSURANCE AND CURRENT/ VALID DRIVERS LICENSE FOR THE OPERATOR. ALL DRIVERS MUST COMPLY WITH ALL GOODFELLOW AFB DRIVING REQUIREMENTS (SPEED LIMITS, SEATBELTS, ETC.) 6C. WHEN NOT ENGAGED IN CONSTRUCTION ACTIVITIES, THE CONTRACTOR'S CONSTRUCTION EQUIPMENT WHEN NOT ENGAGED IN CONSTRUCTION ACTIVITIES, THE CONTRACTOR'S CONSTRUCTION EQUIPMENT AND VEHICLES MUST BE PARKED WITHIN THE WORK AREA OR STAGING AREA. 7C. CONTRACTOR WHILE WITHIN GOODFELLOW AFB, SHALL COMPLY WITH ALL BASE REGULATIONS PERTAINING TO "NO FIREARMS" AND "NO ILLEGAL DRUGS" ON BASE PREMISES POLICY. D. COORDINATION AND COMMUNICATION DURING CONSTRUCTION 1D. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL CORDON OFF THE WORK AREAS AND STREET PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL CORDON OFF THE WORK AREAS AND STREET CROSSINGS BY USING APPROVED BARRICADES. E. TRAFFIC CONTROL 1E. ONLY RUBBER-TIRED VEHICLES SHALL BE ALLOWED ON EXISTING PAVEMENT THAT IS TO REMAIN. ONLY RUBBER-TIRED VEHICLES SHALL BE ALLOWED ON EXISTING PAVEMENT THAT IS TO REMAIN. 2E. ANY DAMAGE TO ROADS AND PAVEMENT DUE TO CONSTRUCTION EQUIPMENT, CONSTRUCTION ANY DAMAGE TO ROADS AND PAVEMENT DUE TO CONSTRUCTION EQUIPMENT, CONSTRUCTION TRAFFIC OR CONSTRUCTION ACTIVITY SHALL BE REPAIRED TO THEIR ORIGINAL CONDITION BY THE CONTRACTOR AT HIS/HER OWN EXPENSE . F. EQUIPMENT AND STOCKPILE HEIGHT 1F. STOCKPILE ALL CONSTRUCTION MATERIALS WITHIN STAGING AREA. MAXIMUM HEIGHT 15.00' WITH STOCKPILE ALL CONSTRUCTION MATERIALS WITHIN STAGING AREA. MAXIMUM HEIGHT 15.00' WITH 5:1 SIDE SLOPES. PROVIDE EROSION CONTROL PROTECTION AROUND THE STOCKPILE LIMITS. ANY MATERIALS THAT ARE TO BE STOCKPILED FOR USE FOR OTHER PROJECTS ON THE BASE SHALL BE COORDINATED WITH 17CES. ALL MATERIAL NOT REQUIRED SHALL BE HAULED OFF GOVERNMENT PROPERTY. G. EXCAVATION AND TRENCHES 1G. OPEN TRENCHES AND EXCAVATIONS AT THE CONSTRUCTION SITE SHALL BE PROMINENTLY MARKED OPEN TRENCHES AND EXCAVATIONS AT THE CONSTRUCTION SITE SHALL BE PROMINENTLY MARKED WITH ORANGE AND WHITE TYPE III BARRICADES AND WITH FLASHING TYPE A-LOW INTENSITY WARNING LIGHTS FROM DUSK TILL DAWN.
AutoCAD SHX Text H. OTHER SAFETY REQUIREMENTS 1H. ALL CONTRACTOR OPERATIONS SHALL BE CONDUCTED AND PERFORMED IN ACCORDANCE WITH ALL CONTRACTOR OPERATIONS SHALL BE CONDUCTED AND PERFORMED IN ACCORDANCE WITH DEPARTMENT OF LABOR, OSHA REQUIREMENTS FOUND IN 29 CFR 1910 (1910.146 AND 1910.147) AND 29 CFR 1926, AND AIR FORCE OCCUPATIONAL SAFETY & HEALTH (AFOSH) AND THE AIR FORCE INSTRUCTION (AFI) STANDARDS INCLUDING AFI 91-203, AIR FORCE CONSOLIDATED OCCUPATIONAL SAFETY INSTRUCTION. THE CONTRACTOR SHALL ALSO ENSURE THAT ALL WORK IS PERFORMED IN ACCORDANCE WITH PROJECT IDENTIFIED NATIONAL STANDARDS, MILITARY MANUALS, INSTRUCTIONS, PAMPHLETS, STANDARDS, AND HANDBOOKS, AND WITHIN THE EDITIONS IN EFFECT ON THE DATE OF THIS SOLICITATION OF THE CORPS OF ENGINEERS (CoE) SAFETY MANUAL 285-1-1. ALL JOB SITES ARE SUBJECT TO INSPECTIONS BY THE DEPARTMENT OF LABOR. IN THE EVENT OF CONFLICTS BETWEEN THE OSHA STANDARDS AND THESE REQUIREMENTS, THE MOST STRINGENT SHALL APPLY. 2H. CONTRACTOR SHALL MAINTAIN SAFETY PRACTICES THAT CONFORM TO OCCUPATIONAL SAFETY AND CONTRACTOR SHALL MAINTAIN SAFETY PRACTICES THAT CONFORM TO OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) REGULATIONS. 3H. CONTRACTOR SHALL MAINTAIN AT ALL TIMES ONE FIRE LANE FREE FROM OBSTRUCTION AND CONTRACTOR SHALL MAINTAIN AT ALL TIMES ONE FIRE LANE FREE FROM OBSTRUCTION AND MAINTAIN ACCESS TO THE SITE AND ALL SURROUNDING ROADS AND STREETS. I. CONTRACTOR SAFETY PLAN SUBMITTALS CONTRACTOR SAFETY PLAN SUBMITTALS 1I. CONTRACTOR SHALL FURNISH A CONSTRUCTION SAFETY PLAN IN ACCORDANCE WITH THE CONTRACTOR SHALL FURNISH A CONSTRUCTION SAFETY PLAN IN ACCORDANCE WITH THE SPECIFICATIONS AS WELL AS A PROJECT SCHEDULE. THE SAFETY PLAN SHALL IDENTIFY THE FOLLOWING ITEMS: A. PROPOSED ACCESS POINTS, STAGING AREA AND HAUL ROUTES. B. TEMPORARY MARKINGS TO BE USED, IF ANY. C. LOCATIONS AND TYPE OF BARRICADES OR OTHER TRAFFIC CONTROL DEVICES. D. METHODS BY WHICH THE CONTRACTOR WILL COMMUNICATE WITH 17CES. E. PROCEDURES AND POLICES FOR EMERGENCIES AND ACCIDENTS. J. MAINTENANCE OF STORAGE AREA MAINTENANCE OF STORAGE AREA 1J. THE CONTRACTOR SHALL AT ALL TIMES KEEP THE CONSTRUCTION SITE, CONSTRUCTION THE CONTRACTOR SHALL AT ALL TIMES KEEP THE CONSTRUCTION SITE, CONSTRUCTION TRAILER(S)/BUILDING(S), AND STORAGE AREA(S) IN A CLEAN, NEAT, WORKMAN LIKE CONDITION, FREE FROM ACCUMULATION OF WASTE, RUBBISH, WEEDS, OVERGROWN GRASS, OR CONSTRUCTION DEBRIS, TO THE SATISFACTION OF THE CONTRACTING OFFICER. ALL LOOSE OR LIGHT WEIGHT MATERIALS SHALL BE SECURED TO PREVENT BLOWING OR SCATTERING. THE BURNING OF TRASH OR CONSTRUCTION DEBRIS IS STRICTLY PROHIBITED ON GOODFELLOW AFB. PRIOR TO FINAL INSPECTION, THE CONTRACTOR SHALL REMOVE ALL CONSTRUCTION DEBRIS, TOOLS, EQUIPMENT, AND MATERIALS NOT THE PROPERTY OF THE GOVERNMENT. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL LEAVE THE WORK SITE AND STORAGE AREA(S) IN A CLEAN, NEAT, AND WORKMANLIKE CONDITION SATISFACTORY TO THE CONTRACTING OFFICER. REFER TO SECTION 01400 - ENVIRONMENTAL PROTECTION FOR GOODFELLOW AFB, PARAGRAPH 2.4.6, POST-CONSTRUCTION CLEANUP. 2J. THE CONTRACTOR SHALL KEEP FENCING IN A STATE OF GOOD REPAIR AND PROPER ALIGNMENT. THE CONTRACTOR SHALL KEEP FENCING IN A STATE OF GOOD REPAIR AND PROPER ALIGNMENT. GRASSED OR UNPAVED AREAS, WHICH ARE NOT ESTABLISHED ROADWAYS, WILL BE COVERED WITH A LAYER OF GRAVEL AS NECESSARY TO PREVENT RUTTING AND THE TRACKING OF MUD ONTO PAVED OR ESTABLISHED ROADWAYS, SHOULD THE CONTRACTOR ELECT TO TRAVERSE THEM WITH CONSTRUCTION EQUIPMENT OR OTHER VEHICLES; GRAVEL GRADATION WILL BE AT THE CONTRACTOR'S DISCRETION. MOW AND MAINTAIN GRASS LOCATED WITHIN THE BOUNDARIES OF THE CONSTRUCTION SITE FOR THE DURATION OF THE PROJECT. GRASS AND VEGETATION ALONG FENCES, BUILDINGS, UNDER TRAILERS, AND IN AREAS NOT ACCESSIBLE TO MOWERS WILL BE EDGED OR TRIMMED NEATLY. 3J. GRASS AND WEEDY VEGETATION WITHIN THE AREAS UTILIZED BY THE CONTRACTOR, INCLUDING WORK AREAS, ADMINISTRATIVE AREAS, AND STORAGE AREAS, SHALL BE KEPT MOWED TO CONTROL VEGETATIVE GROWTH. VEGETATION SHALL BE MOWED WHEN IT REACHES A HEIGHT OF 6 INCHES. MOWING SHALL BE TO A HEIGHT OF 3 INCHES. MOWING SHALL BE ACCOMPLISHED WITH A ROTARY MOWER THAT LEAVES THE CLIPPINGS EVENLY DISTRIBUTED ON THE SOIL SURFACE. MOWING SHALL BE ACCOMPLISHED DURING PERIODS AND IN SUCH MANNER THAT THE SOIL AND GRASS WILL NOT BE DAMAGED. TOWED OR SELF-PROPELLED RIDING MOWERS SHALL NOT BE OPERATED WITHIN 3 FEET OF TREES OR SHRUBS. AREAS ADJACENT TO TREES AND SHRUBS SHALL BE MOWED WITH HAND-PROPELLED MOWERS. 4J. EROSION CONTROL DEVICES SHALL BE USED FOR THE STAGING AREA AND ANY MATERIAL STOCK EROSION CONTROL DEVICES SHALL BE USED FOR THE STAGING AREA AND ANY MATERIAL STOCK PILES WHEN NECESSARY TO CONTROL EROSION AND STORM WATER RUNOFF IN ACCORDANCE WITH FEDERAL, STATE, AND LOCAL REGULATIONS. 5J. AREAS NOT MOWED: GOVERNMENT MAY IMMEDIATELY AFTER NOTICE TO THE CONTRACTOR AND AT AREAS NOT MOWED: GOVERNMENT MAY IMMEDIATELY AFTER NOTICE TO THE CONTRACTOR AND AT THE DISCRETION OF THE CONTRACTING OFFICER MOW THE CONTRACTOR'S AREAS AT ANY TIME THE VEGETATION HEIGHT EXCEEDS 6 INCHES.
AutoCAD SHX Text
PROJECT TITLE
AutoCAD SHX Text Project Number:
AutoCAD SHX Text Designed by: RICHARD ENRIGHT
AutoCAD SHX Text Submitted by:
AutoCAD SHX Text
GENERAL NOTES, STAGING,
AutoCAD SHX Text
SHEET TITLE
AutoCAD SHX Text
COORDINATION, AND SAFETY
AutoCAD SHX Text
SEQ.
AutoCAD SHX Text
OF
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
CS-3
AutoCAD SHX Text
AutoCAD SHX Text Date:
AutoCAD SHX Text Drawn by: SrA LETSON
AutoCAD SHX Text Reviewed by:
AutoCAD SHX Text
GOODFELLOW AIR FORCE BASE, TEXAS
AutoCAD SHX Text 17th TRAINING WING
AutoCAD SHX Text
AutoCAD SHX Text
JCGU 09-1004/1005
AutoCAD SHX Text
REPLACE BASE SANITARY SEWER SYSTEM
AutoCAD SHX Text
JCGU - 09-1004/1005
AutoCAD SHX Text
OCTOBER 23, 2017
| Sheets and Views |
| CS-3 |