AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 4
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
06/24/2015
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE AJ930073 7. ADMINISTERED BY (If other than Item 6) CODE
NOAA/ERAD
200 GRANBY STREET
NOROFLK, VA 23510
See Block 6
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
EA133M-15-RP-0056
10B. DATED (SEE ITEM 13)
04/01/2015
CODE 00008411 FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE
PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE PAGE 2 OF 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
(a)
(b)
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(2) Accounting classification Net decrease $
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation
(1)
(2)
(3)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the
(g)
(h) sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
(4)
(5) convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(1)
(2)
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following
(3)
(4)
(5)
(6)
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
Include subject matter or short title of solicitation/contract where feasible.
entries.
(1) Accounting classification Net increase $
(i) Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
STANDARD FORM 30 (REV. 10-83) BACK
SF30 (continued) EA133M-15-RP-0056 Amendment 0003
Amendment 0003 is issued to complete the following:
A. Answers to questions received in response to the solicitation.
Question: In item 3.10 bilge piping renewal can NOAA supply a material list for the piping materials needed for this item? The drawings supplied do not give enough information to quote this item and at the ship check the tanks were not open for inspections.
Answer: Drawing 529-6233819 (Ref 3.10.1.1) is the most detailed drawing available.
Pipe sizes are indicated on the plan views, lengths of pipe can be reasonably estimated from the drawing, knowing the 2-foot frame spacing, and materials are indicated in the Material Schedule on sheet 1 of the drawing.
Question: In item 3.4 parg. 3.4.3.9 for the Okeanos Explorer it tell the contractor to touch up the chain locker. Question is how many SQ FT of touch up will be required?
Answer: Question refers to para 3.4.3.9; however, the requirements for the chain locker (Spaces 1-6-1-Q and 1-6-2-Q) preservation are contained in para. 3.4.3.19. The paragraph indicates the touch-up is to include a stripe coat followed by a full coat. The stripe coat coverage includes all cut-outs, welds, backsides of angles, flanges, edges, wire clips, ladder rungs, and other hard to reach areas. The full coat is the entire surface area of the chain locker which may be reasonably estimated from information on the General Arrangement Drawing, OE-601-101.
Question: In item 3.5 parg. 3.5.1.1 ( MOC-631-3B ) It tells the contractor to use only International or Devoe paints. Can the contractor use Sherwin Williams paints if they meet the required Mil Spec for the paint system?
Is the contractor required to bump or shift the block to paint 100% of the underwater body?
Answer: (a) Yes, Sherwin Williams paints are perfectly acceptable. The intent is to meet the MIL-PRF-24647 Type I or II requirement in the detail spec. (b) No, there is no requirement to bump or fleet the ship or to move bilge or keel blocks to achieve 100% bottom coverage. This will be achieved at the next drydocking by using a different docking position.
Question: Item 3.7 parg. 3.7.3.5 How much belzona or fairing material will be required?
In order to bid the proper amount of material needed.
Answer: For bidding purposes, assume 10 gallons of Belzona material will be required.
Question: Item 3.3, Paragraph 3.3.3.15 The specifications and drawings indicate that the stern tube lube oil piping transits Ballast Tank 4-86. Does the port side pipe also transit Lube Oil Tank 2-92-2? If this pipe transits 2-92-2, is opening, cleaning and gas freeing this tank to be included in this item?
Answer: Tank 2-92-2-F no longer exists on Okeanos Explorer. Please see Plan 45D on Sheet 6 of the General Arrangement drawing (OE-601-101). What was that tank is now part of the Stern Thruster Room (2-86-0-Q). Currently, the stern tube lube oil piping on the port side runs outboard along the forward side of Bulkhead 94, penetrates the 4-86-2-W Ballast Tank, then turns aft and penetrates Bulkhead 94 approximately 10-12 feet outboard from the centerline. However, had the tank still existed, cleaning and certifying the tank safe for hot work would have been required and would have been covered by para. 4.11.2 of NOAA Standard Specification 000-1G and therefore, should have been included in the price for this item.
Question: Item 3.4, Paragraph 3.4.3.9 & 3.4.3.10
3.4.3.9: Please confirm that the specifications reference to Ballast Tank 4-82-2W should actually be Ballast Tank 4-86-2-W.
3.4.3.10: Will the GFE meters be delivered to the shipyard calibrated?
Answer: (3.4.3.9) Yes, 4-82-2-W was a typographical error. It should have read 4-86-2- W. This typo was corrected in Rev 6 of the spec. (3.4.3.10) The Tank Level Indicator parts were shipped directly from the manufacturer. They are exact replacements for the currently installed TLI components in Fuel Oil Tank 4-14-1-F. Calibration, as required, is expected to be part of the testing and demonstrating of proper operation called out in this paragraph.
Question: Item 3.5, Paragraph 3.5 3.5: Will NOAA accept QP-1 inspection of all critical aspects of surface preparation and coating application?
Answer: No, the surface preparation and painting contractor must be QP-1 certified.
Question: Item 5.11, Paragraph 5.11.3.4.7
Will the Penn/Johnson Controls V43 WRV regulator be GFE?
Answer: No, the Water Regulating Valve called out in this paragraph is to be Contractor-furnished. Note: The V43 valve is somewhat longer than the currently installed V46 valve and has different flanges, hence the requirement for companion flanges for the V43
WRV.
B. The closing date and time remains unchanged.
*****END AMENDMENT 0002*****