A003.pdf

PDF 2 MB Posted

Attached to
CO ER 94/81/106(1), Boulder County Lefthand Canyon Drive
Solicitation number
DTFH6815B00012
Issued by

About this file

Amendment A003

View the file

Other files

File Type Posted
Bid_Tabs_CO_ER_94.pdf PDF
Bid_Opening_Summary-CO_ER_94-81-106(1)_.docx DOCX document
Q-A _revised_10-14-15.pdf PDF
A002.pdf PDF
Sign-in_Sheet.pdf PDF
A001.pdf PDF
Earthwork_by_Station.xlsx XLSX spreadsheet
Cross_Sections.pdf PDF
CO_ER_94-81-106(1)_Lefthand_Canyon_Drive_Pavements_Report-8-25-2015.pdf PDF
CO_ER_94_81_106(1)-1.Boulder_County.Left_Hand_Canyon.Final.2015._.pdf PDF
DTFH6815B00012.pdf PDF
Plans.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

aaron.sanford Typewritten Text

Item No. Quantity Unit Unit Price Amount

15101-0000

Line Z0020 ALL LPSM $ $

15210-3000

Line Z0040 4.130 MILE $ $

15301-0000

Line Z0060 ALL LPSM $ $

15401-0000

Line Z0080 ALL LPSM $ $

15501-0000

Line Z0100 ALL LPSM $ $

40101-5600

Line Z0120 8,000 TON $ $

40105-3000

Line Z0140 75 TON $ $

41201-0000

Line Z0160 30 TON $ $

41301-0600

Line Z0180 67,000 SQYD $ $

63401-0700

Line Z0200 88,000 LNFT $ $

63502-0700

Line Z0220 200 EACH $ $

63502-1300

Line Z0240 200 EACH $ $

63504-1000

Line Z0260 200 SQFT $ $

63506-0500

Line Z0280 500 HOUR $ $

63506-0600

Line Z0300 160 HOUR $ $

Bid Schedule Schedule: Z Schedule Type: Options Project No: CO ER 94/81/106(1) Project Name: Boulder Cty Lefthand Canyon Dr

ANTISTRIP ADDITIVE, TYPE 3

TACK COAT

ASPHALT PAVEMENT MILLING, 2-INCH DEPTH

PAVEMENT MARKINGS, TYPE D, SOLID

TEMPORARY TRAFFIC CONTROL, CONE

TEMPORARY TRAFFIC CONTROL, DRUM

MOBILIZATION

CENTERLINE, VERIFICATION AND STAKING

CONTRACTOR QUALITY CONTROL

CONTRACTOR TESTING

CONSTRUCTION SCHEDULE

ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL

TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

TEMPORARY TRAFFIC CONTROL, FLAGGER

TEMPORARY TRAFFIC CONTROL, PILOT CAR

Amendment A003 October 14, 2015

Joe.Wilson Typewritten Text A-21

Joe.Wilson Typewritten Text

Joe.Wilson Typewritten Text

Joe.Wilson Typewritten Text

Joe.Wilson Typewritten Text

Joe.Wilson

E-34

CO ER 94/81/106(1)

BOULDER COUNTY LEFTHAND CANYON DRIVE

20401-0000 Roadway Excavation. Actual volume of excess material may vary, depending on the processing, sizing and placement of excess material in the available stockpile areas. The computed excess material volume assumes material is stockpiled at 95-percent density.

If imported materials are used for embankment or riprap, excess excavation volumes will increase.

Increases in excess excavation as a result of the Contractor’s discretion in material handling or utilization of import material will result in no increased cost to the Government.

Payment

204.17 Add the following:

Payment for Item 20401 is limited to ten percent of the plan quantity of excavation in the cut until the slope rounding in that cut is completed.

Section 205. – ROCK BLASTING

Description

205.01 Add the following:

Controlled pre-split blasting will be required for all excavated slopes where rock blasting is expected.

205.07 Add the following:

205.07 A test blast of up to 400 cubic yards (300 cubic meters) may be allowed with CO approval.

205.08 Delete the first sentence in fourth paragraph

205.08 (b) Add the following to the seventh paragraph:

Lifts may be offset 36 inches (900 millimeters) for drill clearance.

205.08 (b)(1) Delete first sentence

Measurement

205.11 Delete the text and substitute the following:

205.11 Measure the Section 205 items listed in the bid schedule according to Subsection 109.02 and the following as applicable:

Do not measure controlled blasting or production blast holes. Controlled and Production blasting is considered subsidiary to pay item 20401-0000 Roadway Excavation.

Payment

205.12 Add the following:

Amendment A003 October 14, 2015

E-35

Controlled blasting and production blasting is considered subsidiary to pay item 20401-0000 Roadway Excavation.

Section 251. — RIPRAP

Delete this section and substitute the following:

Description

251.01 This work consists of furnishing and placing riprap for bank protection, slope protection, drainage structures, and erosion control.

It is intended that rock excavated from the roadway prism will be conserved and used for pay items 25110-2800 Grouted Riprap, Method B, Class 8 and 25110-2800 Grouted Riprap, Method B, Class 8 (Bridge Foundation).

It is assumed that 15% grout by volume will be utilized for 25110-2800 Grouted Riprap, Method B, Class 8.

It is assumed that 25% grout by volume will be utilized for 25110-2800 Grouted Riprap, Method B, Class 8 (Bridge Foundation).

Geotextile filters are designated according to Table 714-1.

Material

251.02 Conform to the following Subsections:

Geotextile 714.01 Minor Concrete 601 Riprap 705.02

Construction Requirements

251.03 General. Perform the work under Section 209. Dress the slope to produce a smooth surface. If geotextile filter is required, place according to Section 207. Provide a concrete mix design for grouting that conforms to Section 601

251.04 Placed Riprap. Placed riprap is rock placed on a prepared surface to form a well-graded mass.

Place riprap to its full thickness in one operation to avoid displacing the underlying material. Do not place riprap material by methods that cause segregation or damage to the prepared surface. Place or rearrange individual rocks by mechanical or hand methods to obtain a dense uniform blanket with a reasonably smooth surface.

251.05 Keyed Riprap. Keyed riprap is rock placed on a prepared surface and set into place by impact pressure.

E-36

Place rock for keyed riprap according to Subsection 251.04. Set the riprap into place by exerting impact pressure with a hydraulic-powered bucket or an approximate 5000-pound (2000-kilogram) flat-faced mass.

Repeated impacts should be made until the rock is firmly seated and forms a reasonably uniform surface without reducing the effective sizes of the rocks. Do not use impact pressure on riprap below the water surface.

251.06 Grouted Riprap. Grouted riprap is rock placed or keyed on a prepared surface with the voids filled or partially filled with concrete grout.

Place rock for grouted riprap according to Subsection 251.04 or 251.05. Do not place concrete grout unless the air temperature is at or above 35 °F (1 °C) within the near-surface voids of the riprap. Place the grout in a manner to prevent segregation. Protect grout from freezing for at least 7 days after grouting.

251.07 Acceptance. See Table 251-1 for sampling, testing, and acceptance requirements.

Rock for riprap will be evaluated under Subsections 106.02 and 106.04. Perform acceptance testing for grading at stockpile at the source.

Concrete grout mix design will be evaluated under Section 601.

Material for concrete grout will be evaluated under Subsections 106.02 and 106.03.

Acceptance Method A riprap construction will be evaluated under Subsection 106.02.

Acceptance Method B riprap construction will be evaluated under Subsections 106.02 and 106.04.

Placing grout will be evaluated under Subsection 106.02.

Geotextile filters will be evaluated under Section 207.

Structure excavation and backfill will be evaluated under Section 209.

Measurement

251.08 Measure the Section 251 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:

When measuring riprap by the cubic yard (cubic meter), measure in place.

Concrete grout will not be measured for payment and is considered subsidiary to 25110-2800 Grouted Riprap, Method B, Class 8 and 25110-2800 Grouted Riprap, Method B, Class 8 (Bridge Foundation).

Payment

251.09 The accepted quantities will be paid at the contract price per unit of measurement for the Section 251 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Sheet and Description

B11 B12

Grading Summary

Miscellaneo us

Summaries ALLOWANCE Bid

Schedule

Z0020 15101-0000 MOBILIZATION LPSM ALL

Z0040 15210-3000 CENTERLINE, VERIFICATION AND

STAKING MILE 4.130

Z0060 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL

Z0080 15401-0000 CONTRACTOR TESTING LPSM ALL

Z0100 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL

Z0120 40101-5600 ASPHALT CONCRETE PAVEMENT,

GYRATORY MIX, 1/2-INCH OR

3/4-INCH NOMINAL MAXIMUM SIZE

AGGREGATE, 0.3 TO <3 MILLION

ESAL TON 8,000

003 Z0140 40105-3000 ANTISTRIP ADDITIVE, TYPE 3 TON 71 4 75

003 Z0160 41201-0000 TACK COAT TON 28 2 30

Z0180 41301-0600 ASPHALT PAVEMENT MILLING,

2-INCH DEPTH SQYD 65,007 1,993 67,000

Z0200 63401-0700 PAVEMENT MARKINGS, TYPE D,

SOLID LNFT 88,000

Z0220 63502-0700 TEMPORARY TRAFFIC CONTROL,

CONE EACH 200

Z0240 63502-1300 TEMPORARY TRAFFIC CONTROL,

DRUM EACH 200

Z0260 63504-1000 TEMPORARY TRAFFIC CONTROL,

CONSTRUCTION SIGN SQFT 200

Z0280 63506-0500 TEMPORARY TRAFFIC CONTROL,

FLAGGER HOUR 500

Z0300 63506-0600 TEMPORARY TRAFFIC CONTROL,

PILOT CAR HOUR 160

-O ct -2

8:

A M

N

C O

\c o9

4( 1)

\R oa dw ay

\A m en dm en t

3\

[A

3_ O pt io nZ _E

E_ Es tim at e-

.x ls x] Sh ee t

SUMMARY OF QUANTITIES - Option Z

A M E N D

Line Item No.

Pay Item Number Pay Item Description Unit

Estimated Quantities

Remarks and/or Determination of Estimated

Quantity

STATE PROJECT

B10 ER 94/81/106(1) CO

SHEET

NUMBER

Amendment A003 October 14, 2015

Joe.Wilson Typewritten Text

Joe.Wilson Typewritten Text

Joe.Wilson Typewritten Text

Amendment A003 October 14, 2015

Joe.Wilson Typewritten Text

Untitled
A003_SummaryofQuantities_B10.pdf
Sheet
Text1:
Text2:
0: 1
1: 7
Text3:
0: A003
1: 10/14/2015
2:
0:
1: CO ER 94/81/106(1)
Text4:
0:
0: FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS HIGHWAY DIVISION

12300 WEST DAKOTA AVENUE, SUITE 360

LAKEWOOD, COLORADO 80228

ATTENTION: Joe Wilson 1:

1:
0:
Text6:
0: DTFH6815B00012
1: September 22, 2015
2:
3:
Check Box7:
0: Yes
2: Yes
1:
0:
0: Off
1: Off
2: Off
Check Box9:
1: Off
2: Off
0:
0: Off
1: Off
Text10: 0 *
Text11:
0:
1:
Text12: See Below *
Text13: Invitation for Bid

Remove Page A-21 and replace with attached Page A-21 dated October 14, 2015.

Remove Pages E-34 thru E-36 and replace with the attached Pages E-34 thru E-36 dated October 14, 2015.

Plan Sheets Remove Plan Sheet B10 and replace with attached Plan Sheet B10 dated October 14, 2015.

Remove Plan Sheet B12 and replace with attached Plan Sheet B12 dated October 14, 2015.

NOTE: When printing revised sheets, turn on 'Document and Markups' in the Print Properties menu to illustrate changes on hard copy print.

*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN ITEM 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO SF-1442, PAGE A-2, OF THE SOLICITATION)

Text14:
0:
1:
Text15:
1:
0:
1:
0:
0:
1:
Text16:
0:
1:
Text17:
Text5:
0: 6905001
1:
Check Box1:
0: Yes
1: Off

File details come from the government source that posted it. Updated .