J.3_Milestone_Payment_Schedule.docx
DOCX document 21 KB Posted
- Solicitation number
- DTFH6117R00045
About this file
J.3 Milestone Payment Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_for_Amendment_No._2.docx | DOCX document | |
| Questions_for_Amendment_No._1.docx | DOCX document | |
| RFP_No._DTFH6117R00045_FBO_P2_FINAL_08.11.17.pdf | ||
| J.1_Deliverable_Schedule.docx | DOCX document | |
| J.5_Schedule_of_Rates_No._2.rtf | RTF text file | |
| DTFH6117R00045_Amendment_No._001.pdf | ||
| J.4_Schedule_of_Rates_No._1.rtf | RTF text file | |
| J.4_Schedule_of_Rates_No._1.rtf | RTF text file | |
| Final_Report_3.pdf | ||
| J.1_Deliverable_Schedule.docx | DOCX document | |
| Final_Report_4.pdf | ||
| J.2_Reference.docx | DOCX document | |
| J.7_Standard_Form_LLL.doc | DOC document | |
| J.5_Schedule_of_Rates_No._2.rtf | RTF text file | |
| RFP_No._DTFH6117R00045_FBO_07.31.17.pdf | ||
| Final_Report_2.pdf | ||
| Final_Report_1.pdf | ||
| J.6_Small_Business_Subcontracting_Plan.docx | DOCX document | |
| J.8_Optional_Form_17,_Offer_Label.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTFH6117R00045
Attachment J.3
Milestone Payment Schedule
“Development of Next Generation Pavement Performance Measures and Asset Management Methodologies to Support MAP-21 Performance Management Objectives”
| PAYMENTS |
| DESCRIPTION OF SERVICES |
| UNIT PRICE PAID FOLLOWING |
ACCEPTANCE
| 1 |
| Completion of the following for Tasks 1: |
· Kick Off Meeting
· Final minutes documenting discussion from kickoff meeting.
$ __________ (FFP)
| 2 |
| Completion of Task 2: |
· Technical memorandum outlining activities achieved during Task 2.1, 2.2, and 2.3 and detailing approach towards conducting Task 3 and Task 4.
· Web conference to present the activities achieved during Task 2.1, 2.2, and 2.3 and approach for conducting Task 3 and Task 4 to the Technical Panel and other interested participants.
(FFP)
| 3 |
| Completion of Task 5: |
· Technical memorandum detailing final recommendations and procedures for implementing performance measures and asset management methodologies.
· Web conference to present final recommendations and procedures to the Technical Panel and other interested participants.
$ __________ (FFP)
| 4 |
| Completion of Task 6: |
· Technical memorandum detailing guidance for modifying existing management systems to accommodate the new performance measures and asset management methodologies.
· Web conference to present the guidance to the Technical Panel and other interested participants.
$ __________ (FFP)
| 5 |
| Completion of Task 7: |
· Draft project webinar materials
· Draft Techbrief
· Draft project report
$ __________ (FFP)
| 6 |
| Completion of Task 8: |
· Final project webinar materials
· Final Techbrief
· Final project report
$ __________ (FFP)
NOTE: The Contractor may submit one payment each quarter after the effective date of the task order once the COR has approved the deliverables listed above.