AMENDMENT 3 Q As
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OM_Attachment_I_QA_dever.docx | DOCX document | |
| SOW_Attachment_B_Fire_Alarm_ _Sprinkler_Riser.pdf | ||
| SF_30_(2).pdf | ||
| Round_2 _Part_2_Q As.docx | DOCX document | |
| SF_30_(2).pdf | ||
| ROUND_2_All_QUESTIONS_ _Responses_.docx | DOCX document | |
| Site_Visit_Sign_in_Sheet_5_5_2015.pdf | ||
| Site_Visit_agenda_with__Q_ A_5.5.2015.docx | DOCX document | |
| SF_30_(2).pdf | ||
| SF_30_(2).pdf | ||
| Attachment_L_-_ARQ_(Section_K).pdf | ||
| SF_30.pdf | ||
| Attachment_A_of_SOW_Equipment_inventory.pdf | ||
| SF_30.pdf | ||
| Liberty_Park_CBA_2015_-_2016.pdf | ||
| O M_Attachment_J_SF33_(2).pdf | ||
| O M_Attachment_K _Past_Performance.docx | DOCX document | |
| O M_RFP_4-22-2015.docx | DOCX document | |
| O M_Attachment_F.1_DD254.pdf | ||
| O M_Attachment_I _QA_Template.docx | DOCX document | |
| O M_Attachments_D1-D7.pdf | ||
| O M_Attachment_G _Labor_Wage.pdf | ||
| O M_Attachment_E_SOW_April_22_2015_Final.docx | DOCX document | |
| O M_Attachments_D8-D13.pdf | ||
| O M_Attachment_H _VAR.pdf |
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT I - QUESTIONS AND ANSWER TEMPLATE
TSC FACILITY O&M RFP # DJF-15-4400-PR-0023541
AMENDMENT #3, MAY 1, 2015, Q&As
| QUESTION NUMBER |
| DOC NAME (RFP or Attachment |
| PAGE # OR SECTION # |
| RESPONDENTS QUESTION |
| GOVERNMENT’S RESPONSE |
| 1 |
| Solicitation Number: DJF-15-4400-PR-0023541 |
SOW
| Page 11 z..Environmental Services for Emergency Electrical Systems |
| a) Is the Contractor responsible for coordination of all inspections from the EPA, OSHA, and FBI Compliance? |
b) What is the Contractors level of responsibility for any fine and/or penalties?
a) Yes
b) The Contractor may be penalized accordingly for any violations of laws, rules or standards, along with non-compliance with the Sow.
| 2 |
| SOW |
| Section E Item g. |
a) Is there a requirement for Diesel Fuel Testing?
b) Is so, what is the frequency?
a) Yes
b) Annually
| 3 |
| SOW |
| Section F |
8.1.4
a) What is the level of service expected from Contractors regarding 8.1.4?
b) Please provide the quantity of gates, turnstiles, traffic lights, barriers, and controls.
c) What is the response time for after hour repair service regarding 8.1.4 service?
a) Refer to 9.2 on page 32 of the SOW. The Government’s expectation is that if a priority/emergency response is deemed necessary due to a malfunction or breakdown of any building system, response will be immediate and work will continue until the system is restored to fully functioning capabilities.
b) The equipment listed below was inadvertently omitted from the SOW Attachment A Equipment Inventory Table 4.1.T, and is hereby incorporated into it via this amendment:
· Delta 501 Dual Wedges w/HPU (total # is 2)
· Delta 501 Single Wedges w/HPU (total # is 2)
· Delta DSC 1200 Single Wedges w/HPU (total # is 2)
· Single Barrier Arm Gate Operators (total # is 5)
· Hy Security Single Slide Gates (total # is 4)
· Tomsed Single Turnstile (total # on-site is 2)
· Pedestrian/Walk Gate (total # is 2) Reference SOW 9.2 on page 32.
| 4 |
| RFP |
| Section B, Page 3 |
| Please provide a list of what is included in the Government Required Monthly Materials ($144,000.00 per year). |
| This list refers to a specified monthly allowance of $12K monthly ($144K annually) for materials to complete daily work orders generated by the facility management office. Reference SOW 1.2 on page 4. |
| 5 |
| General Question |
| Must all staff associated with this contract possess a TS/SCI clearance at the start of the contract? |
| All Key Management Personnel must be cleared (possess a TS/SCI clearance) at time of proposal submission. In addition, as stated in RFP Sections L.26.1 and M.3.3…ensure that all Corporate personnel matters of security are favorably adjudicated within 15 working days of contract performance (25% at contract start date, 50% within 2 weeks of contract start date and 100% by the end of week 3)”. |
| 6 | |
| RFP | |
| Page 44 of Section L.9(d) | |
| (L.9 (d) | Asks that Contractors complete and submit ACH/EFT Form- SF 3881 in Attachment A. Please provide a copy of this Attachment. |
Embedded in the 4/22 RFP there is an Attachment A (Page 66) right after the title “Attachment A - ACH Vendor/Miscellaneous Payment Enrollment Form”.
| 7 |
| RFP |
| K.4 , K.6 and K-9 |
| Please confirm that ACQUISITION RISK QUESTIONS that are to be submitted should be filled in using Section K.9 beginning on Page 34. No attachment for ACQUISITIN RISK QUESTIONS is included in the solicitation documents. |
| See added Attachment L titled “Section K - Acquisition Risk Questions”. |
| 8 |
| RFP |
| Page 44 of Section L.9(e) |
| Please confirm that the Key Management Personnel List (KMPL) Form referenced as attachment D-7 is actually Attachment D-13? |
| Correct. The KMPL Form referenced as attachment D-7 on page 44 of Section L.9 (e) should read Attachment D-13. |
General Question
| Please provide the anticipated Start Date of the contract. |
| Intend to award the contract in FY15, with an anticipated kick-off meeting within a week after award, and a start date one (1) week later. |
| 10 |
| RFP |
| Page45 |
l.9(k)
| Please clarify if Contractors are also required to deliver all information electronically via e-mail to Karen.king@ic.fbi.gov in addition to hard copies and disks delivered as instructed? |
| Yes. All information shall also be delivered to Karen.king@ic.fbi.gov electronically via e-mail, in addition to the hard copies and disks delivered as instructed. |
General Question Regarding the complex high density Liebert cooling system:
a) Is there a requirement for the company to have a Liebert “LSPN” Liebert Service Provider Network designation?
b)Is the contractor required to have factory trained and certified technicians working on this equipment?
a) No
b) Yes
| Attachment_A_of_SOW_Equipment_inventory |
| Please note that the following seems to be missing from the Equipment Inventory, please revise the list or comment on the Contractors responsibility regarding this equipment? |
· Quantity (2) Fresh Air Intake with charcoal filter housing in the penthouse.
· Quantity (6) Delta Barriers
· Quantity (3) Sliding vehicle gates
· Quantity (1) Pedestrian gate
· Quantity (1) Guard booth with power and AC/Heat
· Battery (1) Monitoring System
The equipment listed to the left was inadvertently omitted from the SOW Attachment A Equipment Inventory Table 4.1.T, and is hereby incorporated into it via this amendment.
| 13 |
| RFP |
| Section M.2, Page 61 |
| This Section states that “The offeror will demonstrate experience level and shall submit a minimum of three (3) projects being performed in a secure environment requiring a security clearance at a level of no less than a Single Scope Investigation. The completed projects for the experience level must be similar in size nature…” |
Are 3 TS cleared projects of equal size and scope indeed required for an offeror to be considered qualified?
The Government hereby removes the “Single Scope Investigation” requirement. The following revised language is hereby incorporated in place of the language italicized in your question, in Section M.2: “The Offeror will demonstrate experience level and shall submit a minimum of three (3) projects being performed in a secure environment requiring a security clearance. The completed projects for the experience level must be similar in size nature (in terms of dollars also) to in value but not be limited to the following…” In addition, the 2nd sentence in RFP Section L.28.2 is hereby revised to read “The Offeror shall include past performance (for contracts performed in a secure environment that required a security clearance), that reflects relevance to requirements of the solicitation on the basis of similarity in size, scope, complexity, technical difficulty, contract type, dollar value and period of performance.