MiamiMiami
Job Corps Center Miami Gardens, FL
Facility Planning ReportFacility Planning Report Volume II
Supporting Data
Fi lFinal January 2013
Department of Labor/ Office of Job Corps
22Miami Job Corps Center
MiamiMiami
Job Corps Center Miami Gardens, FL
Facility Planning ReportFacility Planning Report Volume II
Supporting Data
Fi lFinal January 2013
Fountain created by CTST
33 Miami Job Corps Center
CONTENTS
MIAMI JOB CORPS CENTER
FACILITY PLANNING REPORT
VOLUME I - Planning Strategy
• Existing Site Plan
• Center Statistics
INTRODUCTION
• Purpose
• Report Contents
EXECUTIVE SUMMARY
A. EXISTING CONDITIONS
• Background
• General Site Conditions
• General Building Conditions
• Preventive Maintenance
• Ownership
• Facility Assessment by Function
• Energy
• Environmental Issues
• Sustainability
• Accessibility Standards
• Completed and Current Projects Since the Last Survey
• Health and Life Safety Issues
• Summary of Defi ciencies
B. RECOMMENDATIONS
• Status of the Previous (PY09) Plan
• Signifi cant Issues
• PY 12 Plan Overview
• Summary of Proposed Projects
• Regional Projects
• Proposed Site Plan
C. PLANNING ANALYSIS
• Purpose
• Planning Objectives and Assumptions
• Space Utilization Analysis
• Federal Real Property Asset Management
• Mission Dependency Site Plan
• Defi ciency Analysis
• Facility Condition Summary Report
• Building Condition by Function
• Building Condition Site Plan
VOLUME II - Supporting Data
• Vicinity Map
• Location Map
• Existing Site Plan
D. DESCRIPTIONS
• Building and Structures
• Space Utilization By Function
• NSF by Building
• Energy Report
• Environmental Management
Asbestos Report Radon Report
• Site Descriptions
• Building Descriptions
E. DEFICIENCIES
F. CORRESPONDENCE AND REPORTS
• Center Review Brief Meeting Minutes
• Survey Brief
• RA and Student Facility Feedback Questionnaire
• Life Safety Defi ciencies Transmittal and List
• O & M Defi ciency List
• Active Warranty Report
• FRPC Performance Measures Matrix
44Miami Job Corps Center
55 Miami Job Corps Center
66Miami Job Corps Center
77 Miami Job Corps Center
D Descriptions
BUILDINGS AND STRUCTURES
00418 MIAMI 01/25/2013
1Page: of Date:
A - ADMIN. & MEDICAL/DENTAL
B - EDUC/VOC/DAY CARE CENTER
C - FEMALE DORMITORY
D - MALE DORMITORY
E - RECREATION BUILDING
F - CAFETERIA/CULINARY ARTS
G - VOCATIONAL SHOPS BUILDING
H - MAINTENANCE/WAREHOUSE
C-1 - GAZEBO
D-1 - PAVILION
D-2 - SOLAR FIELD
E-1 - PAVILION
E-2 - PAVILION
E-3 - PAVILION
G-1 - FLAMMABLE STORAGE
G-2 - STORAGE
G-3 - SHADE HOUSE
G-4 - SHADE HOUSE
Name GSF
9,675 24,430 11,855 20,460 23,280 13,425 17,235 11,870
1,350 3,200 1,850 1,340
Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active
StatusType
Building Building Building Building Building Building Building Building Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure
Use Group Built Flrs Const
Business Business & D Residential Residential Assembly Assembly Business Business Assembly Assembly Utility/Misc.
Assembly Assembly Assembly Storage Storage Utility/Misc.
Utility/Misc.
Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good Good
ConditionAsset Number
0041800010 0041800011 0041800012 0041800013 0041800014 0041800015 0041800016 0041800017 0041808098 0041808102 0041808105 0041808101 0041800020 0041808104 0041800018 0041808100 0041808099 0041808103
8 132,230
10 9,422
18 141,652
Buildings
Structures
Total
GSF
GSF
GSF
Summary
01/23/2013
Space Utilization By Function 00418 Miami Page: 1 of Date:
HOUSING
EDUCATION
FOOD SERVICE
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
Resident Men Resident Women Total Residents
Residents 160 Non Residents 140
300Total Students
(160)
(300)
(300)
DIFFERENCE
16,000
17,880
5,400
20,765
32,855
8,267
Lounge Other Shower/Toilet Sleeping Storage
Academic (300) Non-Academic
30 -- Accounting Clerk 30 -- Business Office Technologies 20 -- Carpentry + 30 -- Computer Service Tech.
20 -- Culinary Arts + 15 -- Electronic Assembly (Off Center) 48 -- Facilities Maint. and Const. + 15 -- Major Appliance Repair (Off Cen 30 -- Nurse Asst/Home Health (OCT) 20 -- Painting +
Vocational Theory (108)
Dining (2 Servings) Food Preparation Food Storage
2,910 2,180 1,225
12,550 1,900
5,130 7,740
1,140 3,950
1,750
8,465
1,795
1,105
3,092 3,765 1,410
1,600
1,920 11,520
3,000 3,000
1,200 1,500
1,200
3,600
1,500
1,080
2,400 1,800 1,200
1,310
-695 1,030
2,130 4,740
-10 -60
2,450 -10
4,865
1,965
Vocations
4,765
14,975
2,867
01/23/2013
Space Utilization By Function 00418 Miami Page: 2 of Date:
RECREATION
MEDICAL/DENTAL
ADMINISTRATION
STORAGE/SUPPORT
SUGGESTED
NSF/
ENROLLEE
SUGGESTED
TOTAL
NSF
ACTUAL
TOTAL
NSF
TYPE OF SPACE
SUB TOTAL
SUB TOTAL
SUB TOTAL
SUB TOTAL
TOTAL 222.17 66,650 97,227
(300)
(300)
(300)
(300)
DIFFERENCE
132,230
0.74
TOTAL GSF
NET TO GROSS RATIO
10,100
2,070
9,200
6,000
16,565
2,685
6,655
9,435
Aerobics/Exercise Arts & Crafts Gymnasium Handball Miscellaneous Recreation Multipurpose Room Recreation Room Recreation Storage Snack Bar Weight Room
Medical/Dental
Administration Child Development Center (40)
Operations & Maintenance Warehouse
6.9
6,725
2,860
2,460
2,685
3,550 3,105
5,015 4,420
2,070
6,000 3,200
2,400 3,600
-2,450 -95
2,615
RESIDENT
NON-RESIDENT
(160)
(140) 15
50 8,000 2,100
6,465
-2,545
3,435
30,577
Net Square Footage By Building Date: 01/23/2013 Page: 1
Center: MIAMI (00418) of 4
HOUSING
Sleeping
Lounge
Storage
Shower/Toilet
Other
Function Suggested
NSF
5,020 7,530
1,200 1,710
1,140
1,390
C - FEMALE DORMITORY
D - MALE DORMITORY
C - FEMALE DORMITORY
D - MALE DORMITORY
C - FEMALE DORMITORY
D - MALE DORMITORY
D - MALE DORMITORY
C - FEMALE DORMITORY
D - MALE DORMITORY
C - FEMALE DORMITORY
Bldg Name Actual NSF Difference
12,550
2,910
1,900
1,225
2,180
Sub Total: 20,765
11,520
1,600
1,920
16,000
1,030
1,310
-695
2,180
( 160
4,765
Page: 2
Center: MIAMI (00418) of 4
EDUCATION
Academic
Vocational Theory (108)
Carpentry
Culinary Arts
Painting
Computer Service Tech.
Facilities Maint. and Const.
Non-Academic
Accounting Clerk
Business Office Technologies
Function Suggested
NSF
1,765
3,530
1,750
1,795
8,465
2,015
1,690
1,445
1,140
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
G - VOCATIONAL SHOPS BUILDING
F - CAFETERIA/CULINARY ARTS
H - MAINTENANCE/WAREHOUSE
G - VOCATIONAL SHOPS BUILDING
F - CAFETERIA/CULINARY ARTS
G - VOCATIONAL SHOPS BUILDING
B - EDUC/VOC/DAY CARE CENTER
G - VOCATIONAL SHOPS BUILDING
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
A - ADMIN. & MEDICAL/DENTAL
E - RECREATION BUILDING
A - ADMIN. & MEDICAL/DENTAL
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
E - RECREATION BUILDING
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
B - EDUC/VOC/DAY CARE CENTER
Bldg Name Actual NSF Difference
5,130
1,105
3,950
1,750
1,795
8,465
7,740
1,140
Sub Total: 32,855
3,000
1,080
1,500
1,200
1,500
3,600
3,000
1,200
17,880
2,130
2,450
-10
4,865
4,740
-10
-60
( 300
14,975
Page: 3
Center: MIAMI (00418) of 4
FOOD SERVICE
RECREATION
MEDICAL/DENTAL
Dining (2 Servings)
Food Preparation
Food Storage
Multipurpose Room
Snack Bar
Arts & Crafts
Gymnasium
Weight Room
Miscellaneous Recreation
Aerobics/Exercise
Handball
Recreation Room
Recreation Storage
Medical/Dental
Function Suggested
NSF
3,092
3,765
1,410
6,725
2,860
2,460
2,685
F - CAFETERIA/CULINARY ARTS
F - CAFETERIA/CULINARY ARTS
F - CAFETERIA/CULINARY ARTS
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
E - RECREATION BUILDING
A - ADMIN. & MEDICAL/DENTAL
Bldg Name Actual NSF Difference
3,092
3,765
1,410
6,725
2,860
2,460
2,685
Sub Total:
Sub Total:
Sub Total:
8,267
16,565
2,685
2,400
1,800
1,200
2,070
5,400
10,100
2,070
1,965
2,867
6,465
Page: 4
Center: MIAMI (00418) of 4
ADMINISTRATION
STORAGE/SUPPORT
Administration
Child Development Center
Warehouse
Operations & Maintenance
Function Suggested
NSF
2,820
3,105
4,420
5,015
A - ADMIN. & MEDICAL/DENTAL
G - VOCATIONAL SHOPS BUILDING
B - EDUC/VOC/DAY CARE CENTER
H - MAINTENANCE/WAREHOUSE
H - MAINTENANCE/WAREHOUSE
Bldg Name Actual NSF Difference
3,550
3,105
4,420
5,015
Sub Total:
Sub Total:
6,655
9,435
6,000
3,200
3,600
2,400
9,200
6,000
-2,450
-95
2,615
-2,545
3,435
Energy Management Report Center: MIAMI (00418)
Page: 1 Date: 01/23/2013 of 3
CENTER ENERGY DATA
Yes
ENERGY CONSUMPTION ASSESSMENT
18% 70,424
67,654 85,637
ENERGY USE BY FUEL TYPE
Energy Audit :
Date of Audit :
Status of Energy Conservation Measure Recommendations :
Electric Company :
Percent Change since Baseline Year :
Natural Gas Company :
Property Status :
9/2009 Not Implemented Florida Power and Light Company Florida City Gas Company
Federally Owned (DOL)
2,311,158 7,886=
Total 9,312
MBtu
MBtu
Total $211,774 MBtu/ $22.742
BTU/GSF
BTU/GSF
BTU/GSF
Electricity
Natural Gas kWh
1,384 MCF = 1,426 MBtu
$199,040 $0.086= kWhElectricity
Natural Gas $12,734 = $9.201 MCF
ENERGY COST BY FUEL TYPE
COMMENTS
ECMs active
1. LED exit signs
2. Hot water set to 120
3. Limiting A/C runs, Staggered A/C Starts
4. O&M Filters
5. R/R old water heaters
WATER CONSUMPTION ASSESSMENT
Percent Reduction Since Baseline Year:
1,000 Gallons
1,000 Gallons
FY 2012 Energy Goal:
Further Reduction in Energy Usage is needed to meet Energy Reduction Goals.
FY 2012 Energy Consumption:
Note: The Federal Government has set a goal of 3% Energy Consumption Reduction per year in EO 13423.
15,713 14,142 4,944,281
Further Reduction in Water Usage is needed to meet Water Reduction Goals.
Note: The Federal Government has set a goal of 2% Water Consumption Reduction per year in EO 13423.
FY 2012 Goal:
FY 2012 Water Consumption:
1,000 Gallons
FY 2003 Energy Baseline:
FY 2007 Baseline:
Page: 2 of 3
Implementing some of the below recommendations can save you 10% to 25% off your annual energy bill without negatively impacting comfort or productivity.
1. Your staff and students are the key to savings. Educate the students and staff on the why of energy saving - costs and environmental impacts. Encouraging them to actively participate in energy reduction is also important. Post reminders at exit doors and bulletin boards about energy conservation. Simple tips include:
a. Turn it down (lights, heating & cooling),
b. Turn it off (lights, computers, other equipment),
c. Keep it tight (close doors and windows, use window blinds)
2. Operations and Maintenance: Educate the O&M staff on the why of energy saving -costs and environmental impacts. Simple tips include:
a. Make sure that the Operations and Maintenance staff is properly trained for the equipment they operate.
b. Tune and clean HVAC: Perform seasonal cleanups on air conditioners, boilers and furnaces, and regularly clean cooling coils and drain pans. Get rooftop or outdoor condenser coils cleaned and maintain an appropriate filter changing schedule.
c. Check (or ask your HVAC contractor to check) your outside air dampers or economizers to verify proper ventilation. Make sure economizer controls function properly. Make sure automatic dampers close during unoccupied periods.
d. Restore automatic control: When troubleshooting a system, take time to figure out and repair the automatic controls. Today's quick fix is tomorrow's bad idea.
e. Reasonable set points: Try 68°F in the heating season and 75°F in the cooling season.
f. Schedule HVAC equipment and lighting: (weekdays, weekends, holidays, off-season). Make sure equipment runs only when it is needed and the buildings are occupied. When buildings are vacant (i.e. dormitories during the day with students in class), make sure all the lights in the building are off.
g. Seasonal (resets, schedules, and shutoffs): As the seasons change, adjust set points and schedules to match the system's response to the weather.
h. Lighting: Invest in an inexpensive light level meter to measure the foot-candles in spaces to determine whether or not they are over lit and lamps can be safely removed. Where four-lamp fixtures are in use, two lamps can usually be removed from every fixture or every other fixture. After lamps are removed, disconnect ballasts. Contact the Energy team at PBDewberry for suggested light levels for individual space types. Cleaning fixtures regularly increases light levels.
i. Utilize power management features for all computers and monitors to shut them off when idle for more than 15 minutes.
Page: 3 of 3
j. Have your vending machine suppliers turn off or remove light tubes from the advertising lighting in the machine. This will save about $50 per year per vending machine.
k. Save water with low flow sink aerators (0.5gpm) and low flow shower heads (1.5gpm - 2.0gpm). This will also reduce water heating energy consumption.
l. Set your water heater to 120°F. Verify by measuring at the tap. Never go below 115°F.
m. For water heaters installed in unconditioned spaces, add insulation blankets making sure that access covers, electric connection areas, and pressure relief valves are left uncovered.
n. Caulk and fill cracks around doors and windows to reduce costly air leaks.
o. When replacing broken glass, use high transmittance, low heat gain windows.
p. Make sure automatic door closers are functioning properly to avoid drafts.
3. Buy energy efficient, buy EnergyStar (www.energystar.gov).
a. Buy EnergyStar appliances and equipment.
b. Replace burned out lightbulbs with EnergyStar labeled compact fluorescent lightbulbs (CFLs).
c. Replace broken thermostats with EnergyStar labeled programmable products.
d. Replace broken exit signs with EnergyStar LED exit signs.
Environmental Management Report
Page: 1 Date: 01/23/2013 of 1
SOLID & HAZARDOUS WASTE MANAGEMENT (RCRA)
Commercial Waste Service
HAZARDOUS MATERIALS STORAGE (EPCRA)
N/A N/A
N/A No
PETROLEUM UNDERGROUND STORAGE TANKS (RCRA)
N/A0
PETROLEUM ABOVEGROUND STORAGE TANKS (CWA)
ASBESTOS AND PCB MANAGEMENT (TSCA)
AIR POLLUTION CONTROL (CAA)
N/A None
Attainment
Solid Waste Disposal :
Hazardous Waste Generator :
Hazardous Waste ID :
Generator Classification :
Hazadous Materials Storage :
Hazardous Materials ID :
HazMat Storage Area :
HazMat Spill Response Plan :
Number of Regulated USTs :
Number of Un-regulated USTs :
Local Hazardous Use Permit :
LEPC Notification :
EPA Generator ID Number :
Hazardous Waste Disposal :
RCRA Compliance
ID LocationFuel Type Capacity
Number of ASTs :
Asbestos Survey Date :
Asbestos Type :
Asbestos Coordinator :
Coordinator Training Date:
Custodial/Maintenance Training :
AHERA Regulated :
Management Plan Approval :
PCB Transformer Testing :
PCB Transformers :
PCB-Contaminated Transformers :
Transformers Labelled :
Regional Air Quality :
Permitted Air Pollution Source :
Source Description :
Waste Management Services, Inc.
No N/A
N/A N/A N/A
N/A
N/A N/A
Overfill Leak Corrosion
SPCC Plan Required : SPCC Plan Completed :
No N/A
No Survey Performed None N/A
N/A No
No Yes
ID Fuel Type Capacity Location Overfill
Prevention Secondary ContainmentTank Status
Tank Status Prevention/Detection
Radon
Date: 01/23/2013Center : Miami (00418) Page: 1 of 1
A - ADMIN. & MEDICAL/DENTAL
B - EDUC/VOC/DAY CARE CENTER
C - FEMALE DORMITORY
D - MALE DORMITORY
E - RECREATION BUILDING
F - CAFETERIA/CULINARY ARTS
G - VOCATIONAL SHOPS BUILDING
H - MAINTENANCE/WAREHOUSE
Bldg Name
09/17/2003
09/17/2003
09/17/2003
09/17/2003
09/17/2003
09/17/2003
09/17/2003
Test Date
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Radon Testing
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
< 4 pCi
Test Result
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Mitigation Mitigation Date
RADON EXPLANATORY NOTES
The US Environmental Protection Agency (EPA) has established a radon action level of 4.0 picoCuries per liter (pCi/L). Occupied buildings with radon concentrations less than 4.0 pCi/L do not require radon mitigation; un-occupied buildings, or those buildings which are occupied only infrequently for brief periods of time, also do not require radon mitigation. Occupied buildings with radon concentrations greater than
4.0 pCi/L require radon mitigation and verification of radon reductions as soon as possible, with priority given to dormitories and student recreation buildings. Occupied buildings with radon concentrations greater than 20.0 pCi/L should be considered significant radon exposure hazards, and priority for mitigation should be given to buildings with these highly elevated radon concentrations.
Radon mitigation techniques include: (1) adjustment of the building HVAC system to create a positive pressure within the building; (2) sealing of foundation wall cracks, penetrations, or other openings;
(3) sealing crawlspace openings and sump pits; (4) installing an active subslab depressurization (ASD) system.
Site Description
MIAMI
Aerial view of the centerAerial view of the center
Page: 1 Date: 01/23/2013 of 4
Paving Type for Roads & Parking Paving Type for Sidewalks
Asphalt Concrete
Comments:
Topography Buildings and Structures
Center is fully enclosed by fencing.
ROADS, PARKING & SIDEWALKS
Water Source Water Authority Service Meter On-Site Treatment Plant
1. Water System
Treatment Type Storage Type Storage Capacity(Gallons)
NoMasterMiami-Dade Water & Sewer AuthorityPublic Water Authority
None 0None
Two wells (Well-1 and Well-2) supply water for irrigation to the northern half and southern half of the facility. A master water meter is located near the parking lot in the northwest area of the facility.
Comments:
Comments:
Fire Hydrants On-Site Water Supply Storage Capacity
(Gallons) Pressure Source FD Response Time (Minutes)
Yes 0 3None Municipal
The nearest Miami-Dade fire station is about one mile away from the center and the emergency response time is about 3 minutes.
Number of Deficiencies = 1
SITE FEATURES
UTILITIES
2. Fire Protection System
Buildings Structures8 10Flat
Surrounding
Outdoor Recreation
Residential
Basketball, Soccer Field, Soft/Baseball, Volleyball None
Entire Site
GSA Vehicle Parking
Solar Field
Chain Link
Chain Link
Cement Panels
Location Type
Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Separate Loop
No
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Ownership
Roads & Parking Adequate Roads & Parking Condition Sidewalks Adequate Sidewalk Condition Yes Good Yes Good
Fencing
Other Features
Page: 2 Date: 01/23/2013 of 4
Comments:
Sewage Treatment Flow
Sewer from the center flows into the city sewer system operated by the Miami-Dade Water and Sewer Authority.
Utility
Publicly Owned Treatment Works
Utility
Gravity
Maintenance ResponsibilityOwnership
Comments: Florida City Gas Company supplies natural gas for cooking and domestic water heating.
Florida City Gas Company
Comments:
Electric Company PCB Trans.
Transformer Mounting Transformer Ownership
Systems Ownership Maintenance Responsibility
Florida Power and Light Company
Service is brought to the center from primary 12.47/7.2 kV overhead lines on 183rd Street NW at the north, along the eastern boundary and on 179th Street NW at the south. The overhead lines transit to underground and terminate in pad-mounted transformers located outside the buildings they serve. Each building has its own meter installed near the pad-mounted transformer or inside near the main distribution panel. The ball field sport lighting system is metered separately from a meter installed on the field near Pavilion Structure K. The ball field lighting, Buildings A, B, E, F, G and H are provided with 277/480V services and step-down transformers for 120/208V.
Female Dormitory Building C and Male Dormitory Building D are provided with 120/208V services only. There is a solar photovoltaic water heating system installed in the back of Male Dormitory Building D. The system consists of a photovoltaic array, two storage tanks, controllers and water circulating pumps.
Pad Utility
Utility Utility
No
12.47/7.2 kV
480/277 and 120/208 Volt, 3-Phase, 4 WireUnderground
Overhead & UndergroundPrimary Service
Secondary Service
Distribution Characteristics
3. Sanitary Sewer System/ Sewage Treatment Plant
5. Fuel Distribution System
Number of Deficiencies = 4
System Capacity Adequate System Condition
Yes Good
4. Storm Water System Number of Deficiencies = 1
Drain Type On-Site Storm Water Management
Underground N/A
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Yes GoodCenter
Comments: There are surface water runoff catch basins strategically located within the center. These catch basins are connected to several localized trench drains which drain the surface water runoff into the ground entirely within the center.
Gas Company Metering
Individual
Ownership Maintenance Responsibility System Capacity Adequate System Condition
Utility Utility Yes Good
7. Electrical (Service)
Transformer Maint Resp
Utility
System Capacity Adequate System Condition
Yes Good
Generator
None
ATS MTS
No No
6. Central Plant: None
Metering Individual
Page: 3 Date: 01/23/2013 of 4
ACCESSIBILITY
Yes
NoNoNoNo
Nationally Registered Site
Site Eligible for National Register
Located in Historic District
Archaeological Significance
Comments:
Telephone Company
On-site Line Owner
AT&T provides four T1 lines to the center which terminate in the electrical room in Administration & Medical/Dental Building A. The server and data/communication equipment is located in the medical supply/storage room. Bell South provides the local telephone service and the Job Corps Data Center (JCDC) provides the long distance telephone voice over internet protocol (VoIP) service with fiber optic cables. Three T1 lines are utilized for internet connection and LAN/WAN networks. One T1 line is dedicated to the VoIP. All data communication systems are managed and maintained by JCDC. The server and communication equipment is supported by a 2 KVA portable UPS module which buffers the power surges and drops in the line voltage, and will maintain the power requirement of the system up to 20 minutes before an automated shut down. The fire alarm control panels in buildings on center are connected to the central fire alarm control/annunciator panel located in the Building A main lobby. The center security system consists of a number of CCTV cameras, a multi-display color monitor, an automatic gate operator and a hand held metal detector. The CCTV cameras are strategically installed on light poles and building exteriors around the center perimeter. The cameras are monitored from the security office in Building A. The hand held metal detector is used at the checkpoint outside the security office. The automatic gate operator is installed at the northeast parking lot. Cable TV is provided in the dormitory, dining, and recreational facilities.
AT&T
Maint. Responsibility
Center Center
CCTV Camera, Color Monitor, Automatic Gate Operator
Earthquake Risk
Low Low MediumLow MediumIBC High
LightningEarthquake Def. Authority Flooding Tornado Hurricane Forest
Fire
Number of Deficiencies = 2
Accessible Parking: Accessible Slope:
Yes
Curb Cuts:
Yes
Ramps:
N/AYes
Site Accessible Route:
HISTORIC PRESERVATION
9. Electrical (Communication/Alarm/Security)
NATURAL HAZARDS
Yes
Central
VOIP
System Capacity Adequate System Condition
GoodYes
8. Electrical (Site Lighting)
Roadways Parking Walkways Building Outdoor Sports
Mounting
Control
Pole Pole Pole & Bollard Building Sport Light
Photocell, Time Clock Photocell, Time Clock Photocell, Time Clock Photocell, Time Clock Time Clock, Switch
System Ownership Maintenance Responsibility System Capacity Adequate System Condition
Center Center Yes Good
Comments: There are flood lights at the center main entrance. Four pole-mounted lights at the south and southwest perimeter are solar powered lights. The center owns and maintains all site lighting.
Number of Deficiencies = 1
Number of Deficiencies = 3
STORAGE TANKS: None
Fire Alarm Security
Page: 4 Date: 01/23/2013 of 4
GENERAL SITE CONDITION
Rating X Good Fair Poor
The site condition is not impacting the functional use of the facilities.
The site condition IS impacting the functional use of the facilities.
The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.
Building Descriptions and Utilities
BUILDING A ADMIN & MEDICAL/DENTALBUILDING A - ADMIN. & MEDICAL/DENTAL
Building Descriptions
Page: 1 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Concrete
Stucco
Wall Roof Batt Rigid
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Business 9,675 6,075 1 Owned 1994 Not Evaluated
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Material
The reduction from 40 to 30 years of the metal roof life expectancy is due to impacts of heavy rain and wind.
The built-up roof was re-coated in 2006 and the estimated roof life is based on visual observation during the March 2012 Facility Survey.
Drainage Year Life
Remaining Type Area Served
Metal
Built-up Roofing
Surface Run-off
Scuppers and Downspouts
Arched
Flat
Breezeway
Entire Building
Number of Deficiencies = 1
Comments:
Comments:
3. Roof
Entire Building
Area Served
Page: 2 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
Comments: Windows have hurricane shutters.
INTERIOR FINISH
Carpet Ceramic Tile Concrete Vinyl Tile Wood
CMU Drywall Wallpaper Covering
Metal Unit - Metal Frame Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Storefront Frame Wrought Iron Fencing Gate - Metal Frame
Fixed - Aluminum Frame; Single Glazing; Sliding - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Number of Deficiencies = 1
Exterior Doors5.
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Five vertical air-handling units (AHU-1 through AHU-5) with duct mounted electric resistance heating coils provide heating and fresh air to the medical/dental and administration wings. These are located in the east and west mechanical rooms. The typical air-handling units are Trane models TWE060C150C0, TWE042C14 and Carrier model NFCP4800C2.
Comments:
HVAC
Heat1.
Electric Resistance
Single Duct None Electric Mechanical None Entire Building
Ceilings
Page: 3 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
Mechanical
Mechanical
Mechanical
Toilet/Shower
Dark Room
Electrical Room
Ventilation Area Served
Split Direct Expansion (Air
Source)
Split Direct Expansion (Air
Source)
Single Duct
Fan Coil
None
Refrigerant
Electric
Electric
Mechanical
Natural
None
None
Entire Building
Electronic Equipment
Room
Exhaust Ventilation
Five split-systems with DX-cooling coils mounted on the discharge provide cooling and fresh air to the medical/dental and administration wings. The typical air-handling units are Trane models TWE060C150C0, TWE042C14 and Carrier model NFCP4800C2. These are located in the east and west mechanical rooms. The outdoor condensing units (R-22 refrigerant) are Trane model 2TTA0042A4000AA, 3.5-ton, built in 01/2008, Trane model 2TTA3060A4000AA, 5-ton, built in 12/2008, Trane model TTA060C400A0, 5-ton, built in 05/1993, and Rheem model RAKA-060DAS, 5-ton, built in 09/1997. These are located in the east and west equipment yards.
A split system provides supplemental cooling to the copy machine/computer room. The condensing unit, Mitsubishi model MUY-D36NA, R-410A refrigerant, built in 2008, provides 3-ton cooling to an indoor ductless evaporating unit, MSY-D36NA, built in 2008.
Comments:
Comments:
Ventilation2.
System Type
Number of Deficiencies = 1
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
3. Number of Deficiencies = 2Air Conditioning
Page: 4 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
Two 30-gallon capacity A. O. Smith electric water heaters (model ELJF30913, S/N MF93-0092548-913,
4.5 kW) provide domestic hot water to the medical/dental and administration wings. These are located in the east and west janitor closets. The water heater serving the medical/dental wing has an in-line circulating pump (B&G series 100 BNF1).
Comments:
Cast Iron None None
Electric Water Cooler Hose Bibb Lavatory Mop Sink Shower Sink Urinal Water Closet (Flush Valve)
None
None None ABC Type Fire Extinguisher
Comments: Service is brought from a pad-mounted transformer located outside the building. Service terminates in a 400A main distribution panel (MDP) located in the electrical room. Two 45 kVA step-down transformers provide 120/208V system for the building. A meter and a C/T cabinet are installed near the pad-mounted transformer. This transformer also serves Educ/Voc/Day Care Center Building B with a separate meter.
Copper Copper Electric None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
High Intensity Discharge (HID)
Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by time clock and photocells. There are some bollards along the walkway in front of the building.
Main Distribution Panel 277/480V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 1
Fuel Distribution4.
FIRE PROTECTION
ELECTRICAL SERVICES
Exterior Lighting1.
LIGHTING
Page: 5 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
FIRE ALARM
Comments: The central fire alarm control/annunciator panel (FACP) is a Simplex 4002, located in the reception area.
The fire alarm control panels in buildings on center are connected to this central FACP.
Comments: The telephone service entrance and associated equipment is located in the electrical room. A CCTV camera is installed at the checkpoint outside the security office. A multi-display color monitor is located in the security manager office.
Audible Alarm Control/Annunciator Panel Duct Smoke Detector Heat Detector Manual Pull Station Smoke Detector Visual Alarm
Connected to Main System Closed Circuit TV None Satellite Dish
Telephone Security Public Address Television
Comments: Recorded footcandle levels include natural light contribution.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Compact Fluorescent
Offices
Medical/Dental
Reception
Mail Room
Wards (Patient)
Equipment Rooms (Elec/Mech)
Toilets
Corridors & Stairs
Storage Rooms
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Emergency Exit
Interior Lighting2. Number of Deficiencies = 1
Emergency /Exit Lighting3.
COMMUNICATION
Electric Water Gas No N/AYes
BUILDING UTILITY METERING
Type Location None None
Comments: There is no plausible means by which harmful levels of CO could enter the male and female wards.
CARBON MONOXIDE DETECTION
Page: 6 of 47
Building: A - ADMIN. & MEDICAL/DENTAL
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Structure: Good Exterior: Good Interior: Good Mechanical: Good Electrical: Good
BUILDING B EDUC/VOC/DAY CARE CENTERBUILDING B - EDUC/VOC/DAY CARE CENTER
Page: 7 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Concrete
Stucco
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Business & Day Care 24,430 16,430 1 Owned 1994 Not Evaluated
Comments: The public restroom is accessible except that the exposed pipes under the lavatory are not padded.
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Material
The reduction from 40 to 30 years of the metal roof life expectancy is due to impacts of heavy rain and wind.
Drainage Year Life
Remaining Type Area Served
Built-up Roofing
Metal
Built-up Roofing
Built-up Roofing
Scuppers and Downspouts
Gutters and Downspouts
Surface Run-off
Scuppers and Downspouts
Flat
Arched
Flat
Flat
Classrooms & Offices
Classrooms
Breezeways
Day Care
Number of Deficiencies = 3
Comments:
3. Roof
Page: 8 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
Wall Roof Batt Rigid
Comments: Windows of the classrooms have hurricane shutters.
INTERIOR FINISH
Carpet Ceramic Tile Concrete Vinyl Tile Wood
CMU Drywall
Metal Unit - Metal Frame Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Storefront Frame Wood Unit - Metal Frame
Fixed - Aluminum Frame; Single Glazing; Single Hung - Aluminum Frame; Single Glazing;
Sliding - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Insulation4.
Exterior Doors5.
Windows6. Number of Deficiencies = 1
Floors1.
Interior Walls2. Number of Deficiencies = 1
3.
Interior Doors4.
Page: 9 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
Mechanical
Mechanical
Restroom
Kitchen
Comments: The kitchen in the day care center is provided with a hood and an exhaust ventilation system.
Ventilation Area ServedExhaust Ventilation
Number of Deficiencies = 3
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
A rooftop-packaged unit (RTU-B-1) with electric resistance heating coils provides heating and fresh air to the career transition resource area. The unit is a Trane model TCD1208400CA, built in 07/1993.
Seven vertical air-handling units (AHU-B2 through AHU-B5 and AHU-B11 through AHU-B13) with duct mounted electric resistance heating coils provide heating and fresh air to the CDC and SIA Tech.
These are located in the south mechanical room and central mechanical room near the career prep.
218. The typical air-handling units are Trane models TWE048C140, TWE060D150C0, TWE120B100BA and TWE180B400BB, built in 1993 and range from 12 kW through 15 kW heating capacity.
Five vertical air-handling units (AHU-B6 through AHU-B10) with duct mounted electric resistance heating coils provide heating to the vocational classrooms 218 through 222. These are located in the individual mechanical rooms. The typical air-handling units are Trane models TWE090B300BA and TWE060E400BA, built in 07/1993 and range from 5 kW through 10 kW heating capacity.
Electric radiant heat panel provides additional heat in the infant change room.
Comments:
Comments:
Comments:
Comments:
HVAC
Heat1.
Electric Resistance
Electric Resistance
Electric Resistance
Electric Resistance
Single Duct
Single Duct
Single Duct
Radiant Panel
None
None
None
None
Electric
Electric
Electric
Electric
Mechanical
Mechanical
Mechanical
Natural
None
None
None
None
Classrooms and Offices
Day Care
Classrooms
Day Care
Ventilation2. Number of Deficiencies = 2
Page: 10 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
Packaged Direct
Expansion (Air Source)
Split Direct Expansion (Air
Source)
Split Direct Expansion (Air
Source)
Split Direct Expansion (Air
Source)
Single Duct
Single Duct
Single Duct
Fan Coil
None
Refrigerant
Refrigerant
Refrigerant
Electric
Electric
Electric
Electric
Mechanical
Mechanical
Mechanical
Natural
None
None
None
None
Classrooms and Offices
Day Care
Classrooms
Classrooms
A rooftop-packaged unit (RTU-B-1) provides DX-cooling and fresh air to the career transition resource area. The unit is a Trane model TCD1208400CA with 10-ton cooling capacity, built in 07/1993.
Seven split-systems with DX-cooling coils mounted on the discharge provide cooling and fresh air to the CDC and SIA Tech. The typical air-handling units are Trane models TWE048C140, TWE060D150C0, TWE120B100BA and TWE180B400BB, built in 1993. These are located in the CDC and SIA Tech mechanical rooms. The typical outdoor condensing units (R-22 refrigerant) are Trane models 2TTA0048A4000A, 4-ton, built in 10/2005, TTA120B400BA, 10-ton, built in 07/1993 and 7/2004, TTA180B400BA, 15-ton, built in 07/1993, and Rheem models UAKA-060DAZ, 5-ton, built in 0/2003, and RAKB-060DAZ, 5-ton, built in 04/2007. These are located in the CDC and SIA Tech equipment yards.
Five split-systems with DX-cooling coils mounted on the discharge provide cooling to the vocational classrooms 218 through 222. These are located in the individual mechanical rooms. The typical dual circuit air-handling units with a split face DX-coil are Trane models TWE090B300BA, 7.5-ton and TWE060E400BA, 5-ton, built in 07/1993. The typical outdoor condensing units (R-22 refrigerant) are Trane models 2TTA3036A000AA, 3-ton, built in 03/2005 and 03/2009, 2TTA0048A4000AA, 4-ton, built in 10/2005 and 01/2006, and Rheem model RAKB-048DAZ, 4-ton, built in 02/2000. These are located in the west equipment yards.
A split system provides supplemental cooling to the math classroom 202. The condensing unit, Mitsubishi model MUY-D36NA, R-410A refrigerant, provides 3-ton cooling to an indoor ductless evaporating unit, MSY-D36NA.
Comments:
Comments:
Comments:
Comments:
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area
3. Number of Deficiencies = 3Air Conditioning
Page: 11 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
An 80-gallon capacity A. O. Smith electric water heater (model EES 80913, S/N ML93-0053743-913,
4.5 kW) located in the south hot water heater room provides domestic hot water to the building.
Comments:
Cast Iron None None
Electric Water Cooler Hose Bibb Lavatory Mop Sink Sink Urinal Water Closet (Flush Valve)
None
None None ABC Type Fire Extinguisher, K Type Fire Extinguisher, Wet Chemical
Copper Copper Electric None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 2
Fuel Distribution4.
FIRE PROTECTION
Location UL300 Compliance Status Day Care Center Kitchen Non-Compliant
Comments: The kitchen hood is equipped with an Ansul R-102 wet chemical fire suppression system although the hood type and type of cooking do not require the system to be UL-300 rated.
UL300 COMMERCIAL KITCHEN HOOD FIRE SUPPRESSION
Page: 12 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
Comments: Service is brought from a pad-mounted transformer located outside the building. Service terminates in a 700A main distribution panel (MDP) located in the electrical room. Two 45 kVA step-down transformers provide 120/208V system for the building. A transient voltage surge suppression (TVSS) device is installed next to a panel that serves computer and sensitive electronic loads. A meter and a C/T cabinet are installed near the pad-mounted transformer. This transformer also serves Admin. & Medical/Dental Building A with a separate meter.
FIRE ALARM
Comments: The fire alarm control/annunciator panel (FACP) is a Simplex 4002, located in the lobby of the education area. This FACP is connected to the central FACP located in Admin. & Medical/Dental Building A.
Comments: TV with VCR and computer work stations are provided in the library and the classrooms.
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
Audible Alarm Control/Annunciator Panel Duct Smoke Detector Heat Detector Manual Pull Station Smoke Detector Visual Alarm
Connected to Main System None None Satellite Dish
Telephone Security Public Address Television
Comments: Recorded footcandle levels include natural light contribution.
Comments: Selected fluorescent lights with battery are also provided in some areas.
High Intensity Discharge (HID)
Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by time clock and photocells. There are some bollards along the walkway in front of the building.
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Offices
Classrooms
Corridors & Stairs
Childcare
Storage Rooms
Equipment Rooms (Elec/Mech)
Toilets
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Main Distribution Panel 277/480V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Emergency Exit
ELECTRICAL SERVICES Number of Deficiencies = 1
Exterior Lighting1.
Interior Lighting2. Number of Deficiencies = 2
Emergency /Exit Lighting3.
COMMUNICATION
Page: 13 of 47
Building: B - EDUC/VOC/DAY CARE CENTER
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
Electric Water Gas No N/AYes
BUILDING UTILITY METERING
BUILDING C FEMALE DORMITORYBUILDING C - FEMALE DORMITORY
Page: 14 of 47
Building: C - FEMALE DORMITORY
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Concrete
Stucco
Wall Roof Batt Rigid
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Residential 11,855 8,260 1 Owned 1994 Not Evaluated
Comments: The public restroom is accessible except that the exposed pipes under the lavatory are not padded.
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Material
The reduction from 40 to 30 years of the metal roof life expectancy is due to impacts of heavy rain and wind.
Drainage Year Life
Remaining Type Area Served
Metal
Built-up Roofing
Surface Run-off
Scuppers and Downspouts
Arched
Flat
Lobby, Corridors
Dorm Rooms, Lounges
Number of Deficiencies = 1
Comments:
3. Roof
Page: 15 of 47
Building: C - FEMALE DORMITORY
INTERIOR FINISH
Ceramic Tile Concrete Vinyl Tile
CMU Ceramic Tile Drywall
Folding - Metal Frame Metal Unit - Metal Frame
Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Aluminum Frame
Fixed - Aluminum Frame; Single Glazing; Sliding - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Exterior Doors5.
Windows6. Number of Deficiencies = 1
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Four horizontal ceiling hung air-handling units (AHU-C2 through AHU-C5) with duct mounted electric resistance heating coils provide heating and fresh air to the orange and yellow wings. These are located in the south and north storage rooms. The typical air-handling unit is a Trane model TWE060C150C0, built in 03/1993.
A vertical air-handling unit (AHU-C1) with duct mounted electric resistance heating coils provides heating and fresh air to the lobby, RA offices and study room. The unit is a Trane model TWE120B300BA, built in 03/1993. It is located in the west mechanical room behind the laundry.
Comments:
Comments:
HVAC
Heat1.
Electric Resistance
Electric Resistance
Single Duct
Single Duct
None
None
Electric
Electric
Mechanical
Mechanical
None
None
Dorm Rooms
Common Area
Page: 16 of 47
Building: C - FEMALE DORMITORY
Mechanical
Mechanical
Toilet/Shower
Equipment Room
Ventilation Area Served
Split Direct Expansion (Air
Source)
Split Direct Expansion (Air
Source)
Single Duct
Single Duct
Refrigerant
Refrigerant
Electric
Electric
Mechanical
Mechanical
None
None
Dorm Rooms
Common Area
Exhaust Ventilation
Four split-systems with DX-cooling coils mounted on the discharge provide cooling and fresh air to the orange and yellow wings. The typical air-handling unit is a Trane model TWE060C150C0, built in 03/1993. These are located in the south and north storage rooms. The typical outdoor condensing units (C-2 through C-5, 5-ton, R-22 refrigerant) are Trane models TTA060C300A0, built in 07/1993, 2TTA060A3000AA, built in 06/2005 and 7/2007, and Goodman model GSC130601CA, built in 12/2009.
These are located in the north equipment yard.
A split-system with DX-cooling coils mounted on the discharge provides cooling and fresh air to the lobby, RA offices and study room. The dual circuit air-handling unit with a split face DX-coil is a Trane model TWE120B300BA, 10-ton, built in 03/1993. It is located in the west mechanical room behind the laundry. The two outdoor condensing units (C-1A and C-1B, 5-ton each, R-22 refrigerant) are Trane models TTA060C300A0, built in 07/1993, and 2TTA3060A3000AA, built in 01/2008. These are located in the north equipment yard.
Comments:
Comments:
Ventilation2.
System Type
Air Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area
3. Air Conditioning
Page: 17 of 47
Building: C - FEMALE DORMITORY
Two 91-gallon capacity Rheem-Ruud gas-fired water heaters (model G91-200-1, S/N URNG1104G00511 and 1104900509, 119 MBH gas input and 193.8 GPH recovery) provide domestic hot water to the building. These are located in the west hot water heater room. Each heater's hot water loop has an in-line circulating pump (Grundfos UPS1558FC).
Comments:
Cast Iron None None
Bathtub Electric Water Cooler Hose Bibb Lavatory Mop Sink Shower Sink Water Closet (Flush Valve)
Gas (Natural)
Comments:
None None ABC Type Fire Extinguisher
Comments: Service is brought from a pad-mounted transformer located in the back of the building. Service terminates in a 600A main distribution panel (MDP) located in the electrical room. A meter and a C/T cabinet are installed near the pad-mounted transformer. This transformer also serves Male Dormitory Building D with a separate meter.
Copper Copper Gas-Fired None No
Hot Water Cold Water Water Heater Water Treatment HW Storage Tank
Grease InterceptorWaste / Vent Interior Storm
Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices
High Intensity Discharge (HID)
Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by time clock and photocells.
Main Distribution Panel 120/208V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches
Sprinkler System Stand Pipe System Fire Suppression
PLUMBING Number of Deficiencies = 1
Water Distribution1.
Sanitary Distribution2.
Fixtures3. Number of Deficiencies = 2
Fuel Distribution4.
FIRE PROTECTION
ELECTRICAL SERVICES
Exterior Lighting1.
The gas meter is located near the west mechanical room with a pressure regulator valve.
Page: 18 of 47
Building: C - FEMALE DORMITORY
FIRE ALARM
Comments: The fire alarm control/annunciator panel (FACP) is a Simplex 4002, located in the RA office. This FACP is connected to the central FACP located in Admin & Medical/Dental Building A.
Comments: Public pay phones have been removed by the telephone company due to a significant drop in usage.
Students make phone calls either with their own cell phones or center phones on a limited case-by-case basis.
Audible Alarm Control/Annunciator Panel Duct Smoke Detector Heat Detector Manual Pull Station Smoke Detector Visual Alarm
Connected to Main System None None Satellite Dish
Telephone Security Public Address Television
Comments: Recorded footcandle levels include natural light contribution. In addition to recessed compact fluorescent lights in the low ceiling areas, the two-story high main lobby has surface-mounted HID light fixtures. The corridors in both dormitory wings have recessed compact fluorescent and decorative wall sconces.
T8 - Fluorescent
T8 - Fluorescent
Compact Fluorescent
T8 - Fluorescent
T8 - Fluorescent
Compact Fluorescent
Compact Fluorescent
Compact Fluorescent
T8 - Fluorescent
T12 - Fluorescent
Sleeping Rooms
Offices
Housing Lounge
Study Room
Laundry Room
Corridors & Stairs
Toilets
Shower
Storage Rooms
Equipment Rooms (Elec/Mech)
Area Recommended Level
Recorded Level Light Type
Battery Backup Battery Backup
Emergency Exit
Number of Deficiencies = 1
Interior Lighting2.
Emergency /Exit Lighting3.
COMMUNICATION
Electric Water Gas No YesYes
BUILDING UTILITY METERING
Type Location N/A N/A
Comments: There is no plausible means by which harmful levels of CO could enter sleeping rooms.
Page: 19 of 47
Building: C - FEMALE DORMITORY
GENERAL BUILDING CONDITION
Rating X Good
Fair Poor
The facility condition is not impacting the functional use of the facility.
The facility condition IS impacting the functional use of the facility.
The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.
BUILDING D MALE DORMITORYBUILDING D - MALE DORMITORY
Page: 20 of 47
Building: D - MALE DORMITORY
BUILDING ENVELOPE
Foundation RoofBuilding
Concrete Loadbearing Masonry Concrete
Stucco
Wall Roof Batt Rigid
AccessibilityFeature
GSF NSF Year Built Use Group Historic Ownership#Floors
Residential 20,460 12,505 1 Owned 1994 Not Evaluated
Comments: The public restroom is accessible except that the exposed pipes under the lavatory are not padded.
REAL ESTATE
Access to Building
Ramps
Entrance
2nd Egress
Visual Alarm
Corridor/Aisle
Rooms
Stairs
Elevator
Restrooms
Drinking Fountain
Telephone
Yes
N/A
Yes
Yes
Yes
Yes
Yes
N/A
N/A
Yes
Yes
N/A
ACCESSIBILITY
Structural Systems1.
Exterior Walls2.
Insulation4.
Material
The reduction from 40 to 30 years of the metal roof life expectancy is due to impacts of heavy rain and wind.
Drainage Year Life
Remaining Type Area Served
Built-up Roofing
Metal
Scuppers and Downspouts
Surface Run-off
Flat
Arched
Dorm Rooms, Lounges
Lobby, Corridors
Number of Deficiencies = 1
Comments:
3. Roof
Page: 21 of 47
Building: D - MALE DORMITORY
INTERIOR FINISH
Carpet Ceramic Tile Concrete Vinyl Tile
CMU Ceramic Tile Drywall
Folding - Metal Frame Metal Unit - Metal Frame
Wood Unit - Metal Frame
VERTICAL CIRCULATION
None
Metal Unit - Metal Frame Storefront - Aluminum Frame
Fixed - Aluminum Frame; Single Glazing; Sliding - Aluminum Frame; Single Glazing;
Acoustical Tile Exposed Structure Gypsum Board
Exterior Doors5. Number of Deficiencies = 1
Windows6.
Floors1.
Interior Walls2.
3.
Interior Doors4.
Heat Source
Heat Distribution
Piping System
Control System
Fresh Air Intake
Energy Conservation
Measure
Area Served
Six horizontal ceiling hung air-handling units (AHU-D2, D3, D4, D5, D7 and D8) with duct mounted electric resistance heating coils provide heating and fresh air to the peach, yellow and green wings.
These are located in the east, west and south storage rooms. The typical air-handling units are Trane model TWE060C150C0, built in 03/1993 and Nordyne model GB3BV060KCB, built in 10/2005.
Two vertical air-handling units (AHU-D1 and AHU-D6) with duct mounted electric resistance heating coils provide heating and fresh air to the lobby, offices and study room. The typical unit is a Trane model TWE120B300BA, built in 03/1993.