STATEMENT OF WORK.docx
DOCX document 18 KB Posted
- Attached to
- to Repair Fire supression system in Bldg 313 Federal contract opportunity
- Solicitation number
- FA2521-12-R-0042
About this file
ATTACHMENT 4 SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Response to Question.docx | DOCX document | |
| Amendment 0004.doc | DOC document | |
| amendment 0003.doc | DOC document | |
| Amendment 0002.doc | DOC document | |
| Conformed Amendment 0002.doc | DOC document | |
| 313 Fire Supp - Asbestos_Lead Paint survey.pdf | ||
| SIgn in Sheet.pdf | ||
| Amendment 001.doc | DOC document | |
| FA2521-12-R-0042.doc | DOC document | |
| FA2521-12-R-0042.doc | DOC document | |
| SXHT 02-1002 Repair Fire Suppression System Bldg 313 | — | |
| PERFORMANCE EVALUATION QUESTIONNAIRE.docx | DOCX document | |
| WDOL DBA FL12001 6Jul12.pdf | ||
| PEQ COVER LETTER.docx | DOCX document | |
| 100 _SXHT 02-1102 Repair FS Bldg 313_PDF Dwgs.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PROJECT SXHT02-1002, Repair Fire Suppression System, Bldg 313
The work to be performed under this project is located at Patrick Air Force Base. The contractor shall provide all labor, materials, equipment, transportation, and supervision to accomplish the following statement of work. All work shall be done in accordance with all local building codes, and the requirements contained in the J2 plans and specifications, dated June 2012.
Contractor work hours shall be 0730 to 1630, Monday through Friday, excluding federal holidays. Should it become necessary for work to be accomplished during weekends and holidays, the contractor is to provide written notification 72 hours prior to the desired days.
Scope: The work to be performed under this project consists of providing the labor, equipment and materials needed to convert the deluge fire suppression system to a wet pipe sprinkler system.
Civil: Provide water supply for sprinkler system including the fire line connection, backflow assembly location, and exterior fire department connection if required.
Fire Protection: In the high bay convert the existing deluge system into a wet pipe sprinkler system as shown on the drawings. Demolish existing deluge risers that are no longer required as indicated on the drawings. Demolish fire alarm connection including conduit, wire and pressure switches for deluge risers being removed. Connect new flow switches to the existing fire alarm control panel for deluge risers that are converted to wet pipe risers. System testing shall be per NFPA 13, NFPA 72 and UFC 3-600-01. Testing shall consist of contractor check out, preliminary test, and final acceptance testing for 100% of new devices and all system functions. Contractor shall provide a one year parts and labor warranty for the newly installed components.
Electrical: Provide power to new fire alarm equipment
All materials shall have the specifications approved prior to installation. If there is a question or concern about an item ask the project manager prior to initiating the work. Work shall be completed within 120 days after receipt of notice to proceed.