RFI_4.pdf
PDF 221 KB Posted
- Attached to
- WIRELESS ACCESS POINTS (WAPs) INSTALLATION
- Solicitation number
- F7R3046131AC01
About this file
RFI 4
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI_1 _2_-_Building_300_As_Built_(rev_1).pdf | ||
| RFI_7.pdf | ||
| Site_Visit_Minutes_-_WAP's_Installation-signed.pdf | ||
| RFI_2.pdf | ||
| RFI_1.pdf | ||
| RFI_3.pdf | ||
| RFI_6.pdf | ||
| RFI_5.pdf | ||
| J A_-_brand_name_(aruba_WAP's)-signed.pdf | ||
| FBO_doc_-_Statement_of_Work.pdf | ||
| FBO_doc_-_AT-OPSEC_REQUIREMENTS.pdf | ||
| FBO_doc_-_RFI_template.doc | DOC document | |
| FBO_doc_-_provisions_ _clauses_attachment_(services).pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
R E
Q U
E S
T O
R S
E C
T
IO
N
From:
Omegatech Communication Services
Date:
8/22/2016
To: Contracting Officer
1. Solicitation Number:
F7R3046131AC01
2. Project title:
Wireless Access Points Installation
3. Information Requested: (Include Specification Section and/or Drawing Number and Page if inquiring about a discrepancy)
In section 3.1.6. it states that
"Provisioning of the WAPs will be conducted by the 179th Communications Flight, but shall be tested and fully operational before contract is complete."
Does this mean that integration of the WAPs into Network will be done by 179th Communications Flight and that the contractor is only responsible for the hardware and hardware testing?
Attachments:
N/A
Date Response Required:
Asap
By:
Daniel Laing
Title:
Operation Manager
Requestor's FAX Number:
Requestor's Telephone Number:
561-951-2776
G O
V E
R N
M E
N T
R E
S P
O N
S E
To: Omegatech Communication Services
Date:
8/29/2016
Response:
Partially, the provisioning and integration into the network of the wireless access points will be done by the 179th, however the contractor shall be responsible for running cat 6 cable, installing the LAN drop, and supplying the patch cable from the access point to the LAN drop.
This information is a clarification of the solicitation/contract and does not change the contract terms or conditions.
This information is a proposed change to the solicitation/contract. An amendment will be issued.
Contracting Officer: