Proposal Due Date remains June 13 2013 at 2 00 pm EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_001_-_NPS-BLRI_WMS_NC(1).pdf | ||
| Birdge_Insp_Rpt_5140-180P.pdf | ||
| Birdge_Insp_Rpt_5140-091P.pdf | ||
| ADV_Offeror's_Qualifications_Form.doc | DOC document | |
| Birdge_Insp_Rpt_5140-176P.pdf | ||
| Birdge_Insp_Rpt_5140-178P.pdf | ||
| Birdge_Insp_Rpt_5140-177P.pdf | ||
| FP03_Eng_.pdf | ||
| Plans_-_PRA-BLRI_WMS_NC(1).pdf | ||
| FP03_Errata.pdf | ||
| Birdge_Insp_Rpt_5140-179P.pdf | ||
| Birdge_Insp_Rpt_5140-182P.pdf | ||
| RFP_Solicitation_-_PRA-BLRI_WMS_NC(1).pdf | ||
| VETS-100A-Form.pdf | ||
| Birdge_Insp_Rpt_5140-181P.pdf | ||
| Birdge_Insp_Rpt_5140-183P.pdf | ||
| Birdge_Insp_Rpt_5140-099P.pdf | ||
| REV_Synopsis_Notice_-_PRA-BLRI_WMS_NC(1).doc | DOC document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
DTFH7113R00013
x x
0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sterling VA 20166-6511
EFLHD-CO
21400 Ridgetop Circle Construction Office Eastern Federal Lands Highway Div.
Federal Highway Administration
Sterling VA 20166-6511
EFLHD-AC
21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.
Federal Highway Administration
SEE BLOCK 1406/06/2013002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/13/2013
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
NPS-BLRI WMS NC(1)
The purpose of this Amendment is to:
1) Replace the Solicitation B Pages to correct the Superpave asphalt quantity.
2) Revise Plans to correct the Superpave asphalt quantity.
3) Provide a summary of responses to questions/clarifications asked by potential Offeror's.
The Proposal due date of June 13, 2013 at 2:00 pm EST., will remain the same as amended under Amendment 001.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 002
Info Page 1 of 2
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Project NPS-BLRI WMS NC(1)
Blue Ridge Parkway Structure Repairs MP 276.3 to 305.2 Solicitation: DTFH71-13-R-00013
The purpose of this Amendment is to:
1) Replace the Solicitation B Pages to correct the Superpave asphalt quantity.
2) Revise the Plans to correct the Superpave asphalt quantity.
3) Provide a summary of responses to questions/clarifications asked by potential bidders.
The Proposal due date of June 13, 2013 at 2:00 pm EST., will remain the same as amended under Amendment 001.
Solicitation B Pages changes
Delete the Solicitation Bid Schedule pages B-1 through B-5, and substitute the amended Bid Schedule pages B-1 through B-5.
Pay item 40101-0100 updated with the Superpave asphalt quantity change.
Plan Sheet changes
Delete Plan Sheets C1 and C4, and substitute the amended Plan Sheets C1 and C4.
a) Sheet C1 (Tabulation of Quantities) updated to match Bid Schedule.
b) Sheet C4 (Summaries and Schedules) updated to correct the Superpave asphalt quantity.
Info Page 2 of 2
Questions / Clarifications
The following question and issue were submitted via email at eflhd.contracts@dot.gov. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included. The Government’s direct response to the sender may also have been updated below for better clarity.
There are traffic control items, drums, lights signs, etc. but no item for the installation maintenance and removal of the detour. Is this cost to be spread out among the traffic control item and or mobilization or will an item be added for the detour?
Response: There is no direct payment for maintaining and removing detour. The detour requires many of the temporary traffic control items included in the bid item list.
Please see Subsection 109.05 of the FP for further information regarding scope of payment for direct and indirect work. Each bidder will have to determine where they absorb their indirect costs.
mailto:eflhd.contracts@dot.gov
Project: NPS-BLRI WMS NC(1)
REPAIRS TO DRAINAGE STRUCTURES, RETAINING WALLS & BRIDGES: MP 276.35 TO 305.19
B- 1
Bid Schedule A AMENDMENT 2
Pay Item No.
Estimated Quantity Unit Bid Price Amount Bid
15101-0000 MOBILIZATION
ALL Lump Sum $___________________
15401-0000 CONTRACTOR TESTING
ALL Lump Sum $___________________
15705-1700 SOIL EROSION CONTROL, FILTER BERM
LNFT $_______________ $___________________
15705-1800 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM
LNFT $_______________ $___________________
15706-2200 SOIL EROSION CONTROL, FILTER BAG
EACH $_______________ $___________________
20202-0000 SELECTIVE CLEARING
SQYD $_______________ $___________________
20220-1000 REMOVAL, INDIVIDUAL TREE
EACH $_______________ $___________________
20301-1200 REMOVAL OF HEADWALL
EACH $_______________ $___________________
20302-2100 REMOVAL OF PIPE CULVERT
LNFT $_______________ $___________________
20303-0100 REMOVAL OF APPROACH SLAB
SQYD $_______________ $___________________
20303-1400 REMOVAL OF PAVED WATERWAY, CONCRETE
SQYD $_______________ $___________________
Project: NPS-BLRI WMS NC(1)
Bid Schedule A - Base Contract
Pay Item No.
Estimated Quantity Unit Bid Price Amount Bid
B- 2 AMENDMENT 2
20460-0000 HAND EXCAVATION (AT ABUTMENT 2)
CUYD $_______________ $___________________
20701-1100 EARTHWORK GEOTEXTILE, TYPE III-B
SQYD $_______________ $___________________
20801-0000 STRUCTURE EXCAVATION
CUYD $_______________ $___________________
25101-3000 PLACED RIPRAP, CLASS 3
CUYD $_______________ $___________________
26101-0000 ROCK DOWEL
LNFT $_______________ $___________________
30805-0000 BEDDING AND BACKFILL AGGREGATE
CUYD $_______________ $___________________
40101-0100 SUPERPAVE PAVEMENT, 3/8-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, <0.3 MILLION ESAL (TYPE IV PAVEMENT ROUGHNESS)
TON $_______________ $___________________
41301-0000 ASPHALT PAVEMENT MILLING (2-INCH DEPTH)
SQYD $_______________ $___________________
55201-1200 STRUCTURAL CONCRETE, CLASS SEAL
CUYD $_______________ $___________________
55202-1000 STRUCTURAL CONCRETE, CLASS D (AE), FOR APPROACH SLABS, TYPE
SQYD $_______________ $___________________
60103-0020 CONCRETE, HEADWALL FOR 6-INCH PIPE CULVERT
EACH $_______________ $___________________
60201-1200 48-INCH PIPE CULVERT
LNFT $_______________ $___________________
Project: NPS-BLRI WMS NC(1)
Estimated Quantity Unit Bid Price Amount Bid
B- 3 AMENDMENT 2
60504-0000 GEOCOMPOSITE SHEET DRAIN SYSTEM
SQYD $_______________ $___________________
60801-0400 PAVED WATERWAY, TYPE 4 (AT ABUTMENT 1)
SQYD $_______________ $___________________
61204-0000 SANITARY HATCH COVER
EACH $_______________ $___________________
62001-0000 STONE MASONRY
CUYD $_______________ $___________________
62011-0600 STONE MASONRY HEADWALL FOR 30-INCH PIPE CULVERT
EACH $_______________ $___________________
62011-0900 STONE MASONRY HEADWALL FOR 48-INCH PIPE CULVERT
EACH $_______________ $___________________
62027-0000 REMOVE AND RESET STONE MASONRY
1,960
LNFT $_______________ $___________________
62030-0000 REPOINT STONE MASONRY
25,900
LNFT $_______________ $___________________
62036-0000 JOINT SEALANT
LNFT $_______________ $___________________
62403-0000 FURNISHING AND PLACING TOPSOIL
CUYD $_______________ $___________________
62502-0000 TURF ESTABLISHMENT
SQYD $_______________ $___________________
62901-0600 ROLLED EROSION CONTROL PRODUCT, TYPE 2.B
SQYD $_______________ $___________________
Project: NPS-BLRI WMS NC(1)
Estimated Quantity Unit Bid Price Amount Bid
B- 4 AMENDMENT 2
63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
LNFT $_______________ $___________________
63502-0300 TEMPORARY TRAFFIC CONTROL, ADVANCE WARNING ARROW PANEL,
TYPE C
EACH $_______________ $___________________
63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
EACH $_______________ $___________________
63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
EACH $_______________ $___________________
63502-1900 TEMPORARY TRAFFIC CONTROL, SHADOW VEHICLE
EACH $_______________ $___________________
63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE
SIGN
EACH $_______________ $___________________
63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
LNFT $_______________ $___________________
63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
LNFT $_______________ $___________________
63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
1,370
SQFT $_______________ $___________________
63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
1,270
HOUR $ 21.10 $26, 797.00
Project: NPS-BLRI WMS NC(1)
Estimated Quantity Unit Bid Price Amount Bid
B- 5 AMENDMENT 2
63701-0000 FIELD OFFICE
EACH $_______________ $___________________
$_____________________TOTAL
Submitted by:
Name of Bidder
Project: NPS-BLRI WMS NC(1)
TABULATION OF QUANTITIES
C1
SCHEDULE A
AMD #1- Revised 40101-0100 SMS 6/6/13
DESCRIPTION BY DATE
REVISIONS
NO.
AMENDMENT NO. 2 1
EASTERN FEDERAL LANDS HIGHWAY DIVISION
STERLING, VIRGINIA
REG STATE PROJECT SHEET NO.
SE
NPS
NO.NO.
PMIS
NC
BLUE RIDGE PARKWAY
147611 147639 601
116481 NC(1)
NPS-BLRI WMS
C4
SUMMARIES AND SCHEDULES
EARTHWORK, PAVING AND REMOVALS
SOIL EROSION CONTROL
AMD #2- Revised Item 40101-0100 SMS 6/6/13
DESCRIPTION BY DATE
REVISIONS
NO.
AMENDMENT NO. 2 1
EASTERN FEDERAL LANDS HIGHWAY DIVISION
STERLING, VIRGINIA
REG STATE PROJECT SHEET NO.
SE
NPS
NO.NO.
PMIS
NC
BLUE RIDGE PARKWAY
147611 147639 601
116481 NC(1)
NPS-BLRI WMS
| Amendment 2 info.pdf |
| U.S. DEPARTMENT OF TRANSPORTATION |
| FEDERAL HIGHWAY ADMINISTRATION |
| EASTERN FEDERAL LANDS HIGHWAY DIVISION |
| Amendment No. 002 |
| Project NPS-BLRI WMS NC(1) |
| Structure Repairs MP 276.3 to 305.2 |
| Solicitation: DTFH71-13-R-00013 |