This is a price proposal form for the City of Toledo's Crosstown Water Main Route Study Request for Proposal. The project encompasses seven basic service tasks: Project Initiation and General Requirements, Corridor Identification and Major Crossing Analysis, Corridor Data Collection and Desktop Utility Subsurface Utility Engineering (SUE), Environmental Assessment, Permitting Coordination and Stakeholder Outreach, Weighted Multi-Criteria Decision Matrix development, and Final Route Selection Report preparation. The form requires proposers to identify task hours and associated costs for each basic service component. Additionally, the form includes provisions for two supplemental services—Topographical Survey and Preliminary Design—that may be required at the City's discretion with separate Notices to Proceed issued if needed. Proposers must submit completed pricing for all tasks along with standard business information including firm name, address, contact details, Federal I.D. Number, and authorized signatures.
The price proposal requires bidders to establish a total estimated basic project cost and specify a multiplier on direct labor excluding benefits or fringes. All submissions must be made in compliance with conditions outlined in the entire proposal package, and the City of Toledo requires that all city-mandated forms identified in Exhibits D and E be completed and attached to the bid submission. The proposal form serves as a binding commitment subject to all terms and conditions established in the RFP documentation.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF TOLEDO
PRICE PROPOSAL FORM
for
Crosstown Water Main Route Study RFP
Basic Services Task Task
Hours Cost
1. Project Initiation/General Requirements
2. Corridor Identification & Major Crossing Analysis
3. Corridor Data Collection & Desktop Utility SUE
4. Environmental Assessment
5. Permitting Coordination & Stakeholder Outreach
6. Weighted Multi-Criteria Decision Matrix
7. Final Route Selection Report
TOTAL ESTIMATED BASIC PROJECT COST = _______________
Multiplier on direct labor (without benefits or fringes):_______
SUPPLEMENTAL SERVICES
The following task may or may not be required from the selected proposer, but are included for costing purposes. Separate Notices to Proceed will be issued if these services are required.
Task Task Hours Cost
8. Topographical Survey
9. Preliminary Design
(EXHIBIT B) Page 1 of 2
This proposal is made in compliance with and subject to all conditions of the entire proposal package.
Firm/Company Name
Address
City State Zip
Telephone Number
Fax Number
Federal I.D. Number
Signature Date
Name (Print) Title
(EXHIBIT B) Page 2 of 2