This document is an Exhibit G Bid Price Sheet for Hurricane Nicole Dune Walkover Repairs at Van Ave, which appears to be a FEMA-funded infrastructure restoration project. The bid sheet details 15 line items for a comprehensive coastal repair and reconstruction effort, including mobilization, survey, environmental compliance, traffic control, demolition, excavation, and specific construction elements such as concrete sidewalk, sheet pile installation, concrete cap and plug work, helical anchors, aluminum fencing and railing, and site restoration with Bahia sod. The project involves multiple construction and restoration tasks, with quantities specified for each item, though all current unit prices are listed as $0.00, suggesting this is a preliminary or template pricing document.

The bid price sheet indicates this is a FEMA-funded project, which implies disaster recovery and restoration funding is available for the coastal infrastructure repairs. The total project scope includes 100 cubic yards of imported beach quality fill, 32 square yards of concrete sidewalk, 38 linear feet of composite sheet pile, 44 linear feet of concrete cap, 2 concrete plugs, 4 helical anchors, 29 linear feet of aluminum fence, 65 linear feet of aluminum railing, and 60 square yards of Bahia sod restoration. While the current document shows no monetary values, it provides a detailed breakdown of the anticipated construction and restoration work required for the Hurricane Nicole damage site.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1 Exhibit G - Bid Price Sheet 25-B-104IF - REVISION 1 Hurricane Nicole Dune Walkover Repairs - Van Ave.

Contractor's Cost
ITEM No.DESCRIPTIONQUANTITYUNITPRICE / UNITPRICE
FEMA Funded
1Mobilization and Demobilization1LS$ - 0$ - 0
2Construction and As-Built Survey1LS$ - 0$ - 0
3Environmental Compliance1LS$ - 0$ - 0
4Temporary Traffic Control1LS$ - 0$ - 0
5Demolition, Hauling and Disposal1LS$ - 0$ - 0
6Excavation, Grading, and Compaction1LS$ - 0$ - 0
7Imported Beach Quality Fill100CY$ - 0$ - 0
86" Concrete Sidewalk32SY$ - 0$ - 0
9CMI UC-95 Composite Sheet Pile38LF$ - 0$ - 0
10Concrete Cap44LF$ - 0$ - 0
11Concrete Plug2EA$ - 0$ - 0
12Helical Anchors4EA$ - 0$ - 0
13Aluminum Fence29LF$ - 0$ - 0
14Aluminum Railing65LF$ - 0$ - 0
15Site Restoration Bahia Sod60SY$ - 0$ - 0
Subtotal Bid Price$ - 0
Payment and Performance Bond$ - 0
Total Bid Price (inclusive of Payment and Performance Bond)$ - 0
LS=Lump Sum; LF= Linear Foot; CY=Cubic Yard; SY= Square Yard; SF= Square Foot; EA= Each; TN=Ton