Atch_10_-_Sample_Project_SOW_and_Response_Form.pdf
PDF 219 KB Posted
- Attached to
- Repair Building Envelope Federal contract opportunity
- Solicitation number
- FA2521-18-R-0018
About this file
RFP Attch 10 Sample Project 1 Page
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA2521-18-R-0018_-04.pdf | ||
| FA2521-18-R-0018_Amendment_03.pdf | ||
| Atch_3_-_Davis_Bacon_6_Jul_18.pdf | ||
| Answers__for_18-R-0018_Solicitation_13_Jul_18.pdf | ||
| FA2521-18-R-0018-02_Update_Section_L,_Instructions.pdf | ||
| Attch_12_Question_and_Answer_Template.docx | DOCX document | |
| FA2521-18-R-0018-01.pdf | ||
| Atch_1_-_Specifications.pdf | ||
| Atch_11_-_Sample_Project_Drawings.pdf | ||
| Atch_5_-_Hazardous_Waste_Form.doc.pdf | ||
| Atch_4_-_GPP_Form.doc.pdf | ||
| Atch_2_-_Statement_of_Work.pdf | ||
| Atch_7_-_Past_Performance_Questionairre.pdf | ||
| Atch_9_-_Price_Schedule.xlsx | XLSX spreadsheet | |
| Atch_8_-_SubKtr_Consent_Letter_Template.docx | DOCX document | |
| Solicitation_FA2521-18-R-0018,_Building_Envelope_CCAFS.pdf | ||
| Atch_6_-_Badge_Request_Form.pdf | ||
| Atch_3_-_Davis_Bacon_1_Jun_18.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMPLE PROJECT
SAMPLE PROJECT STATEMENT OF WORK (SOW)
1. All work to be accomplished in accordance with contract details, specifications, and drawings, unless indicated otherwise.
2. WARRANTY AND WARRANTY SIGN: Upon completion of the project, contractor shall provide and install 1 warranty sign for each facility. Warranty sign shall include the following information:
Completion Date, Warranty Expiration Date, Warranty Number, Manufacturer and Contractor Information, Roof System
Information, Roof Type Application, Roof Area and Deck Type, and statement, “Do Not Make Repairs or Alterations to this
Roof Without Approval from the Facility Manager.”
For this Sample Project, Contractor must select the appropriate Item Number(s) for the Warranty Sign. An actual sign is not required.
3. Performance period for project will be 90-days to include 15 non-access days.
4. Provide all the equipment, labor and materials necessary to Replace Roof of SAMPLE PROJECT, CCAFS, FL as shown on
Project Drawings. Project will provide a complete usable roof system.
OFFEROR RESPONSE
i. SCHEDULE OF WORK: Prepare a schedule of work for the individual work tasks required to complete the Sample Project. Each unique work task shall be reflected in the appropriate sequence, that is, the tasks shall be presented in the order they would need to occur for satisfactory completion of the Project. In the table below, provide a task description, a task begin day, a task end day, and duration of each task. Tasks that occur concurrently will show overlap in the time period between of the begin day and end day. If contractor proposes to complete the actual construction in 53 days, the “begin day” of Task 1 will have a begin day of “1,” and the
End Day of the last task will be “53.” A narrative describing any assumptions that were made may be placed in the last column. You may insert more rows as needed.
SAMPLE PROJECT – SCHEDULE OF WORK
Task
No.
Task Description
Task
Begin
Day
Task
End
Day
Task
Duration
(Days)
Task Narrative
1 1
ii. PROPOSED LINE ITEMS: In the first column below, provide Line Item Numbers from the Price Schedule (Attachment 10), required to fulfill the work given on the SOW and Drawings of the Sample Project. In the second column provide the “Reason for
Selection of the Line Item Number” such as, the corresponding drawing flag note, SOW paragraph number, Specification reference or other reason(s) for selecting the specific line item number. A narrative describing any assumptions for each line item selection may be added in the last column. You may insert more rows as needed.
SAMPLE PROJECT - LINE ITEM NUMBERS
IDIQ Line
Item No.
Reason for Selection of Line Item No. Narrative
File details come from the government source that posted it.