Exhibit E _ General Conditions_Breakdown.xlsx
XLSX spreadsheet 28 KB Posted
- Solicitation number
- PE-50300-RFP-2027-000000330
- Issued by
- Fulton County, Georgia
About this file
This is a Construction Overhead Cost Breakdown exhibit (Exhibit E) for a Construction Management/General Contractor (CM/GC) services project at the Georgia Institute of Technology for the Architecture West Mechanical Systems Improvement project (Project No. 0535-2025, GT Bid-Contract No. 2002-27). The spreadsheet provides a detailed line-item template for bidders to complete all applicable construction overhead costs, organized into five primary categories: Site Supervision & Management, Site Office Expense, Safety & Security, Bonds & Insurance, and Miscellaneous. The form includes 80 line items with columns for quantity, unit of measure, labor costs, material costs, subcontractor costs, and associated subtotals, with notes indicating whether certain items are included in other line items, to be provided by the architect, or marked as not applicable. Bidders are explicitly instructed that any attempts to recategorize items as "Fee," "Cost of Work," or "By Others" will result in a non-responsive proposal.
The form indicates a projected Guaranteed Maximum Price (GMP) of $46 million, with a projected fee of $1,231,000. All line items in the template currently display zero values, indicating this is a blank form awaiting completion by competing bidders. The structure requires itemized cost accounting across labor, materials, and subcontractor categories to ensure transparent and comparable overhead cost proposals from all respondents to the Construction Management solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit C _ CM_GC Fee Proposal.docx | DOCX document | |
| _2002_27_ 2025_0535 CM RFPQ R_dv2.pdf | ||
| Exhibit D _ Preconstruction Cost_Expenses Bre.xlsx | XLSX spreadsheet | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attach. B - Const. OH Cost)
| EXHIBIT E | |||||||||||||||||||||
| Fill-in all applicable costs, any attempts to recategorize any of these items as "Fee", "Cost of Work", or "By Others" will be treated as a non-responsive proposal. | |||||||||||||||||||||
| CONSTRUCTION OVERHEAD COST BREAKDOWN | |||||||||||||||||||||
| Description | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | Qty | Unit | Labor* | Mat'l** | Sub | Labor Subtotal | Mat'l Subtotal | Sub Subtotal | Total | Notes | |
| Site Supervision & Management: | |||||||||||||||||||||
| 1 | Senior Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 2 | Project Mgr. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 3 | Project Supt. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 4 | Asst. Project Supt. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 5 | Area Supt. | mos | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 6 | Secretary | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 7 | Project Engineer | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 8 | Engineer or Eng. Company | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 9 | Cost Control | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 10 | Safety Engineer | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 11 | Scheduling | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 12 | Purchasing | mos | $0 | $0 | $0 | $0 | 0 | $30,000 | |||||||||||||
| 13 | Project Accountant | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 14 | 0 | $0 | |||||||||||||||||||
| 15 | Incl. | ||||||||||||||||||||
| Subtotal | $0 | $0 | $0 | 0 | $0 | ||||||||||||||||
| $30,000 | |||||||||||||||||||||
| Site Office Expense: | |||||||||||||||||||||
| 18 | Job Office Trailer Rent | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 19 | Office Jobsite Build Out | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 20 | Office Jobsite Set-up | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 21 | Temp. Const. Trailer/Storage | ea | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 22 | Office Furniture | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 23 | Office Machines/Equip. | mos | $0 | $0 | $0 | $0 | Incl. Below | ||||||||||||||
| 24 | Copy Machines/Maintenance | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 25 | Office Supplies | mos | $0 | $0 | $0 | $0 | Incl. Above | ||||||||||||||
| 26 | Janitor/San. Supplies | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 27 | Postage & Shipping | mos | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 28 | First Aid/Med. Treat. | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 29 | Telephone System | ls | $0 | $0 | $0 | $0 | $0 | $0 | |||||||||||||
| 30 | Phone Installation | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 31 | Phone Charges | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 32 | Phone Charges-Long Dist. | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 33 | Radio Communications | ea | $0 | $0 | $0 | $0 | By Arch. | ||||||||||||||
| 34 | Radio Maintenance | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 35 | Computer-PCS | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 36 | Computers | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 37 | Software | allow | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 38 | MIS Charges | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 39 | Temp. Electric-Office | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 40 | Security-Office | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 41 | Water - Field Office | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 42 | |||||||||||||||||||||
| 43 | 0 | $0 | |||||||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Safety & Security: | |||||||||||||||||||||
| 43 | Safety Incentives | ls | $0 | $0 | $0 | $0 | |||||||||||||||
| 44 | Watchman/Guard Ser. | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 45 | Traffic Control | ls | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 46 | Safety Equipment | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 47 | Rainwear/Hardhats, etc. | ls | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 48 | Drug Testing | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 49 | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 50 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Bonds & Insurance: | |||||||||||||||||||||
| 51 | Perform. & Payment Bonds | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 52 | Workers Comp. Insurance | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 53 | Liability Insurance | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 54 | Fed. & State Unemployment | mos | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 55 | FICA | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 56 | Builders Risk Insurance | mos | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 57 | |||||||||||||||||||||
| 58 | |||||||||||||||||||||
| Subtotal | $0 | ||||||||||||||||||||
| $0 | |||||||||||||||||||||
| Miscellaneous | |||||||||||||||||||||
| 59 | Off-Site Parking | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 60 | Ceremony Expense | ls | $0 | $0 | $0 | $0 | |||||||||||||||
| 61 | Vehicle for On-Site Project Manager | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 62 | Vehicle for On-Site Superintendent | mos | $0 | $0 | $0 | $0 | |||||||||||||||
| 63 | Vehicle Repairs/Maintenance | ls | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 64 | Water - Coolers | mos | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 65 | Water Barrels | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 66 | Ice Machine | mos | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 67 | Ice and/or Cups | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 68 | Temporary Toilets Install | ea | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 69 | Temporary Toilets | mos | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 70 | Cold Weather Protection | ls | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 71 | Temp. Heat for Bldg. | ls | $0 | $0 | $0 | $0 | $0 | 0 | $0 | ||||||||||||
| 72 | Job Signs | ea | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 73 | Progress Photos | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 74 | Extra Plans & Specs. | ea | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||||
| 75 | Blueprint/Photostat. | allow | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 76 | Temp. Electric -Building | mos | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $0 | |||||||||||
| 77 | Building Permit | ls | $0 | $0 | $0 | $0 | Incl. | ||||||||||||||
| 78 | Plan Check Fees | ls | $0 | $0 | $0 | $0 | NA | ||||||||||||||
| 79 | NA | ||||||||||||||||||||
| 80 | NA | ||||||||||||||||||||
| Subtotal | $0 |
| TOTAL ALL CONSTRUCTION OVERHEAD COSTS: | $0 | ||
| 108 | Projected Fee (Based on $46 Million GMP) | ||
| $1,231,000 | |||
| 109 | Grand Total GCs & Fee | $0 | |
| ERROR:#REF! |