Project No. WA PFH WA 29‐1(5)
Project Middle Fork Snoqualmie River Road Slope Stabilization
# General Technical Question Answer Date
1 x Is the retainage on this project 10%?
If the Prime retains from their subcontractors then the Government will also withhold that amount from the progress estimate. After substantial completion of the contract, the CO may retain an amount adequate for the protection of the Government. This amount will be released with the final payment. FP 109.08(g). Otherwise there is zero set retainage on this project.
4/18/17
2 x
The last question and answer in this field report from Golder says the construction sequence for the draped rockfall protection is top down in lifts and that it needs to be in place prior to blasting. Looking at page 21 of the plans it looks like part of the system must go in after the blast. Should we plan to install the draped rockfall protection in stages? The upper part on the soil before the blast and the lower part after the blast and excavation?
The sequencing of construction is to be determined by the Contractor considering many factors including the stability of the slope during construction and the protection of work already installed. There is a requirement to provide an anchored mesh work plan SCR 651.04(2).
4/18/17
3 x
Specification section 622 lists a smooth drum roller and Motor grader as rental equipment, but no bid item is provided for these two types of equipment. Are there supposed to be bid items for the roller and grader by the hour?
See Amendment A002, which revises the
SCR 622 to include the required equipment.
4/18/17
4 x
Are there loading limits on the middle fork road from the blasting site to the bridge scour site?
Do we need to haul the rock in a truck with standard H‐20 axles or can we use a rock truck?
Legal Loads only. 4/18/17
5 x Is saw cutting asphalt pavement incidental to the asphalt patching prices by the square yard?
No direct payment is provided. See Section
109.05.
4/18/17
6 x
Scour mitigation plans show a 12' access road.
We need a road at least 20' wide to acess the site. Trees will need to be removed to build the access.
Submit an access plan for approval according to Subsection 251.03A. Adjust clearing limits to the minimum necessary to perform work, and stake the limits for review, according to Subsection 201.03.
4/25/17