Attch_13_Answers_to_Questions.pdf
PDF 26 KB Posted
- Attached to
- Demolish Heritage Launch Deactivation Delta II Complex 17 Phase 2 and Various Locations Federal contract opportunity
- Solicitation number
- FA2521-16-B-0002
About this file
Attachment 13 Answers to Questions Received 16 Sep 16 2 pages
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ANSWERS TO QUESTIONS RECEIVED
FA2521-16-B-0002
16 Sep 16
1. Other (Specify) AMIS Asbestos Data Archive List___________________________
Question: The AMIS Asbestos Data Archive lists a “flu rope gasket” located in the pump room;
where is this rope located, or has it been previously abated?
The AMIS data files indicate that the rope gaskets are located between the generator exhaust pipes and the west wall apertures.
2. Other (Specify) AMIS Asbestos Data Archive List___________________________
Question: The AMIS Report lists 500 linear feet of asbestos containing building seal; is this material located on the interior or the exterior of the facility?
The asbestos seal is in the caulking used to seal the louvers, window openings, door jambs, interior and exterior walls. Please refer to attachment “01-40906 WATER PUMP STATION #1” Sheet 102-103 Detail 6/P-1, 7/P1, 8/P1, 9/P, 8/P2, 14/P2, and 16/P.
3. RFP Section I__________ Paragraph _52.211-12________
Question: What is the amount of liquidated damages per day for this acquisition?
The Liquidated Damages are $336.18 for the first day and each day thereafter $269.10.
4. Other (Specify) Non-Access Days___________________________
Question: What is the estimated number of non-access days anticipated for the 600-day period of performance?
The period of performance is 600 including 60 non-working days.
5. Other (Specify) Existing Underground Infrastructure Asbuilts
Question: Are there existing asbuilts that show any/all existing structures/infrastructure (piping, etc…) underground that are scheduled to be demolished?
All the available as-builts have been provided.
6. Question: It was stated at the walk down that documents would be issued for the project, I.E.
As-Built Drawings, Demo Boundary Clarifications. May the question cut-off date be extended to allow for review of these documents once we receive and to ask potential questions?
Due to the need to award before the end of FY16, the cut-off date cannot be extended.
7. Question: We are interested in this project and see the Size Standard is set at $15m, but we have been unable to find the anticipated dollar size or range of the project itself? We need to understand that to be sure our bonding will work for the bid. Can you provide that for us?
The magnitude is listed in block 10 of the SF1442. It reads as follows:
"The magnitude of the requirement is between $1,000,000.00 and $5,000,000.00 (IAW FAR 36.204)"
No additional questions were received in response to the solicitation.