Attch_D_Submittal_Log.pdf
PDF 76 KB Posted
- Attached to
- Tucson Substation Stage 02 Federal contract opportunity
- Solicitation number
- DE-SOL-0009771
About this file
Submittal Log
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2.pdf | ||
| Amendment_2_Revised_Bidding_Schedule.pdf | ||
| Amendment_001_Attch_A_Specifications_7_8_16.pdf | ||
| Ammendment_001_Pre-bid_Sign-in.pdf | ||
| Amendment_001.pdf | ||
| Attch_E__Foreign_National_Data_Card.pdf | ||
| Attch_F_o442_21.pdf | ||
| Attch_B_Drawings.pdf | ||
| Attch_C_Wage_Determination.pdf | ||
| Attch_G_Tucson_Sub_Geotechnical_Report.pdf | ||
| Attch_A_Specifications_6_16_16.pdf | ||
| DE-SOL-0009771.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Title: TUCSON SUBSTATION, STAGE 02 Award Date:
Contract No.: NTP:
Contractor: Completion Date:
Contractor's Western's Location Date Submittal Item In Date Approved
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS
STANDARD 1
1 Construction Schedule 1.1.4.1. (see project spec)
2 Survey Plan 1.1.5.2.(1) Prior to survey work
3 Survey Notes 1.1.5.5. & 1.1.5.7. Immed. upon completing
4 Survey Data Collector Dump & Computer Printout 1.1.5.6. Immed. upon completing
5 Survey Field Book 1.1.5.7. Immed. upon completing
6 Breakdown of Contract Prices 1.1.6.1. NLT 30-days after NTP
7 Electrical Equipment & Steel Purchase Orders 1.2.3.1. NLT 10-working-days after PO award
8 Cable Location Plan w/Print of Locations 1.3.4.2 & 1.4.5.2 Prior to starting excavation
9 Acknowledgement When Stringing Over Energized Lines 1.3.5.3. Prior to starting stringing
10 Safety and Health Program 1.4.1.5. NLT 10-days prior to start of construction
11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use
12 - Load Performance Tests 1.4.1.10.(1) Prior to use
13 - Crane & Aerial Lift Equipment Annual Inspection Records 1.4.1.10.(2) Prior to use
14 - Brake Performance Test 1.4.1.10.(3) Prior to use
15 - Test Results of Protective Ground Leads 1.4.1.10.(4) Prior to use
16 - Material Safety Data Sheets 1.4.1.10.(5) Prior to use
17 - Manufacturer's Load Rating For Hoists and Grips 1.4.1.10.(6) Prior to use
18 - Certification of Fabricated Lifting and Rigging Devices 1.4.1.10.(7) & 1.4.11 Prior to use
19 - Medical Examiner's Certificate 1.4.1.10.(8) & 1.4.3.3 Prior to use
20 - Data For Excavation Protective System 1.4.1.10.(9) & 1.4.5.5 Prior to use
21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use
22 Respiratory Protection Program 1.4.4.8 Prior to work requiring resp.
protection
23 Structure Erection Plan 1.4.8.1. Prior to structure erection
24 Suspended Work Cart Work Procedure 1.4.12 Prior to use
25 Helicopter Operations and Safety Program 1.4.13 NLT 15-days prior to helicopter operations
SUBMITTAL TRACKING SHEET
Contractor's Western's Location Date Submittal Item In Date Approved
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS 26 Protective Ground Lead Test Results & Certification 1.4.14.3. Prior to use
27 Clearance, Hot Line Order & Special Work Permit Requests 1.4.15.3. NLT 10-working-days prior to starting work
28 Stringing Plan 1.4.17.3. Prior to stringing
29 HLO/Clearance Approval or Denial From Other Utilities 1.4.17.4.(3) 1) Prior to stringing
30 Transmission Line Removal Plan 1.4.18 Prior to removal
STANDARD 2
31 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 20-days prior to compacting
32 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. Immed. after test complete
33 Gravel Surfacing Material Gradation 2.1.1.4 Prior to placing
34 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 NLT 7-days after test complete
35 Herbicide Applicator's References 2.1.1.5.(1) & 2.11.3.2. NLT 30-calendar-days prior to application
36 Herbicide Applicator's Certification/License 2.1.1.5.(2) NLT 30-calendar-days prior to application
37 Herbicide Application Plan 2.1.1.5.(3) NLT 30-calendar-days prior to application
38 Herbicide Application Final Report 2.1.1.5.(4) NLT 7-days after application
39 Aggregate for Paving Courses 2.1.1.7.(4) NLT 20-days prior to paving
40 Gravel Base Certification 2.1.1.7.(5) NLT 20-days prior to paving
41 Batch Certification 2.1.1.7.(6) NLT 20-days prior to paving
42 Earth Backfill Material 2.3.1.3. & 2.8.1.2.(1) Prior to refill
STANDARD 3
43 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3. NLT 20-days prior to concrete placement
44 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10-days prior to use
45 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20-days prior to use
46 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10-days prior to use
47 Batch Certificates 3.1.1.2.(7) Provide at delivery
48 Test Reports 3.1.1.2.(8) Immed. upon completing
49 Void Forming Material 3.1.1.2.(9) & 3.1.1.4. &
3.1.4.2. Prior to use
50 Nonshrink Grout 3.1.1.2.(10) Prior to use
51 Drawings & Data For Electrical Equip. Foundation Design 3.2.1.2. Prior to installation
52 Approval Drawings For Precast Cable Trench 3.2.1.3. Prior to precasting
53 Approval Drawings For Precast Concrete Pull Boxes 3.2.1.4. Prior to precasting
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS 54 Final Drawings For Precast Cable Trench & Pull Boxes 3.2.1.5. Prior to material shipment
STANDARD 4
55 Approval Drawings For Steel Structures & Steel Modifications 4.1.1.2. Prior to fabrication
56 Approval Drawings & Data For Oil Storage Tanks 4.1.1.3. Prior to fabrication
57 Final Drawings For Steel Structures & Oil Storage Tanks 4.1.1.4. Prior to material shipment
58 Weld Procedures 4.1.1.5.(1) & 4.1.7.4. Prior to fabrication
59 Partial Penetration Weld - Test & Evaluation Procedure 4.1.1.5.(2) & 4.1.7.4. Prior to fabrication
60 Nondestructive & Metallographic Test Reports 4.1.1.5.(3) & 4.1.7.4. NLT 20-days after test
61 Connection Bolts 4.1.1.6. Prior to fabrication
62 Mill Test Reports 4.1.1.7. Prior to fabrication
63 Dulling Surface Treatment For Galvanizing 4.1.1.8. Prior to use
64 Tower Test Procedures 4.1.1.9.(1) Prior to testing
65 Calibration of Load Testing Devices 4.1.1.9.(2) NLT 5-days prior to testing
66 Tower Test Report 4.1.1.9.(3) NLT 4-weeks after testing
67 Certified Mill Test Reports 4.1.5.3. Prior to shipping material
68 Magnetic Particle and Dye Penetrant Weld Test (if required by COR) 4.1.7.5. Upon test completion
69 Master List of Bundles - Steel Structure & Tower Material 4.1.13 Upon completion of material bundling
STANDARD 5
70 Test & Evaluation Procedure For Partial Penetration Welds 5.1.1.4.(2) & 5.1.1.9. Prior to fabrication
71 Paints 5.1.1.6.(1) & 5.1.1.9. &
5.1.4.9. Prior to use
72 Material Safety Data Sheets 5.1.1.6.(2) & 5.1.1.9. Prior to use
73 Approval Erection Drawings 5.1.1.7.(1) & 5.1.1.9. Prior to fabrication
74 Approval Shop Detail Drawings 5.1.1.7.(2) & 5.1.1.9. Prior to fabrication
75 Final As-builts & Bill of Materials 5.1.1.8. & 5.1.1.9. Prior to final payment
STANDARD 9
76 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site
77 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7-days after testing
78 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) Prior to testing
79 Infrared Inspection Tape 9.1.2.2.(15) NLT 48-hours after testing
80 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. NLT 60-days after NTP
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS 81 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60-days after NTP
82 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21-days prior to equip.
installation
83 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21-days prior to equip.
installation
84 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21-days prior to equip.
installation
85 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5. Prior to shipping equipment
86 Equipment Insulating Liquid PCB Certification Table 9-1 & 9.1.3.6. Prior to delivery of oil or equip.
87 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60-days after NTP
88 Revised Wiring Diagrams Table 9-1 & 9.1.3.9. NLT 60-days after receipt of drawings
89 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60-days after equip.
checkout
90 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60-days after equip.
checkout
91 Test Reports For Ground Tests 9.2.1.3. NLT 15-days after completion of testing
STANDARD 10
92 Catalog Data Sheets of Accessories & Hardware Used In Conductor & Overhead Ground Wire Installation 10.2.2. NLT 40-days prior to material installation
93 Drawings of Insulator & Overhead Groundwire Assemblies and Details 10.2.2. NLT 40-days prior to material installation
94 Complete Material List 10.2.2. NLT 40-days prior to material installation
95 Conductor Insulator Assembly Test Reports 10.2.3.1. & 10.3.3. ASAP
96 Conductor Test Reports 10.2.3.2. & 10.6.1.2. ASAP
97 Overhead Ground Wire Test Reports 10.2.3.3. & 10.6.2.2. ASAP
98 Overhead Ground Wire Assemblies Test Reports 10.2.3.4. & 10.4.3. ASAP
99 Ground Resistance Measurements 10.2.3.5. & 10.5.3. ASAP
100 Vibration Damper Test Reports 10.2.3.6. & 10.6.4.3. ASAP
101 Conductor Spacer Damper Test Reports 10.2.3.7. & 10.6.6.2. ASAP
102 Optical Overhead Ground Wire Test Reports 10.2.3.8. & 10.6.3.2. ASAP
103 Assembly & Installation Instructions For Conductor Insulator Assemblies 10.3.4 NLT two-weeks prior to installation
104 Optical Overhead Ground Wire Suspension Clamp Attachment Assemblies 10.4.2.3. Prior to use
STANDARD 11
105 Wood Truss Shop Drawings 11.1.2.4. & 11.6.2.3.(1)
106 Steel Doors and Frames Shop Drawings 11.1.2.4. & 11.8.1.2.(1)
107 Access Flooring Shop Drawings 11.1.2.4. & 11.10.1.3.(1)
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS 108 Termite Control Product Data 11.1.2.5. & 11.2.3.3.(1)
109 Masonry Veneer Product Data 11.1.2.5. & 11.4.2.2.(1)
110 Miscellaneous Metals Product Data 11.1.2.5. & 11.5.1.2.
111 Preformed Roof Panels Product Data 11.1.2.5. & 11.7.2.2.(1)
112 Prefinished Plywood Soffit Product Data 11.1.2.5. & 11.7.3.2.(1)
113 Caulking and Sealants Product Data 11.1.2.5. & 11.7.4.2.(1)
114 Finish Hardware Product Data 11.1.2.5. & 11.8.2.2.(1)
115 Access Flooring Product Data 11.1.2.5. & 11.10.1.3.(2)
116 Emergency Spray Product Data 11.1.2.5. & 11.11.1.2.(1)
117 Mechanical, General Product Data 11.1.2.5. & 11.12.1.2.
118 Service Building Electrical, General Product Data 11.1.2.5. & 11.13.1.4.
119 Termite Control Installation Data 11.1.2.6. & 11.2.3.(2)
120 Masonry Veneer-Water Repellent Coating Installation Data 11.1.2.6. & 11.4.2.2.(3)
121 Masonry Veneer Samples 11.1.2.7. & 11.4.2.2.(2)
122 Preformed Roof Panel Samples 11.1.2.7. & 11.7.2.2.(3)
123 Prefinished Plywood Soffit Samples 11.1.2.7. & 11.7.3.2.(2)
124 Rubber Cove Base Samples 11.1.2.7. & 11.9.2.2.(1)
125 Access Flooring Samples 11.1.2.7. & 11.10.1.3.(3)
126 Finish Hardware Maintenance Material 11.1.2.8. & 11.8.2.2.(2)
127 Access Flooring Maintenance Material 11.1.2.8. & 11.10.1.3.(4)
128 Mechanical, General Maintenance Material 11.1.2.8. & 11.12.1.2.
129 Termite Control Test Reports 11.1.2.9. & 11.2.3.(4)
130 Mechanical, General Test Reports 11.1.2.9. & 11.12.1.2.
131 Project Record Documents 11.1.2.10.
132 Draft Operation and Maintenance Data For Emergency Spray 11.1.3.2.(1) & 11.11.1.2.(2)
133 Draft Operation and Maintenance Data For Mechanical, General 11.1.3.2.(1) & 11.12.1
134 Completed Operation and Maintenance Data For Emergency Spray 11.1.3.2.(1)
135 Completed Operation & Maintenance Data For Mechanical, General 11.1.3.2.(2)
136 Termiticide Applicator's Certificate/License 11.2.3.3.(3)
137 Preformed Roof Panel Shop Drawings 11.7.2.2.(2)
# # Submittal Item Standards Date Due Submitted Rejected COMMENTS 138 System Operational Manual 11.12.3.5.
STANDARD 12
139 Manufacturer's Data 12.1.1.2.
STANDARD 13
140 Recycled Materials Quantity Report 13.1.1. & 13.6. Prior to final payment
141 Products Containing Recovered Materials Report 13.1.2. & 13.7. Prior to final payment
142 Reclaimed Refrigerant Receipt & Technician Certification 13.1.3. & 13.8.
143 Spill Prevention Notification & Cleanup Plan 13.1.4. & 13.10.
144 Tanker Oil Spill Prevention & Response Plan 13.1.5. & 13.10.
145 Pesticide Use Plan 13.1.6. & 13.11.
146 Treated Wood Pole & Members Recycling Consumer Info. Receipt 13.1.7. & 13.12.
147 Asbestos Licenses or Certificates 13.1.8. & 13.14.
148 Lead Paint Notices 13.1.9. & 13.15.
149 Water Pollution Permits 13.1.10. & 13.16.
150 PCB Test Reports 13.1.11. & 13.17.
151 Oil & Oil-Filled Electrical Equipment Receipt 13.1.12. & 13.17.
152 Cleanup Work Management Plan 13.1.13. & 13.18.
153 Post Cleanup Report 13.1.14. & 13.18.
STANDARD 15
154 As-Built Drawings 15.2.6. Prior to final payment
"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable
Sheet1
File details come from the government source that posted it. Updated .