Questions and Answers for RFP DOL-OPS-16-R-00025
1. Is there a pre-proposal conference and/or site visit scheduled for the above-referenced solicitation? If so, when will it be held?
A: The Site Visit will be August 30, 2018 at 10:00 am at the Frances Perkins Building. No more than 2 personnel per company, any more than 2 people per company will NOT allowed to attend the site visit. If you are LATE you will not be allowed to attend the Site Visit. The CUTOFF time is 10:00AM NO EXCEPTIONS
***NO PARKING will be provided***.
2. Can we use CPARS evaluations instead of the past performance questionnaires? No! you will have to submit the Past performance questionnaires per the instruction is the RFP
A: No! you will have to submit the Past performance questionnaires per the instruction is the
RFP. The Contracting Officer (CO)/Contracting Specialist(CS) will review your CPARS.
3. Sections L and M both reference NAICS Code 541519; however, other areas of the RFP reference
NAICS Code 236220. Can you please confirm that this procurement falls under NAICS Code
236220?
A: The correct NAICS Code is 236220
4. Sections L and M require complete resumes be submitted for the primary Contract Manager and key personnel proposed to work on this project. Can you please define the key personnel positions (besides the primary Contract Manager)?
A:
Contract Manager Project Manager Superintendent Quality Control Manager
5. Are key personnel considered a non pre-priced item or are they factored into the line item pricing? They are factored into the
A: The key personnel will be identified and priced separately at a fixed price.
6. Is there a wage scale for this project?
A: This will be established at the task order level.
7. Are there available parking spaces for us within the building or near it?
A: There is street and public parking garages within the general area.
8. Does the work have to be done during normal hours or night hours?
A: This will be established at the task order level.
9. For the fire sprinkler, who would be telling us what has to get relocated and to where?
A: This will be established at the task order level.
10. Can you provide us the workable documents for Section B – Supplies or Services/Price, and
Standard Form 1442 so we can fill in the prices and/or the required information?
A: I have attached the Word document for Section B.
11. Section C of the RFP requests us to include design, engineering, and other consultant costs to this task order. The pricing schedule in Section B – Supplies or Services/Prices does not have such cost line items. Where do we include those costs? If we’re to incorporate such costs into the cost line items in Section B, is there a minimum amount of work so the design, engineering, and other consultant costs are covered? It’s recommended to the government to have those services itemize into the pricing schedule of Section B as separated line items
A: This will be established at the task order level.