Amendment_001.pdf

PDF 105 KB Posted

Attached to
Tucson Substation Stage 02 Federal contract opportunity
Solicitation number
DE-SOL-0009771
Issued by
Department of Energy Western Area Power Administration

About this file

Amendment 001

View the file

Other files for this federal contract opportunity

Other files attached to Tucson Substation Stage 02, newest first.
File Type Posted
Amendment_2.pdf PDF
Amendment_2_Revised_Bidding_Schedule.pdf PDF
Amendment_001_Attch_A_Specifications_7_8_16.pdf PDF
Ammendment_001_Pre-bid_Sign-in.pdf PDF
Attch_E__Foreign_National_Data_Card.pdf PDF
Attch_A_Specifications_6_16_16.pdf PDF
DE-SOL-0009771.pdf PDF
Attch_F_o442_21.pdf PDF
Attch_D_Submittal_Log.pdf PDF
Attch_B_Drawings.pdf PDF
Attch_C_Wage_Determination.pdf PDF
Attch_G_Tucson_Sub_Geotechnical_Report.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DE-SOL-0009771

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PHOENIX AZ 85005-6457

DSW

PO BOX 6457

DESERT SOUTHWEST REGIONAL OFFICE

US DOE/WESTERN AREA POWER

WAPA (DSW)

07/11/2016000001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/17/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See continuation pages.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

07/11/2016

DE-SOL-0009771

Amendment 0001

This Amendment provides a copy of the Pre-bid Site Visit Attendance Register, responds to questions, extends the bid opening and replaces the specifications.

A. The date and time specified for the Bid Opening and receipt of Bids is hereby changed to July 21, 2016, 2:00 PM Local Time.

B. The Specifications are hereby replaced with the attached Specifications, dated July 8, 2016, 69 Pages.

Revisions have been denoted by a line in the right-hand margin.

C. A copy of the Pre-bid Site Visit Attendance Register is attached.

D. Below are responses to questions received related to Solicitation DE-SOL-0009771.

Q: Will the necessary hazardous material testing for the items being demolished be provided by the government or contractor?

A: Hazardous material testing, and information presently available, is addressed in Division 13.B.2. of the Specifications.

Q: Not knowing how much or what materials will be involved in bid item “0003 Remove Environmental Contaminates” what should we consider when pricing this bid item?

A: Project Specifications’ Division 13.B.2. addresses all work associated with Removal of Environmental Contaminates. In addition, refer to Drawings TUC2052 EI, TUC2052, TUC2053, TUC2054 EI, and TUC2055 EI.

Q: There appears to be a structure on the north side of the substation (see attached drawing) within the clouded scope of work that does not have structure type associated with it. If this is in the project scope can you please provide the structure type.

A: The structure is 24/16, and is shown on Drawing TUC 0011B.

Q: Where can one obtain a copy of Division 13 Standards?

A: Per the Specifications, all Divisions can be located using the following link: https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

Q: A lot of the big items on this one show as “Gov’t furnished.” Does WAPA already own or are they coming out on a separate RFQ?

A: All Government-furnished items have already been procured.

Q: Please confirm the distance between the existing fence and the new fence.

A: See "Fence Detail" on Drawing TUC 2053C.

Q: Is the new fence being installed on the exterior side or interior side of the existing fence?

A: See "Fence Detail" on Drawing TUC 2053C.

Q: Please confirm the distance between the existing fence and the new fence.

https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

Amendment 0001

DE-SOL-0009771

A: See "Fence Detail" on Drawing TUC 2053C.

Q: Is the new fence to be installed on the exterior side or interior side of the existing fence?

A: See "Fence Detail" on Drawing TUC 2053C.

Q: Depending on the location of the new fence, will there be an option of installing the new chain link fence fabric on either side of the new fence posts?

A: The fence fabric shall be installed on the outside of the new fence posts.

Q: In regards to the removal of the existing fence, should we also include the removal and disposal of concrete encasements for the metal fence posts or can the existing posts be cut at grade?

A: Existing fence posts and concrete footings shall be completely removed in accordance with Standard 2 – Sitework, paragraph 2.2.1.3.

Q: Please confirm the gate opening dimensions for the new double swing chain link gate.

A: The double gate opening shall be 24'-0" face of gate post to face of gate post.

Q: Please provide detail for isolation fences (at two locations). Drawing refers to Detail C (31 1501) but could not locate this detail.

A: Drawing 31 1501 is a standard Western drawing. Detail C is located to the right, and in the bottom half of the drawing page, entitled “Type 1 Fence Isolation Joint Detail”, with a drawing underneath.

Instructions for locating this drawings are given in Division 1 – General Requirements, paragraph A.

Q: Specifications page 14, Gravel Surfacing calls for 6” of gravel and 2” of crushed rock, the drawings show 6" total, also will the WAPA Standards for gravel apply with the PI requirements, or will a Arizona DOT spec. be acceptable.

A: "Gravel Surfacing" as used in the description of bid items in Division 2.A.8. shall consist of 6" of gravel surfacing over which 2" of washed crushed rock shall be placed giving a combined thickness of 8". Gravel surfacing shall comply with Standard 2-Sitework, paragraph 2.11.1.