This is an exhibit document outlining the Expertise-Driven Project Delivery (XPD) process for the City of Seattle's Strategic Energy Management (SEM) Program consulting services contract (RFP# SCL-767054841). The XPD process consists of three primary phases: Selection Phase, Pre-Award Clarification Phase, and Post-Award Performance Metrics. During the Selection Phase, the City evaluates consultant proposals based on their ability to differentiate from competitors, identify and minimize project risks, add value to the City, demonstrate strong past performance on similar projects, and propose qualified project teams. Proposals must be brief and allow the City to make justifiable selections. Qualifications are due no later than 2:00 pm on Friday, October 2, 2026, with all questions to be submitted through the e-procurement portal at https://procurement.opengov.com/portal/seattle no later than 2:00 pm on Friday, September 4, 2026. Initial screening by the City includes review of responsiveness and responsibility, compliance with RFP instructions, Equal Benefits requirements, Minimum Qualifications, WMBE Inclusion Plans, satisfactory financial responsibility, and past performance on City projects.
The Pre-Award Clarification Phase occurs after consultant selection but prior to contract award, requiring the selected consultant to present a detailed implementation plan, coordinate risk minimization solutions, clarify value assessment options, and identify specific support and resources needed from the City. This phase ensures the selected consultant has adequately addressed all aspects of the project scope. Past performance on similar City projects and overall firm responsibility are considered during evaluation, including any significant failures to perform on previous City contracts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| On-Call_Consulting_Services_for_Electrification,_Grid_Modernization,_and_Strategic_Technology.pdf | ||
| Exhibit_D_-_Insurance_Transmittal_Form.pdf | ||
| Exhibit_B_-_Pre-Submittal_Meeting.docx | DOCX document | |
| Exhibit_A_-_City_Consultant_Contract_Boilerplate.pdf | ||
| Attachment_H_-_Checklist_of_Tasks.docx | DOCX document | |
| Attachment_G_-_Hourly_Rates_-_Prime_&_Sub_Rate_Sheet.xlsx | XLSX spreadsheet | |
| Attachment_F_-_Consultant-Questionnaire_2-12-26.docx | DOCX document | |
| Attachment_E_-_WMBE_Consultant_Inclusion_Plan.docx | DOCX document | |
| Attachment_D_-_Relevant_Experience.docx | DOCX document | |
| Attachment_C_-_List_of_Subconsultants.docx | DOCX document | |
| Attachment_B_-_Past_Performance_Survey.docx | DOCX document | |
| Attachment_A_-_Minimum_Qualifications.doc | DOC document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit C – Overview of Expertise-Driven Project Delivery Process
Design, Implement, and Manage Seattle City Light Strategic Energy Management (SEM) Program
RFP# SCL- 767054841
Overview of the Expertise-Driven Project Delivery Process This contract will be delivered via the Expertise-Driven Project Delivery (XPD) process as outlined in this RFP. The XPD process consists of three primary phases: 1) Selection Phase, 2) Pre- Award Clarification Phase, and 3) Post-Award Performance Metrics.
The XPD process consists of a 1) Selection Phase, and a 2) Pre-Award Clarification Phase, as summarized in the following paragraphs and outlined below.
Selection Phase:
The first phase of the XPD process focuses on each Consultant’s ability to differentiate itself from competing proposals. Consultants will be evaluated based upon the ability to identify, prioritize, and minimize project risks, add differential value to the City, show a high level of past performance on behalf of other clients and similar projects, and propose a highly qualified project team.
Submitted proposals should be brief, show differentiation, and allow the City to make a justifiable selection. It is imperative that each Consultant realize that what is written in the proposals and discussed in the interviews will become part of the final contract.
Pre-Award Clarification Phase:
The second phase of the XPD process occurs prior to award with the selected Consultant. The selected Consultant will be required to clearly present their implementation plan for the project, coordinate risk minimization solutions, clarify value assessment options, and identify specific support and resources that will be requested from the City throughout the project. This phase is provided to the selected Consultant to ensure they have properly addressed and accounted for all aspects of the scope in their proposal.
Selection Phase.
Initial Screening The City will review responses for responsiveness and responsibility in accordance with the Selection Phase of the XPD process as described in Section 8. Those responses that comply with the instructions provided in Section 8 of the RFP shall proceed for full evaluation by the Consultant Evaluation Committee. Equal Benefits, Minimum Qualifications, a WMBE Inclusion Plan, satisfactory financial responsibility, and other elements are also screened at this time. A significant failure to perform on past City projects may also be considered in determining the responsibility of a firm.