J.1_Deliverable_Schedule.docx
DOCX document 33 KB Posted
- Solicitation number
- DTFH6117R00045
About this file
J.1 Deliverable Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_for_Amendment_No._2.docx | DOCX document | |
| Questions_for_Amendment_No._1.docx | DOCX document | |
| RFP_No._DTFH6117R00045_FBO_P2_FINAL_08.11.17.pdf | ||
| J.1_Deliverable_Schedule.docx | DOCX document | |
| J.5_Schedule_of_Rates_No._2.rtf | RTF text file | |
| DTFH6117R00045_Amendment_No._001.pdf | ||
| J.4_Schedule_of_Rates_No._1.rtf | RTF text file | |
| J.3_Milestone_Payment_Schedule.docx | DOCX document | |
| J.4_Schedule_of_Rates_No._1.rtf | RTF text file | |
| Final_Report_3.pdf | ||
| Final_Report_4.pdf | ||
| J.2_Reference.docx | DOCX document | |
| J.7_Standard_Form_LLL.doc | DOC document | |
| J.5_Schedule_of_Rates_No._2.rtf | RTF text file | |
| RFP_No._DTFH6117R00045_FBO_07.31.17.pdf | ||
| Final_Report_2.pdf | ||
| Final_Report_1.pdf | ||
| J.6_Small_Business_Subcontracting_Plan.docx | DOCX document | |
| J.8_Optional_Form_17,_Offer_Label.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTFH6117R00045
Attachment No. J.1
DTFH6117R00045
Attachment No. J.1
J.1 DELIVERABLES SCHEDULE
This technical exhibit lists any reports or documentation that is required as a deliverable to include the frequency, # of copies, medium/format and who/where it is to be submitted. A deliverable is anything that can be physically delivered but may include non-physical things such as meeting minutes.
| Deliverable |
| Frequency |
| # of Copies |
| 508 Compliance |
| Medium/ Format |
| Submit To |
| Meeting Agenda |
| One-time, within 10 business days after the award of the contract. |
| one (1) electronic copy |
| No |
| Electronic copy in MS Word format |
| COR by e-mail |
Minutes documenting discussion from kickoff meeting
SOW Section 1.4, Task 1 One-time, within 10 business days after the meeting.
one (1) electronic copy
| No |
| Electronic copy in MS Word format, with any supporting data in MS Excel format |
| COR by e-mail |
Quarterly Progress Reports (QPR)
SOW Section 1.4
| Due on the weekday closest to the 15th of the month following the quarterly period of performance |
| One (1) electronic copy |
| No |
| Electronic copy in MS Word® format |
| COR & CO by |
Technical memorandum outlining activities achieved during Task 2.1 – 2.3 and detailing approach towards conducting Task 3 and Task 4.
SOW Section 1.4, Task 2
| One-time, up to eight (8) months from date of contract award |
| one (1) electronic copy |
| No |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
COR by e-mail
Web conference to present the activities achieved during Task 2.1 – 2.3 and approach for conducting Task 3 and Task 4 to FHWA.
SOW Section 1.4, Task 2
| One-time, up to eight (8) months from date of contract award |
| one (1) electronic copy |
| No |
| MS PowerPoint |
| COR |
At completion of first State DOT validation, webinar to present approach used and findings to FHWA, State DOTs and other invited participants.
SOW Section 1.4, Task 3
| One-time, up to thirty (20) months from date of contract award |
| one (1) electronic copy |
| No |
| MS PowerPoint |
| COR |
Technical memorandum detailing activities and findings resulting from State validation efforts. A separate technical memorandum shall be developed for each DOT validation effort.
SOW Section 1.4, Task 3
| One each for each DOT validation effort, up to thirty (30) months from date of contract award |
| One (1) electronic copy |
| No |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
| COR by e-mail |
Technical memorandum detailing activities and findings resulting from Federal validation effort.
SOW Section 1.4, Task 4
| One-time, up to thirty (30) months from date of contract award |
| one (1) electronic copy |
| No |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
| COR by e-mail |
In-person meeting and presentation to FHWA discussing approaches used and results of State and Federal validation.
SOW Section 1.4, Task 3 and 4.
| One-time, up to thirty (30) months from date of contract award |
| one (1) electronic copy |
| No |
| MS PowerPoint |
| COR |
Technical memorandum detailing final recommendations and procedures for implementing performance measures and asset management methodologies.
SOW Section 1.4, Task 5
| One-time, up to thirty-two (32) months from date of contract award |
| one (1) electronic copy |
| No |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
| COR by e-mail |
Web conference to present final recommendations and procedures to FHWA.
SOW Section 1.4, Task 5
| One-time, up to thirty-two (32) months from date of contract award |
| one (1) electronic copy |
| No |
| MS PowerPoint |
| COR |
Technical memorandum detailing guidance for modifying existing management systems to accommodate the new performance measures and asset management methodologies.
SOW Section 1.4, Task 6
| One-time, up to thirty-four (34) months from date of contract award |
| one (1) electronic copy |
| No |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
| COR by e-mail |
Web conference to present guidance for modifying existing management systems to accommodate the new performance measures and asset management methodologies to FHWA.
SOW Section 1.4, Task 5
| One-time, up to thirty-four (34) months from date of contract award |
| one (1) electronic copy |
| No |
| MS PowerPoint |
| COR |
Draft final project webinar materials Draft Techbrief Draft final project report Revised draft final project report
SOW Section 1.4, Task 7
| One-time, up to thirty-six (36) months from date of contract award |
| one (1) electronic copy |
| Yes |
| Electronic copy in MS Word format, any supporting data in MS Excel format |
| COR by e-mail |
Final deliverables including all documentation, tool, techbrief, 508 captions, copyright releases, and government edits, ready for publication.
SOW Section 1.4, Task 8
| One-time, five (5) business days prior to contract end date. |
| one (1) electronic copy |
| Yes |
| Electronic copy in MS Word format, any supporting data in MS Excel format |