16 SIR16R00175_Atch1_Spec 100 combined - 29Aug16.pdf

PDF 606 KB Posted

Attached to
Replace Obsolete Wall Panels at the Hampton ARTCC, Hampton, Georgia.
Solicitation number
DTFAEN-16-R-00175
Issued by

About this file

16 SIR16R00175_Atch1_Spec 100 combined - 29Aug16 (pdf)

View the file

Other files

File Type Posted
21 SF30 Amend 0001 signed Wall Panel - 7Sep16.pdf PDF
16 SIR_Wall Panels Final - 29Aug16.pdf PDF
16 SIR16R00175_Atch3_SOW NAP 2012 Panelboard - 29Aug16.pdf PDF
16 SIR16R00175_Atch1_Spec 100 combined - 29Aug16.pdf PDF
16 SIR16R00175_Atch5_Bus Dec - 29Aug16.pdf PDF
16 SIR16R00175_Atch4_WD GA20150133_Wall Panel - 29Aug16.pdf PDF
16 SIR16R00175_Atch6_Construction Breakdown_Wall Panels - 29Aug16.pdf PDF
16 SIR16R00176_Atch7_PPQ_Wall Panels - 29Aug16.pdf PDF
16 SIR16R00175_Atch2_Drawings 100 Signed - 29Aug16.pdf PDF
21 SF30 Amend 0002 signed Wall Panel - 20Sep16.pdf PDF
16 SIR16R00175_Atch6_Construction Breakdown_Wall Panels - 29Aug16.pdf PDF
16 SIR_Wall Panels Final - 29Aug16.pdf PDF
16 SIR16R00175_Atch4_WD GA20150133_Wall Panel - 29Aug16.pdf PDF
16 SIR16R00175_Atch2_Drawings 100 Signed - 29Aug16.pdf PDF
16 SIR16R00176_Atch7_PPQ_Wall Panels - 29Aug16.pdf PDF
16 SIR16R00175_Atch5_Bus Dec - 29Aug16.pdf PDF
16 SIR16R00175_Atch3_SOW NAP 2012 Panelboard - 29Aug16.pdf PDF
16 SIR16R00175_Atch1_Spec 100 combined - 29Aug16.pdf PDF
21 SF30 Amend 0001 signed Wall Panel - 7Sep16.pdf PDF
16 SIR_Wall Panels Final - 29Aug16.pdf PDF
16 SIR16R00175_Atch5_Bus Dec - 29Aug16.pdf PDF
16 SIR16R00176_Atch7_PPQ_Wall Panels - 29Aug16.pdf PDF
16 SIR16R00175_Atch6_Construction Breakdown_Wall Panels - 29Aug16.pdf PDF
16 SIR16R00175_Atch3_SOW NAP 2012 Panelboard - 29Aug16.pdf PDF
16 SIR16R00175_Atch4_WD GA20150133_Wall Panel - 29Aug16.pdf PDF
16 SIR16R00175_Atch2_Drawings 100 Signed - 29Aug16.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Atlanta Air Route Traffic Control Center Atlanta, GA

Electrical Panelboard Replacement Project

SPECIFICATIONS

March 2016

SPEC. # FAA-ZTL-1203568

Prepared by: Federal Aviation Administration ATO Tech Ops Engineering Services

Atlanta Enroute Unit

ELECTRICAL PANELBOARD REPLACEMENT PROJECT MARCH 2016

ATLANTA AIR ROUTE TRAFFIC CONTROL CENTER (ARTCC) FAA-ZTL-1203568

TABLE OF CONTENTS 002 - 1

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS

01000 GENERAL REQUIREMENTS

01010 SUMMARY OF WORK

01030 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS

01040 COORDINATION AND TESTING

01042 CONSTRUCTION SCHEDULES

01300 SUBMITTALS

01651 MATERIALS AND EQUIPMENT

01710 CLEANING

01730 OSHA SAFETY REQUIREMENTS

01740 SAFETY AND HEALTH REQUIREMENTS

01800 CONTRACT CLOSEOUT

DIVISION 7- THERMAL AND MOISTURE PROTECTION

07270 PENETRATION FIRESTOPPING

DIVISION 16 – ELECTRICAL

16050 BASIC ELECTRICAL MATERIALS

16100 RACEWAY AND BOXES

16120 WIRES AND CABLES

16140 WIRING DEVICES

16190 SUPPORTING DEVICES

16195 ELECTRICAL IDENTIFICATION

16452 GROUNDING

16470 PANELBOARDS

16482 MOTOR CONTROL CENTER

* * * END OF DOCUMENT 002 * * *

TABLE OF CONTENTS 002 - 2

SECTION 01000 GENERAL REQUIREMENTS

PART 1 – GENERAL

1.1 SCOPE

A. These specifications, together with referenced specifications, standards, construction drawings specified on the contract documents and conditions of the construction contract cover the requirements of the Federal Aviation Administration (FAA) for the work associated with this project.

1.2 REPAIR AND PROTECTION

A. General: Upon completion of inspection and testing, repair damaged construction and restore finishes.

B. Protect construction exposed by or for quality control service activities, and protect repaired construction.

C. Repair and protection is Contractor's responsibility, regardless of the assignment of responsibility for inspection, testing, or similar services.

1.3 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to the COR for a decision before proceeding.

1.4 RECORD DRAWINGS

The Government shall provide the Contractor with an electronic copy of the record drawings in .pdf format.

Changes to the original plans, drawings or shop drawings shall be annotated in red.

END OF SECTION 01000

GENERAL REQUIREMENTS 01000-1

SECTION 01010 SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Scope of Work - These specifications, together with the referenced specifications, standards, and drawings specified in the contract documents cover the requirements for all work associated electrical panel board replacement in the Atlanta Air Route Traffic Control Center (ARTCC) to include:

The demolition/temporary power/installation/construction phasing and details are provided in the drawings.

The following is a general summary:

1. Remove and replace building service and essential power panelboards, conduits, feeder and branch circuits as shown on the drawings.

2. Install new feeders and intercept existing conduits for essential panel.

3. Provide temporary power to support panelboard replacement.

4. Panelboard removal and replacement is sequential, one at a time with authorized cutovers at night or weekends.

The General Contractor (GC) shall be expected to work during day times, 0700 AM to 0430 PM except for authorized cutovers. Extensive coordination between the GC and FAA personnel shall be required at all times in order to maintain an operational facility.

B. FAA Holiday Moratorium - No work shall be scheduled or take place during the week of and the weekend preceding and following: The Thanksgiving, Christmas, and New Years Holidays. Only emergency work to restore critical services to the Facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration of the project.

C. FAA Holidays Observed - The FAA also observed the following Holidays:

1. Birthday of Martin Luther King, Jr.

2. Washington’s Birthday

3. Memorial Day

4. Independence Day

5. Labor Day

6. Columbus Day

7. Veterans Day

If the Contractor thinks that work will be required on any of these Holidays he will need to coordinate with the Contracting Officer Representative (COR) two weeks in advanced.

D. Intent of Specifications - This specification identifies all material, labor, and equipment required to perform this work. All work performed and all materials and equipment used are subject to

SUMMARY OF WORK 01010- 1

approval by the Contracting Officer (CO) and /or the Resident Engineer (RE). This shall include but is not limited to inspection, scheduling, reporting and submittals.

E. Title - Titles to division and sections of the specifications and notes and titles on drawings referring to subcontractors, division of work by trade, or type of work, are introduced merely for convenience in reading the specifications and drawings and do not imply any separate contractual arrangements of work assignments. Such separations into titled divisions and sections shall not operate to make the Government an arbiter to establish subcontract limits between the contractor and subcontractors, or between the subcontractors themselves.

F. Contract Documents - The drawings, as shown on the "List of Drawings" in Attachment 2 in each specification package, General, Architectural, Mechanical, Electrical, and Southern Standards, all form a part of the construction requirements for this project. The renovation of these systems shall be in accordance with the lines and grades shown on the drawings. The Contractor shall not use dimensions scaled from drawings. All dimensions shown on the drawings shall be field verified by the contractor prior to any modifications and fabrications. Any discrepancies between the drawings and specifications and the existing conditions shall be referred to the CO for adjustment before any work affected is performed.

G. Precedence of Contract Documents - In the event of a difference between the following contract provisions, the order of precedence to determine which provision shall govern is:

1. Contract Clauses and Provisions

2. Project Specifications

3. Project Drawings

Any discrepancies between the contract provisions, the specifications and the contract drawings shall be referred to the CO for a written determination in accordance with Contract Clause entitled Order of Precedence.

H. Contracting Officer -The term "Contracting Officer" (CO) as used herein denotes the person designated to act on behalf of the Government in the performance of this contract. Where reference is made to "Federal Aviation Administration" (FAA), "Resident Engineer" (RE), "Contracting Officer's Representative" (COR), or the like, this shall mean the Contracting Officer or his/her authorized representative.

I. Contractor Superintendence - In accordance with Contract Clause entitled SUPERINTENDENCE

BY THE CONTRACTOR, the Contractor shall at all times during performance of this contract and until the work is completed and accepted, directly superintend the work or assign and have on site a competent superintendent with the authority to act for the Contractor.

The Contractor shall submit a Project Organizational Chart with the key personnel identified and their qualifications for the Government’s review and approval.

1.2 SPECIAL REQUIREMENTS

SUMMARY OF WORK 01010- 2

A. Asbestos Containing Materials. - No new materials supplied by the contractor for this construction shall contain asbestos or lead-based products. The contractor shall verify that all materials, including those supplied by third parties, are asbestos free and/or lead-based free materials.

1. Contractor certification requirements. - The contractor shall provide to the Contracting

Officer (CO) a signed document stating that to the best of his/her knowledge, no asbestos containing or lead-based materials were used during the construction, renovation, and/or modernization of this facility.

2. Material Data Safety Sheets. - The contractor shall submit Material Data Safety Sheets

(MSDS) with all submittals for review and approval by the Contracting Officer. New materials found to contain asbestos and/or lead-based products will be automatically disapproved. Copies of all MSDS sheets shall be provided to the facility FAA personnel for the building records. The contractor shall comply with all health and safety provisions outlined in each MSDS and shall follow all OSHA guidelines regarding personnel protection.

3. Hazardous materials.- If the FAA RE suspects the presence of asbestos or lead-based products in the new materials, the FAA will sample the suspect material to verify that no asbestos containing material or lead-based material were used. If these materials are found to contain asbestos or lead-based products, the cost of the survey and all subsequent removal/replacement of any hazardous materials shall be at the contractors’ expense.

B. Work plan and scheduling. – Prior to the contractor shall submit for approval a plan and schedule of his work. This schedule shall include all of the requirements as defined in Section 01042 of this specification.

C. Sequence of work. - The contractor shall be responsible for scheduling all aspects of the work and coordinating among the different trades involved in the project. The contractor shall follow the guidelines outlined in the sequence of work as described in the contract drawings. The Federal Aviation Administration has developed a list of milestones that the contractor shall be required to meet.

D. Construction Activities and Milestones. – Construction Activities and Milestones below shall be included in the submitted schedule. They are provided for guidance, but are not intended to direct how and when contract activities shall be ordered or take place in the submitted schedule.

1. SUBMITTAL APPROVAL

2. ORDER LONG LEAD ITEMS

a. Panel boards

3. NOTICE TO PROCEED

a. Scheduled by the FAA’s CO

4. ESTABLISH PROTECTION OF PERSONNEL AND EQUIPMENT

5. PROPOSED DATE FOR EQUIPMENT TESTING.

SUMMARY OF WORK 01010- 3

6. REMOVE AND REPLACE PANELBOARDS PER CONSTRUCTION PHASING

REQUIREMENTS

7. REMOVE PERSONNEL AND EQUIPMENT PROTECTION

8. EQUIPMENT WARRANTY

9. CLOSE JOB

E. Driveway Closures - Contractor shall maintain access to the loading dock at all times.

END OF SECTION 01010

SUMMARY OF WORK 01010- 4

SECTION 01030 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS

1.1 SUMMARY

A. Existing facility operations. - Construction/demolition shall in no way interfere with Air Traffic Control

Operations. The ARTCC is a 24 hour, seven day a week facility. Extreme care shall be exercised so as not to cause any interference or interruption of service from this facility. Controller functions are vital to the safety of the flying public. It is absolutely mandatory that the contractor protects FAA personnel and existing FAA communication, electrical and mechanical equipment both inside and outside buildings from damage caused by impact, water, debris, dust or odor. The contractor shall have the overall responsibility for the performance and enforcement of all forms of protection within the ARTCC premises against any damages due to work performed under this contract. Any damages incurred, as a result of construction activity during the performance of this contract will be repaired/replaced immediately by the contractor at no cost to the FAA.

Any work or activity that may impact the National Airspace System (NAS), such as work on critical equipment or circuits, will require coordination with the Contractor Office Representative (COR). The COR will prepare and submit a work or activity specific “Risk Assessment” for the facility’s review and approval. This process may take one week to complete. Typically, this type of work or activity is performed from midnight to 05:00 am and/or on weekends.

B. Construction limits and access. -

1. Construction limits.- The contractor shall confine operations, activities, storage of materials and employee parking within the designated areas, as indicated on the construction staging plan, or as designated by the COR. Additional space the contractor deems necessary shall be obtained off site, at no additional cost to the Government.

2. Access. - Access route for the contractor, subcontractors, employees, deliveries, etc., shall be off

Woolsey Road, or as designated by the COR. Access to all, parking areas, and loading dock shall be kept unobstructed. If temporary access obstruction is unavoidable, the contractor shall advise the COR immediately. Vehicles transporting materials shall not be loaded beyond the capacity prescribed by federal, state, or local laws. Obstruction of existing roadways, driveways, to the ARTCC is strictly prohibited.

3. Damage to site. - Damage to existing paving, lawns, curbs, sidewalks, and utilities caused by the contractor's activities shall be repaired immediately. Any damage to the building, interior or exterior, that are a result of the contractor’s activities shall be repaired. All costs of repairs shall be paid by the contractor. After notice to proceed and prior to the commencement of construction, the contractor and COR shall conduct joint inspections of the existing areas affected by the construction. Existing damage or defects shall be noted and will be used as the basis for determination of damages caused by the contractor's operations.

4. The Contractors’ employees can use the cafeteria for takeout service, but no dining in.

C. Inspection of site by contractor. - It is strongly urged that the contractor carefully examine the premises to determine the extent of work and the conditions under which it must be done.

D. Government use and access to premises. - The Government reserves the right to enter the construction area at any time for work inspection and for the operation of the facility.

SITE ACCESS CONSTRUCTION LIMITS 01030- 1

E. Work hours. - All work hours, shifts, and overtime work shall be coordinated with the COR. Before commencing construction, furnish to the COR a statement of hours per day and days per week to normally be worked and approximate number of persons on the job for a normal work shift. Work week is 40 hours.

F. Security requirements. -

1. Personnel List. - Contractor shall provide the COR with a list of contractor personnel who require access to the ARTCC. The list shall be submitted immediately after contract award. The list shall be kept current during the project and shall include the following:

Full name, including middle initial Federal or State issued photo ID Date of Birth Place of Birth

2. Security Investigation and identification. - Contractor's personnel may be subject to security investigation by FAA. The contractor shall promptly complete all security forms provided by the CO. Contractor's personnel shall report to the FAA security guard at entrance to the facility and submit proper identification when signing in to obtain an FAA badge which will be worn on an outside garment, above the waist and below the neck, facing forwards, at all times while on the ARTCC premises.

3. Vehicle identification. - Vehicle identification tags will be issued for contractor's and contractor's employees' vehicles that require access into the ARTCC site. The identification tags shall be displayed in the windshield of the vehicle at all times when the vehicle is on the site. The contractor shall be responsible for the collection and return of all vehicle tags which are no longer required.

4. Escort requirement. - Contractor is responsible to provide an escort for his employees. This will required a security background investigation by the FAA. Contractor's personnel shall not violate any security regulations pertaining to the ARTCC facility. Violators may be removed from the premises with the right to reenter revocable. Contractor's day-to-day work schedules in the classified areas shall be so arranged to allow for minimum escort.

5. Right to search. - Current procedures at FAA facilities include the "right to search." If in the judgment of the FAA a cause to search a vehicle or the person of personnel exists, such search will be made.

6. Replacement of lost identification. - The FAA will provide personnel badges and vehicle identification tags as described above. It is the contractor's responsibility to return these badges and tags daily and upon completion of the project. The contractor shall be liable to pay for any FAA badge or tag not returned or replaced at the completion of the work.

7. Physical Security. - At the end of each work day, the contractor shall secure all construction areas by closing and locking all doors and gates. The contractor is responsible for the security of the staging area, and shall provide the required measures at no additional expense to the government.

SITE ACCESS CONSTRUCTION LIMITS 01030- 2

END OF SECTION 01030

SITE ACCESS CONSTRUCTION LIMITS 01030- 3

SECTION 01040 COORDINATION, LOCAL PERMITS AND TESTING

PART 1 – GENERAL

1.1 SUMMARY

A. Project coordination. - It shall be the duty of the Contractor to prepare a detailed schedule of work and work layout to resolve conflicts and to assure coordination of the work by different trades.

B. Weekly Meeting. - Coordination between the COR and Contractor shall take place weekly at the site. Special meetings will be scheduled if requested by either the COR or Contractor. The subjects to be discussed at the progress meetings shall included, but are not limited to, the following:

-Safety concerns/Issues -Progress of Work -Previous meeting action items/issues -Field problems -Material and Equipment delivery status -Submittal status/schedules -Progress planned during the upcoming week(s) -Review of changes, and potential effects on the schedule -Construction schedule revisions -Schedule Revisions -Other current business

The following persons will be expected to attend meetings; FAA COR, Prime Contractor

Superintendent, Project Manager and Project Manager/Superintendents for other major trades.

C. Facility Coordination Meeting. - Weekly coordination meeting shall take place between the facility managers, COR and the Contractor’s Project Superintendent.

D. Work Affecting Operational Systems. - The contractor shall coordinate all work which has any or may have any impact on any operational system within the facility through the COR.

The contractor shall immediately cease any work which is adversely impacting the operation of the ARTCC and shall immediately repair or restore any portion of the operational system that has been damaged or suffered diminished performance as a result of the contractor's activities.

E. Local permits and Coordination. - The Contractor will be responsible for obtaining and payment of all building fees, inspection fees, utility connection charges and any other fees or charges which may be incurred in the performance of this contract.

F. Applicable documents. - The contractor shall comply with all local city, county, and state construction codes.

1.2 TESTING

A. Contractor's responsibility.- Unless otherwise indicated as the responsibility of another identified entity, Contractor shall provide certified testing and inspection agencies, inspections, tests, and other quality-control services specified elsewhere in the Contract Documents and required by authorities having jurisdiction.

COORDINATION, LOCAL PERMITS AND TESTING 01040-1

1. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Contractor's responsibility, the Contractor shall employ and pay a qualified independent testing agency to perform quality-control services.

2. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Government's responsibility, the Government will employ and pay a qualified independent testing agency to perform those services.

a. Where the Government has engaged a testing agency for testing and inspecting part of the Work, and the Contractor is also required to engage an entity for the same or related element, the Contractor shall not employ the entity engaged by the Government, unless agreed to in writing by the Government.

B. Retesting - The Contractor is responsible for retesting where results of inspections, tests, or other quality-control services prove unsatisfactory and indicate noncompliance with Contract Document requirements, regardless of whether the original test was Contractor's responsibility.

1. The cost of retesting construction, revised or replaced by the Contractor, is the Contractor's responsibility where required tests performed on original construction indicated noncompliance with Contract Document requirements.

C. Selection and payment. - The contractor shall pay for all testing. The contractor shall select and use a certified and qualified testing laboratory to perform the requirements of this contract. The testing laboratory shall be certified by the American Association of Laboratory Accreditation.

D. Rejected materials or workmanship.- All materials or workmanship or both which have been rejected by the COR by reasons of failure to conform to the requirements of the Contract Documents shall be removed and replaced with new, acceptable materials by the contractor at the contractor's own expense. Contractor shall also pay for testing of new materials which have been installed in place of rejected materials.

1. The testing laboratory will furnish three copies of each report directly to the COR covering all of its determinations and conclusions. Reports will show all data customarily listed by the laboratory in reporting on quantities, qualities, and types of materials, together with their correlation with the project and applicable Specification Section.

END OF SECTION 01040

COORDINATION, LOCAL PERMITS AND TESTING 01040-2

SECTION 01042 CONSTRUCTION SCHEDULES

A. Description. - The work plan and schedule prepared by the contractor shall consist of a Gantt and Pert chart(s) and logical narrative plan. The charts shall show all significant activities and shall include detailed activities when critical work is to be performed.

1.2 PRODUCTS

A. Diagrams -

1. Show the order of the activities.

2. Include construction activities, the submittal and approval of materials, samples and shop drawings, the procurement of critical materials and equipment, fabrication of special materials and equipment along with their installation and testing, and costs associated with each activity in the bar chart.

3. Provide a two-week look-ahead schedule.

B. Progress Schedules. - Within 30 calendar days of contract award, the contractor shall submit the schedule and work plan.

1.3 EXECUTION

A. Review and Evaluation. - The Contractor shall participate in a review and evaluation of the proposed schedule with the Contracting Officer. Any revisions necessary as a result of the review shall be re-submitted for approval of the Contracting Officer within 14 days after the conference.

The approved schedule shall then be used by the contractor for planning, organizing, and directing work, reporting progress, and requesting payment for work accomplished. If the contractor, thereafter, desires to make changes in the schedule, the Contracting Officer shall be notified in writing, stating the reasons for the change. If the Contracting Officer considers the change to be of a major nature, the contractor may be required to revise the schedule and submit it for approval, without additional cost to the government.

B. Monthly Update. - The contractor shall meet with the COR at monthly intervals to discuss the construction progress. If the project is behind schedule and requires a change in the schedule, the contractor shall submit a revised schedule with a description of the delaying factors and their impact, and an explanation of corrective actions taken or proposed.

C. Payment. - The monthly update shall show the activities or portions of activities completed during the reporting period, and their total value will be the basis for the contractor's periodic request for payment. Payment will be based on the total value of such activities completed or partially completed after verification by the Contracting Officer.

D. Submission Requirements. - Schedule charts shall be on (minimum) 11" x 17" size paper. Update charts shall show the date of the latest revision. Schedule charts with revisions and monthly updates shall be submitted in three copies.

CONSTRUCTION SCHEDULES 1042- 1

E. Requirements for Schedule Chart. -

1. Activities.- The significant activities to be included in the schedule chart shall include, but not be limited to:

a) The milestones listed in 01010 1.2. D.

b) Any system shutdowns or cut-overs

c) Any other significant activities the contractor or FAA feels necessary.

d) A minimum of 50 activities.

F. Shutdown and Cut Over.

1. Electrical Systems. - New construction shall have no impact on the critical electrical service at this facility. For the changes to building service and essential power panelboards, transformers, feeders, branch circuits, all shutdowns for cutovers, electrical connections within live power panels and connections to existing equipment will be scheduled with the COR at least 14 days in advance. All electrical connections to existing panels shall be coordinated with FAA personnel. Equipment shutdown and lock-out shall be accomplished by FAA personnel.

END OF SECTION 01042

CONSTRUCTION SCHEDULES 1042- 2

SECTION 01300 SUBMITTALS

PART 1 – GENERAL

Applicable provisions of this Section and other provisions and requirements of the Contract Documents apply to all sections, except as modified in Sections of Divisions 2 through 16.

1.1 SUMMARY

Submit Shop Drawings, product data, samples, warranties, certificates, test reports and third party disposal letters as required by the contract documents.

1.2 RELATED REQUIREMENTS

A. Section 01040: Coordination and Testing

B. Section 01651: Materials and Equipment

C. Section 01800: Closeout Procedures

1.3 SUBMITTALS

Submittals required include, but are not necessarily limited to, the following:

A. Submittal schedule

B. Construction progress schedule

C. Submittal log

1.4 SUBMISSION REQUIREMENTS

A. Number of Copies - Submit in ample time for approval before installation. Unless otherwise noted, submit a minimum of four (4) copies of documents to the Resident Engineer (RE). The RE will retain Three (3) copies. If additional copies are required, provide the quantity and submit additional copies to meet this requirement.

B. Time for Approval - Receive submittal approvals prior to starting the work. Time necessary for government approval or disapproval of samples, certificates, test reports, and shop drawings will not be more than 30 calendar days after receipt of a submittal.

All materials installed in the work shall match the approved submittals. After a submittal has been approved, the RE will permit no substitutions without written approval. No extension of Contract Time will be authorized because of failure to transmit to the RE sufficiently in advance of the Work to permit processing.

SUBMITTALS 01300-1

C. Submittal Approval - The checking, marking or approval of the submittal by the FAA shall not be construed as a complete check, but will indicate only that the product or method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for compliance with the specifications or for any error that may exist. The Contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work. Possible approval actions taken by the FAA include:

1. Approved as submitted - If the RE marks a submittal "approved as submitted" each copy of the submittal will be identified as having received such approval by being stamped and dated. After submittal has been approved, the RE will permit no substitutions without written approval.

2. Approved as noted - If the RE marks “approved as noted”, the submittal is satisfactory contingent upon Contractor acceptance of corrections, notations, or both, and if accepted, does not require resubmittal.

3. Not approved - If the RE marks “not approved”, the submittal data does not meet job requirements and the Contractor must resubmit. If the submittal is disapproved, the Contractor shall resubmit the corrected material in the same quantity as specified for the original submittal with in fourteen (14) calendar days of notification. Correct disapproved submittals and resubmit for approval by the RE. Approval of resubmittals requires an additional fourteen (14) calendar days.

4. Submittal Schedule - Identify within the Contractor’s Construction Schedule a schedule of submittals for shop drawings, material approval, etc., showing the dates when submittals will be submitted for the project.

a) Contents - On the schedule indicate the following information:

1) Schedule date for submittal

2) Related Section number

3) Submittal category (Shop Drawings, Product Data, or Samples)

4) Name of the subcontractor (if applicable)

5) Description of the part of the Work covered.

5. Distribution - Following response to the initial submittal, print and distribute copies to the RE, Government, subcontractors, and other parties required to comply with submittal dates indicated. When revisions are made, distribute to the same parties. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.

6. Schedule Updates - Revise the schedule after each meeting or activity where revisions have been recognized or made.

SUBMITTALS 01300-2

D. Construction Progress Schedule – The progress chart to be prepared by the Contractor pursuant to the Contract Clause entitled “SCHEDULES FOR CONSTRUCTION CONTRACTS” shall consist of network analysis system, or pertchart (barchart). The contractor shall be required to complete the work within the contract time limits after receipt of Notice to Proceed excluding the FAA holiday moratorium as specified in section 01010.

1. Contractor shall provide a cost loaded schedule with a minimum of 50 activities The schedule shall indicate which areas are being worked on.

2. The diagram shall show a continuous activity flow from left to right. The diagram shall show the sequence in which the work is to be accomplished as planned by the Contractor.

3. Dates shall be shown on the diagram for start of the project, any milestones required by the contract, and contract completion.

4. The critical path shall be clearly identified.

5. Network activities shown shall include submittal and review of shop drawings and samples and procurement of materials and construction activities.

6. Government activities that affect progress shall be shown. These include but are not limited to: Notice-to-Proceed, approvals, and inspections.

NO PHYSICAL CONSTRUCTION WORK AT THE SITE MAY TAKE PLACE UNTIL THE

CONTRACTOR SUBMITS AND THE GOVERNMENT APPROVES THE SCHEDULE.

Government review of schedule submittal(s) will not exceed 30 calendar days. Resubmittal, if necessary shall not exceed fourteen (14) calendar days.

E. Schedule updates will be provided weekly. Changes for the current week may be hand written. Actual work completed that is more that one week old shall be updated and printed out. Changes to the early and late start times and early and late finish times for scheduled activites will be updated weekly.

F. Submittals - Submit shop drawings, material and equipment lists, and all other data required under various headings of these specifications necessary to permit commencement of work. RE will return the submittals within 30 calendar days after receipt, indicating approval or disapproval.

G. Submittal Preparation - Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.

1. Transmittals - transmittal letters identifying the contents of the submittal shall accompany all submittals. It shall be clearly indicated on the transmittal letter with a statement and signature of the Contractor that the submittal item was verified for compliance with the contract requirements and approved by the Contractor. Transmittal letters shall consist of one original.

SUBMITTALS 01300-3

2. Contents - Submittals shall be complete and detailed and assembled into sets.

Lack of completeness or clarity or inadequate description will be justification for disapproval. Submittals shall bear the following information:

a) Name of project or facility and contract number;

b) Date of submission;

c) Contract drawing number and latest revision;

d) Specification page and paragraph number;

e) Name of contractor and subcontractor or supplier/manufacturer;

f) Clearly identified contents and location of work;

g) Any proposed variances to specification requirements;

h) Contractor’s approval certifying he checked and coordinated the work of other trades.

1.5 SHOP DRAWINGS

A. Applicable Documents -

B. Presentation: Present drawings in a clear and thorough manner. Identify details by reference to sheet and detail, building wing and section shown on contract drawings.

1. Submit newly prepared information drawn accurately to scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not a Shop Drawing.

2. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings.

C. Contents - Provide the following information on each submittal:

1. Submittal number (paragraph 2.1 of this Section) and identify as "Part A" or "Part B" item

2. Date of submission

3. Name of project and facility (full name)

4. Name of Contractor or Subcontractor

5. Reference to drawing number (with revision, if applicable) and/orspecification section

6. Clearly identify contents and location of work.

7. Contractor's approval certifying he checked and coordinated the work of other trades.

8. Dimensions.

9. Identification of products and materials included by sheet and detail number

10. Compliance with specified standards

11. Notation of coordination requirements

12. Notation of dimensions established by field measurement

SUBMITTALS 01300-4

13. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 36 by 48 inches.

D. Submittal - Submit blue- or black-line prints for the RE's review. Submit five copies, of which the RE will retain three.

1. One of the prints returned shall be marked up and maintained as a "Record Document."

2. Do not use Shop Drawings without an appropriate final stamp indicating action taken.

1.6 PRODUCT DATA

A. Collect Product Data into a single submittal for each element of construction or system.

Product Data includes printed information, such as manufacturer's installation instructions, catalog cuts, Material Safety Data Sheets (MSDS), standard color charts, roughing-in diagrams and templates, standard wiring diagrams, and performance curves, for all materials brought on site.

B. Preparation

1. Clearly mark or highlight each copy to identify pertinent site specific products or models the Contractor intends to use

2. Highlight/clearly indicate all performance characteristics and capacities

3. Highlight/clearly indicate all dimensions and clearances required

Note: If the submittal is not clearly marked, regarding the above pertinent data, the submittal will be returned marked "DISAPPROVED".

1.7 WARRANTIES/GUARANTIES

A. Assemble two (2) copies with original signatures of warranties executed by each of the respective manufacturers, suppliers, and subcontractors into a warranty book and prepare a Table of Contents.

B. Additional Data - Provide complete information for each item, include the following:

1. Product or work team

2. Firm, with name of principal, address, and telephone

3. Scope

4. Effective dates of warranty based on Final Acceptance of the item.

5. Information for owner's personnel on proper procedures to evoke the warranty in case of failure and instances which might affect the validity of warranty

C. Warranties - Effective after project completion and acceptance by the FAA.

SUBMITTALS 01300-5

1.8 CERTIFICATES

Assemble certificates executed by each of the respective manufacturers, suppliers, and subcontractors.

A. Additional Data - Provide complete information for each item to certify compliance with contract documents.

1. Product or work item

2. Firm, with name of principal

3. Scope of compliance

4. Signature by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.

PART 2 – MATERIAL

NOT USED

PART 3 – EXECUTION

3.1 GENERAL

Submittals are required for, but not limited to, the items listed in the specifications or on the drawings. The following is a partial list of submittals required: Schedules, Manufacturer's Literature, Shop Drawings, Samples, Test Reports, Warranties, Certificates, Design Calculations, MSDS, and Installation Instructions. This list should not be construed as a complete list of all submittals required. Submittal dates shall comply with this specification unless a more stringent date is specified. Substitutions and all requested changes will require a submittal.

3.2 SCHEDULE FOR CRITICAL SUBMITTALS

Process after the construction contract has been awarded and prior to NTP:

All Critical Submittals are due 30 calendar days after the contract has been awarded. See below for a list of critical submittals. The construction Notice to Proceed (NTP) will not be issued until all critical submittals are approved. All other submittals shall be submitted and approved prior to installation or construction. Critical submittals include the following:

1. Section 01300 - Construction Schedule

2. Section 16470 - Panelboards

3. Section 01730- Safety Plan

No later than two weeks after the contract has been awarded, the Contractor shall be available to participate in a meeting/telecom with the Contracting Officer, Resident Engineer and Office Project Engineer to discuss and coordinate the following:

1) Contractor’s FAA point of contact for submitting the Critical Submittals.

2) Discuss the submittal process and forms.

3) Discuss process and forms for request of FAA security badges.

SUBMITTALS 01300-6

4) Discuss the proposed date for Notice to Proceed (NTP)

PART 4 – QUALITY ASSURANCE

NOT USED

* * * END OF SECTION * * *

SUBMITTALS 01300-7

SECTION 01651 MATERIALS AND EQUIPMENT

1-1 SUMMARY

A. General. - Material and equipment incorporated into the work shall conform to applicable specifications and standards and comply with size, make, type and quality specified, or as specifically approved in writing by the COR. Manufactured and fabricated products shall be designed, fabricated and assembled in accordance with the best engineering and shop practices.

Like parts of duplicate units shall be manufactured to standard sizes and gages and shall be interchangeable. Two or more items of the same kind shall be identical and manufactured by the same manufacturer. Products shall be suitable for service conditions. Equipment capacities, sizes and dimensions shown or specified shall be adhered to unless variations are specifically approved in writing. Do not use material or equipment for any purpose other than for which it is designed or specified. Furnish and install products specified, under options and conditions for substitution stated in this section.

1. Manufacturer's instructions.- When contract documents require that installation of work shall comply with manufacturer's printed instructions, copies of such instructions shall be distributed to parties involved in the installation, including two copies to the COR. Maintain one set of complete instructions at the job site during installation and until completion.

Products shall be handled, installed, connected, cleaned and conditioned in strict accordance with such instructions and in conformity with specified requirements. If job conditions or specified requirements conflict with manufacturer's instructions, the contractor shall consult with the COR for further instructions. All work shall be performed in accordance with manufacturer's instructions. No preparatory step or installation procedure shall be omitted unless specifically modified or exempted by contract documents.

2. Transportation and handling. - Products shall be delivered in undamaged condition, in manufacturer's original containers or packing, with identifying labels intact and legible.

Shipments shall be inspected to ensure compliance with requirements of contract documents and approved submittals, and products are properly protected and undamaged immediately on delivery. Provide equipment and personnel to handle products by methods to prevent soiling or damage to products or packing.

3. Storage. - Unless specified, products shall be stored in accordance with manufacturer's instructions, with seals and labels intact and legible. Products subject to damage by the elements shall be stored in weather tight enclosures.

4. Temperature. - Temperature and humidity shall be maintained within the ranges required by the manufactures instructions. Fabricated products shall be stored above the ground, on blocking or skids to prevent soiling or staining. Products which are subject to deterioration shall be covered with impervious sheet coverings and adequate ventilation shall be provided to avoid condensation.

5. Substitutions. - A separate request for each substitution shall be submitted. Each request shall be supported with complete data substantiating compliance of proposed substitution with the requirements stated in the contract documents. Each request shall include product identification, manufacturer's literature including address, product description, reference standards and performance and test data. Samples shall be submitted as applicable. An

MATERIALS AND EQUIPMENT 01651- 1

itemized comparison of the proposed substitution with the product specified shall be included.

The following information shall also be included: data relating to changes in the construction schedule; list of changes required in other work or products; and accurate cost data.

Substitute products shall not be ordered or installed without written acceptance. In making a formal request for substitution, the contractor represents that he has investigated the proposed products and has determined that it is equal to or superior in all respects to that specified.

The contractor ascertains that he will provide same warranties or bonds for substitutions as for product specified. That he will coordinate installation of accepted substitution into work to be complete in all respects; that he waives claims for additional costs caused by substitution which may subsequently become apparent; and that cost data is complete and includes related costs under his contract. Primarily, an “or equal” product will not be considered a substitution. If an actual substitution is accepted, it shall be done only by formal contract modification and not by a submittal approval.

END OF SECTION 01651

MATERIALS AND EQUIPMENT 01651- 2

SECTION 01710 CLEANING

The scope of this project will be performed in a partially occupied special use environment. Daily cleaning and protection of critical electronic equipment shall be a requirement. All prospective bidders are encouraged to visit the project site to ascertain the criticality of maintaining a clean and dust free environment.

A. Requirements Included.

1. Execute cleaning during the progress of work. This includes but not limited to the following:

a) Wipe all surfaces within the limits of work at the end of each shift.

b) Vacuum all floors where work took place.

c) Remove temporary protective covers at the end of each shift.

2. Execute cleaning for final inspection.

3. Execute cleaning at completion of the work.

RELATED REQUIREMENTS

Section 01651: Materials and Equipment Section 01800: Contract Closeout.

1.2 PRODUCTS

A. Materials. - Use only those cleaning materials recommended by the manufacturers of the surface being cleaned so as not to create hazards to health or property.

1.3 EXECUTION

A. Disposal Requirements. - Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws.

B. Final Cleaning.

1. Employ skilled workmen for final cleaning from a Professional Cleaning Company.

2. Remove grease, mastic, adhesive, dust, dirt, stains, fingerprints, labels, and other foreign materials from visible interior and exterior surfaces.

C. During Construction. - Maintain all areas under Contractor's control free of extraneous debris.

Conduct a specific maintenance program to prevent accumulation of debris at the construction site, storage and parking areas, and along access roads and haul routes.

D. ARTCC Operational Areas. - Clean up after each work shift.

E. Debris Collection. - Provide containers for debris deposit and schedule periodic collections and disposal of debris. Provide additional collections whenever the periodic schedule is inadequate to prevent accumulation.

CLEANING 01710-1

END OF SECTION 01710

CLEANING 01710-2

SECTION 01730 - OSHA SAFETY REQUIREMENTS

1.1 SCOPE

A. This section identifies some of the requirements of the OSHA Construction Standard.

1.2 CONTRACTOR RESPONSIBILITY

A. General Safety Provisions - The Contractor shall bear full responsibility to provide safe working conditions for its employees and Contractors. The Contractor shall not permit any employee or Subcontractor to work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to the health and safety of the employee.

B. Accident Prevention - The Contractor shall bear the responsibility of maintaining an accident prevention program such that frequent and regular inspections of the job site, materials and equipment are made by a competent person designated by the employer.

C. Use of Equipment - The Contractor shall not permit the use of any machinery, tool, material, or equipment that is not in compliance with OSHA regulations. The employer shall permit only those employees qualified by training and/or experience to operate equipment and machinery.

1.3 CONTRACTOR RESPONSIBILITY

A. The FAA shall not be held responsible for safety inspections to assure Contractor conformance with the OSHA safety regulations. The FAA, however, reserves the right to notify the Contractor of any deficiencies regarding worker safety.

B. The FAA will evaluate the Contractor on its safety performance, including that of its Subcontractors. The number and severity of safety and security violations will be considered in this evaluation. Contractor safety violations are cause for termination for default, may result in notification of the Contractor’s bonding company, and will affect the Contractor’s opportunity to propose on future work. Failure to correct such deficiencies may impact the Contractor’s ability to work on future FAA contracts.

1.4 OSHA REGULATIONS

A. The Contractor shall comply with the latest Occupational Safety and Heath Administration regulations (CFR 29 Part 1926) regarding safety in the work area.

B. The Contractor shall be responsible for obtaining copies of non-FAA referenced documents without additional cost to the FAA. If Contractor requests a copy of FAA directives, they may be obtained by contacting the Contracting Officer.

C. The Contractor is not relieved from adhering to other OSHA requirements not listed herein. The Contractor shall consult the latest referenced OSHA documents for safety regulations.

OSHA SAFETY REQUIREMENTS 01730-1

1. Documents:

a) OSHA Documents:

1) CFR 29 Part 1926 Safety and Health Regulations for Construction

2) CFR 29 Part 1910 General Industry Standards Applicable to

Construction Industry

b) FAA Documents:

1) FAA Order 3900.49 Control of Hazardous Energy During

Maintenance, Servicing and Repair

* * * END OF SECTION 01730 * * *

OSHA SAFETY REQUIREMENTS 01730-2

01740- SAFETY AND HEALTH REQUIREMENTS

1. Objectives and Responsibilities

The objectives of the safety and health requirements are to eliminate contractor generated facility shutdowns, interruptions, injuries, illnesses, and incidents. When the Contractor is notified by the Contracting Officer Representative (COTR) of non-compliance with the safety or health provisions of the Contract, the Contractor shall immediately, unless otherwise instructed, correct the unsafe act or unsafe condition.

It is the contractor’s responsibility to understand the work to be performed, perform the work in a professional manner and to protect his workforce and FAA from incidents.

2. Communication

A. All contractor tasks must be communicated to FAA prior to the tasks being performed.

A1. Preconstruction Safety Meeting The FAA will schedule a preconstruction meeting after the Notice to Proceed. The agenda will include:

1. The FAA will identify the Contracting Officer Representative (COTR) and Resident Engineer (RE). The contractor will identify his site management.

2. The FAA will review the chain of authority.

3. The FAA will review the procedure to process field decisions and change orders.

4. The FAA will review the facility safety procedures, and safety and health requirements.