Additional questions and answers regarding line items for a Superintendent and Quality Control representative.

View the file

Other files for this federal contract opportunity

Other files attached to Asbestos & Lead Based Paint Abatement ID/IQ, newest first.
File Type Posted
Amendment_2.pdf PDF
FA3020-18-R-0012_Amendment_1.pdf PDF
RFP_FA3020-18-R-0012_Asbestos_IDIQ.pdf PDF
01_-_VNVP_149202_Specifications_-_SOW.pdf PDF
02_-_Price_Exhibit_-_Blank_FINAL.xlsx XLSX spreadsheet
01_-_VNVP_149202_ACM-LBP_IDIQ_Package.pdf PDF
RFP_FA3020-18-R-0012_Asbestos_IDIQ.pdf PDF
06_-_SAFB_Form_151_-_Base_Pass.pdf PDF
04_-_Past_and_Present_Performance_Questionaire_Sheet.pdf PDF
05_-_SF_LLL.pdf PDF
07_-_SWP3_Checklist.pdf PDF
03_-_TX180326Wichita.pdf PDF
02_-_Price_Exhibit_-_Blank_FINAL.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VNVP 149202

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to address questions regarding not having a line item for a Superintendent or Quality Control Representative and information about a seed project.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Jul-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA302018R0012

X 9B. DATED (SEE ITEM 11)

07-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jul-2018

CODE

82 CONS/LGCN, TODD K. RAINES

206 J. AVE, BUILDING 1662

SHEPPARD AFB TX 76311

FA3020 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA302018R0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Questions and Answers for RFP FA3020-18-R-0012 Asbestos & Lead Based Paint Abatement IDIQ

Question 1: I don’t see a line item for QC or Superintendent. Is a QC and Superintendent needed for this job? Also, do we need to provide a price for the seed project? Please advise… Answer: There is no specific line item for a Superintendent or Quality Control representative. These positions are administrative and therefore cost for them should be captured as you deem appropriate within Other Direct Costs, Overhead, or both. Please see Section 01 30 00 (Administrative Requirements), paragraph 1.5 (Site Project Superintendent) of the Specification/Statement of Work for details on the requirement for these positions. No, a price for the seed project has not been requested for submission of a proposal.

Question 2: Normally, the seed project SOW is provided during the solicitation period and then awarded to the awardee.

Answer: The seed project SOW will only be provided to the awardee upon award of the contract to mitigate any confusion that may result otherwise. Sufficient time will be given to the awardee to prepare their proposal for the seed project.

(End of Summary of Changes)