Atch_2_-_Statement_of_Work.pdf

PDF 140 KB Posted

Attached to
Repair Building Envelope Federal contract opportunity
Solicitation number
FA2521-18-R-0018
Issued by
Department of the Air Force Space Command

About this file

RFP Attch 2 SOW 1 Page, January 2018

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATCH 9

BUILDING ENVELOPE REPAIR CONTRACT

STATEMENT OF WORK

SOW:

Provide all labor, materials, and equipment necessary to remove/replace damaged building envelope components and apertures. Provide all accessories necessary for a complete and usable paint, window, and roofing systems to include but not limited to demolition, water proofing, temporary roof repairs, wall finish repairs, masonry repairs, steel building components repairs, EIFS repairs, wall coatings, building component asbestos abatement, lead paint abatement, building component/cladding repair, window repair, window replacement, signage, testing for hazardous materials, lightning protection system repair/replacement, shingle roof repair, tile roof repair, and roof access ladder installation for a complete and usable system.

Emergency Response Requirements:

Upon notification by Contracting Officer via phone of an Emergency Incident at a 45th SW facility and declaration by Security Forces of all clear, the contractor shall report within 8 hours to the site of the incident with personnel, equipment, and materials necessary to effect repairs (temporary or permanent) as necessary to protect the effected facility from further damage from the elements. Emergency situations requiring response include one or more of the following but shall not be limited to:

1. Tornado damages facility doors, windows, roofs, associate adjacent surface, interior finish, or other building component.

2. Sink hole, subsidence, or erosion event damages facility doors, windows, roofs, associate adjacent surface, interior finish, or other building component.

3. Hurricane, tropical storm, tropical depression, or extreme weather event damages facility doors, windows, roofs, associate adjacent surface, interior finish, or other building component.

4. Security incident damages facility doors, windows, roofs, associate adjacent surface, interior finish, or other building component.

Compliance with the Emergency Response Requirements may require Contractor to do one or more of the following (but not limited to):

1. Designate primary and secondary supervisors as emergency contacts who will carry mobile phones and have the responsibility to coordinate crews, equipment, and materials.

2. Stage company owned or leased equipment and materials within close proximity to crews and PAFB and CCAFS to be available to responding crews.

3. Designate an inland location where crews and equipment can rally/stay during and until after extreme weather event all clear has been announced.