21 SF30 Amend 0002 signed Wall Panel - 20Sep16.pdf
PDF 616 KB Posted
- Attached to
- Replace Obsolete Wall Panels at the Hampton ARTCC, Hampton, Georgia. Federal contract opportunity
- Solicitation number
- DTFAEN-16-R-00175
About this file
21 SF30 Amend 0002 signed Wall Panel - 20Sep16 (pdf)
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 8
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0002 09/20/16
6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6)
Federal Aviation Administration Eastern Service Area, AAQ-510ATL Attn: Michael Hollis 1701 Columbia Avenue College Park, GA 30337
SAME AS BLOCK 7
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
DTFAEN-16-R-00175
9B. DATED (SEE ITEM 11)
08/29/2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation on as amended, by one of the following methods:
(a) By completing Item 8 and 15, and returning 1 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.
AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment to SIR- Request for Proposal DTFAEN-16-R-00175 is being executed for the following(s):
1. Site Visit attendees list, updated Past Performance Questionnaire and responses to Request for Information are attached.
2. Proposal due date is change to September 23, 2016 @ 2PM EDT.
3. Past Performance questionnaire due date is change to September 23, 2016 @ 2PM EDT.
NO OTHER CHANGES OR UPDATES ADDED.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Michael Hollis
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign)
BY
(Signature of Contracting Officer) 09/20/2016
OMB Control No. 2120-0595 (SF-30) FAA Template No. 11 (Reverse) (8/97)
OMB No. 2120-0595 DTFAEN-16-R-00175
Attachment 9
Past Performance Survey
Replace Obsolete Wall Panels Hampton ARTCC Hampton, Georgia
PAST PERFORMANCE SURVEY
Solicitation No.: DTFAEN-16-R-00175 Replace Obsolete Wall Panels Hampton ARTCC
Hampton, Georgia
To: ____________________ (Point of Contact) ____________________ (Company) ____________________ (Phone) ____________________ (Fax)
The Federal Aviation Administration is currently evaluating and you were listed as a performance reference. It would be greatly appreciated if you would take 5 or 10 minutes to complete the following information and return to me via email (preferred) by September 23 , 2016 @ 2PM EDT. Email: michael.hollis@faa.gov or Fax: 404-305-5774
If you have any questions or comments, feel free to contact me. Thank you in advance for your assistance.
Michael Hollis Contracting Officer, AAQ-510ATL Eastern Acquisitions Service Area Southern Region, Tel-404-305-5298
Please identify the project(s) that this company has performed for your organization, description, city, state, and approximate dollar value:
Respond to the following on a scale of 1 to 5, with 3 being Acceptable, and 5 being Outstanding.
1. Did the contractor commit adequate resources in timely fashion to the contract to meet the requirements and to successfully solve problems? 1 2 3 4 5
2. To what extent did the contractor respond positively and promptly to technical direction, contract change orders, etc.? 1 2 3 4 5
3. How reliably did the contractor follow through on commitments? 1 2 3 4 5
Replace Obsolete Wall Panels Hampton ARTCC
Hampton, Georgia
4. To what extent did the contractor’s management system provide visibility into problems and risks? 1 2 3 4 5
5. How responsive do you think the contractor was to information requests, issues, or problems during the course of the contract? 1 2 3 4 5
6. How effective has the contractor been in identifying user requirements?
1 2 3 4 5
7. To what extent did the contractor have the ability to administer and manage the contract?
1 2 3 4 5
8. To what extent did the contractor issue professional correspondence?
1 2 3 4 5
9. How well did the contractor adhere to the Statement of Work? 1 2 3 4 5
10. What was your level of satisfaction with the contractor’s management and support staff?
1 2 3 4 5
11. What was your level of satisfaction with the contractor’s Supervisor(s)?
1 2 3 4 5
12. To what extent did the contractor submit required reports and documentation in a timely manner? 1 2 3 4 5
13. To what extent were the contractor’s reports and documentation accurate and complete?
1 2 3 4 5
14. To what extent was the contractor’s maintenance and problem tracking/reporting documentation timely, accurate and of appropriate content?
1 2 3 4 5
15. To what extent did the contractor comply with safety requirements?
1 2 3 4 5
16. What was your level of satisfaction with the contractor’s overall quality of service?
1 2 3 4 5
Replace Obsolete Wall Panels Hampton ARTCC
Hampton, Georgia
17. To what extent was the contractor effective in interfacing with the Government staff?
1 2 3 4 5
18. What was your level of overall customer satisfaction? 1 2 3 4 5
19. To what extent were the contractor’s employees experienced and qualified?
1 2 3 4 5
Respond: Yes or No.
20. Were there any cure notices issued? Yes: ____ No: ____
21. Was contractor pro-active? Yes: ____ No: ____
22. Did contractor suggest cost-saving changes? Yes: ____ No: ____
23. Would you recommend this contractor? Yes: ____ No: ____
For Federal contracts:
24. Were there any Labor Department Investigations? Yes: ____ No: ____
24a. If yes, please describe reason and final outcome.
25. Were there any safety investigations? Yes: ____ No: ____
25a. If yes, please describe reason and final outcome.
26. Were there any security investigations? Yes: ____ No: ____
26a. If yes, please describe reason and final outcome.
27. Was there a partial or complete termination for default or convenience? Yes: ___ No: ___
Replace Obsolete Wall Panels Hampton ARTCC
Hampton, Georgia
27a. If yes, please describe reason and final outcome.
28. Are there any pending terminations? Yes: ____ No: ____
29. What is/was the duration of the contract? _____________________
30. Were there any performance issues regarding the contractor’s work? If yes, please describe.
Please provide other comments:
Signature: ____________________________
Date: ____________________________
QUESTIONS & ANSWERS
Replace Wall Panels
Hampton, ARTCC
DTFAEN-16-R-00175
September 20, 2016
Q1. I would like to follow up on the Replace Obsolete Wall Panels at the Hampton ARTCC project. May I obtain a copy of the pre-bid meeting sign-in sheet or plan holders list if available?
A1. The sign in sheet will be posted on the faaco.faa.gov website.
Q2. Can you extend the bid date out for this project from 9/20/2016?
A2. Bid date will be change to 09/23/2016 @ 2PM EDT.
Q3. Will the Notice to Proceed be issued after the submittals are approved and the panelboards are received by the contractor? (4-6 week lead time on panelboards after ordering).
A3. NTP will be issued after all submittal are approved and panel boards are received due to the long lead time. Contractor will be required to provide this office with a copy of the ordering documentation and a copy of the shipment received documentation.
Q4. Drawing E002 Notes “Panelboard E-B101-1 (Previous: Panel E-B102-A)” states that temporary feeder shell feed from B-B102. Can you locate panel B-B102 for me? I cannot find it.
A4. Panel B-B102 is located in the break room, right outside of B101. See attached file for the location.
Q5. Will we be allowed to run the temp feeders during normal working hours?
A5. The temporary feeder conductors and conduits can be installed during normal working hours. The final termination to the power panel has to be done at night. No energize work allowed.
Q6. Can MC cable or SO cord be used as temp power?
A6. Some MC cable or SO can be used as temp power and is subject to COR for approval on a case by case basis.
Q7. Has anyone asked for an extension on this Sources Sought? If so, when has it been extended to?
A7. See response in A2.
| 2016-09-20T08:09:47-0400 | |