Design Report.pdf
PDF 15 MB Posted
- Attached to
- Y1DA--561A4-20-105| Lab Hood B-1 Federal contract opportunity
- Solicitation number
- 36C24222B0036
About this file
This document outlines a federal contract opportunity for replacement of an existing fume hood and related HVAC equipment. The solicitation is being conducted by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2. Services required under the contract include professional construction services and design to replace a fume hood and HVAC equipment in Building 1 of the VA NJ Health Care System facility in Lyons, New Jersey. The period of performance is 240 days from notice to proceed, plus time for construction. A phasing and infectious control risk assessment plan must be provided in compliance with drawings and specifications. The estimated cost of the contract is $1,021,239. The place of performance is 151 Knollcroft Road in Lyons, New Jersey.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Responses to Requests for Information for Solicitation Install Lab Hood.docx | DOCX document | |
| 6-28-22 - VA LYONS - REPOINTING SKETCHES- RFI Answers.pdf | ||
| SKAS-110.1- RFI Answer.pdf | ||
| SKMH-702.1 - RFI Answer.pdf | ||
| 36C24222B0036 0003.docx | DOCX document | |
| 36C24222B0036 0002.docx | DOCX document | |
| Design Report new.pdf | ||
| 36C24222B0036 0001.docx | DOCX document | |
| Specifications.pdf | ||
| 36C24222B0036_1.docx | DOCX document | |
| Drawings Part B.pdf | ||
| Drawings Part A.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Consulting Engineers In: NY, NJ, PA, CT, VT, MA, RI
BASIS OF DESIGN REPORT – 100% SUBMISSION
www.fellp.com
Prepared By:
Fellenzer Engineering, LLP
22 Mulberry Street, Suite 2A
Middletown, NY 10940
(845) 343-1481
19-083
Prepared For:
Department of Veterans Affairs
VA Lyons Medical Center
151 Knollcroft Road
Lyons, NJ 07939
Attn: Gary Boehner, COR
Lateisha Robinson, CO
December 3, 2021
F E
P ro je ct
N o -4
Replace/Install Lab Hood – Bldg. 1
Lyons Medical Center
VA Project No. 561A4-20-105
Table of Contents
I. List of Drawings
II. Executive Summary
III. Review of Existing Conditions
IV. Design Intent Narrative
A. Codes & Standards
B. Site Civil
C. Architectural
D. Structural
E. Mechanical
F. Electrical
G. Plumbing
H. Fire Protection
I. Energy Efficiency
J. Tie-In Points (Electrical, HVAC, Plumbing, Fire Protection, Etc.)
K. Asbestos/Hazardous Materials
V. Project Cost Estimate
VI. ICRA Form
VII. Asbestos Survey
I. List of Drawings
DRAWING # DRAWING TITLE
GI-001 COVER SHEET WITH INDEX OF DRAWINGS
GI-002 SAFETY AND GENERAL INFORMATION
GI-003 SCAFFOLDING DETAILS & NOTES
GI-004 ICRA PLAN
HA-101 ASBESTOS: GROUND FLOOR PLAN
HA-102 ASBESTOS ABATEMENT DIAGRAMS AND NOTES
AS-001 EGRESS AND LIFE SAFETY PLAN – ARCHITECTURAL
AS-020 TYPICAL BARRIER FREE STANDARDS
AS-021 TYPICAL MOUNTING HEIGHTS & DETAILS
AS-030 PARTITION TYPE AND DETAILS
AS-032 STANDARD UL RATED ASSEMBLIES
AS-110 DEMOLTION AND NEW CONSTRUCTION FLOOR PLAN
AS-201 REFLECTED CEILING PLAN AND FINISH PLAN
AS-910 MILLWORK ELEVATIONS AND DETAILS
MH-001 HVAC: SYMBOLS, ABBREVATIONS & NOTES
MD-101 HVAC: GROUND FLOOR DEMOLITON PLAN
MH-100 HVAC: BASEMENT FLOOR HYDRONIC PLAN
MH-101 HVAC: GROUND FLOOR HYRDONIC PLAN
MH-102 HVAC: GROUND FLOOR PLAN
MH-201 HVAC: ROOF PLAN
MH-401 HVAC: SEUQENCE OF OPERATIONS, POINTS LIST, &
CONTROLS SCHEMATICS
MH-701 HVAC: DETAILS
MH-702 HVAC: DETAILS
MH-801 HVAC: SCHEDULES
PL-001 PLUMBING: SYMBOLS, ABBREVIATIONS & NOTES
PD-100 PLUMBING: BASEMENT FLOOR SANITARY/DOMESTIC DEMOLITION PLAN
PD-101 PLUMBING: GROUND FLOOR SANITARY/DOMESTIC DEMOLITION PLAN
PL-100 PLUMBING: BASEMENT FLOOR SANITARY/DOMESTIC PLAN
PL-101 PLUMBING: GROUND FLOOR SANTIARY/DOMESTIC PLAN
PL-701 PLUMBING: DETAILS
FX-001 FIRE PROTECTION: SYMBOLS, ABBREVIATIONS & NOTES
FX-201 FIRE PROTECTION: GROUND FLOOR PLAN
ES-001 ELECTRICAL: SYBMOLS, ABBREVIATIONS & NOTES
ED-101 ELECTRICAL: GROUND FLOOR POWER DEMOLTION PLAN
ED-201 ELECTRICAL: GROUND FLOOR LIGHTING DEMOLTION PLAN
ES-101 ELECTRICAL: GROUND FLOOR POWER PLAN
ES-201 ELECTRICAL: GROUND FLOOR LIGHTING PLAN
ES-701 ELECTRICAL: DETAILS
ES-702 ELECTRICAL: DETAILS
ES-801 ELECTRICAL: SCHEDULES
II. Executive Summary
This project proposes the renovation of a 1,250 +/- square foot (sf) existing chemistry lab on the ground floor of building 1 at the VA Lyons campus. The purpose of the is project is to a provide a reconstructed laboratory for clinical research. This will be done by providing complete design services for the items stated above.
Building 1 is situated on the facilities’ main campus and is connected to building 3.
Domestic water, sanitary, HVAC and electricals service to this area will be provided by the VA.
This report includes design plans for Architectural, Fire Protection, HVAC, Plumbing and Electrical systems.
III. Review of Existing Conditions
The existing chemistry lab, located on the ground floor building 1, has been around since the building was originally constructed and has undergone several renovations throughout the years. The lab is currently vacant and sits adjacent to the blood lab and police barracks. It is comprised of several lab benches and general office furniture that is no longer being used.
Figure 1. Lab Southeast Corner
Figure 2. Lab Northeast Corner
Figure 3. Lab Northeast Corner Close Up
Figure 4. Lab Northwest Corner and Existing Eyewash Station (Bottom Left)
Figure 5. Lab Northwest Corner Continued
Figure 6. Lab Southwest Corner
Existing HVAC systems include several thru the wall A/C units and an 8.5-Ton packaged Carrier unit.
As seen in figure 7 below the Carrier system has been decommissioned for some time and will be completely demolished as part of this project.
Figure 7. Existing Condensing Units (Left) and Decommissioned Carrier Unit (Right)
Figure 8. Typical Thru the Wall A/C Unit
Existing sanitary and domestic service is provided from the basement below the clinic as seen in figures
9-10.
Figure 9. Basement Domestic and Sanitary Piping Distribution
Figure 10. Basement Domestic and Sanitary Piping Distribution Continued
The existing electrical service for the chemistry lab comes from 5 existing power panels located in the adjacent blood lab and from the main switchgear in the basement (Room 013 switchboard) below.
Existing service is either 208/120V/1P/3W or 208/120V/3P/4W. The fire alarm system that serves this area was updated during a campus wide renovation in 2008. As of today, the VA as reported no problems with the existing fire protection system. The existing fire alarm control panel is located in the main switchgear room (Room 013 switchboard) as seen in figure 11 below.
Figure 11. Existing Fire Alarm Control Panel (Red Box Second from the Left)
IV. Design Intent Narrative
A. Codes & Standards
• VA Directives, Design Manuals, Master Specifications, VA National CAD Standard
Application Guide, and other Guidance on the Technical Information Library (TIL)
• NFPA (National Fire Protection Association)
• NEC (National Electric Code)
• ASHRAE (American Society of Heating, Refrigerating and Air-Conditioning Engineers)
• AHRI (Air-Conditioning, Heating and Refrigeration Institute)
• OSHA (Occupational, Safety and Health Administration)
B. Site Civil
There is minor site work for this project. The extent of proposed work will include restoring the site to its original condition once construction is complete, and pouring a new concrete equipment pad for new compressor/condenser unit ACCU-1.
C. Architectural
There are several architectural items that will be addressed during this project. Work will include but is not limited to; installing new partition walls to create a small mechanical room, providing new wall finishes throughout, performing any subfloor restoration, installing new LVT flooring, installing new ceiling tiles using the existing ceiling grid, selecting and locating new lab furniture/equipment, and providing new window panes where A/C units are located.
D. Structural
There is minor structural work associated with this project. The extent of work includes infilling openings in the exterior wall, creating new openings in the exterior wall, and repairing lintels where windows are being worked on.
E. Mechanical
Due to the scope of this project, the HVAC design plan will encompass several new systems in order to meet the latest VA design standards. For demolition, all existing systems and their associated appurtenances (ductwork, controls, etc.) will be removed completely. These systems will then be replaced by a new 100% outside air (OA) variable air volume (VAV) air handling unit (AHU), and a new rooftop exhaust fan. Listed below is a breakdown of each respective system with its corresponding tag from the drawings:
1) 100% Outside Air Variable Air Volume Air Handling Unit (AHU-LAB-1)
To maintain a proper comfort level within the lab, the design plan is to provide a 1,900
CFM 100% OA VAV AHU. The system will utilize a direct expansion (D/X) coil for cooling control, a hot water/glycol coil for heating control, a single steam dispersion tube for humidification control, and a fixed membrane heat exchanger for energy recovery.
The system will be located outside just plan east of the lab, and will come in a stacked orientation (supply air on top and exhaust on the bottom). To circulate the air, each air stream comes with a centrifugal plenum fan that is controlled through a variable frequency drive (VFD). The system will also work in conjunction with the fume hood
(FH-1) to maintain a negative air balance in the room.
2) Exhaust Fan with Plume Hood (PEF-1)
As part of this project, a new laboratory fume hood will be installed. To exhaust air out of this hood the plan is to provide a new roof mounted constant volume (CV) exhaust fan with a plume stack. The system will exhaust anywhere from 100 CFM to 425 CFM based on the hood sash position. This fan will work in conjunction with the hood (FH-1) to maintain a constant face velocity at the work area.
To maintain compliance with VA standards, both systems will be integrated into the existing
BMS via a Lon works protocol communication.
F. Electrical
For power distribution the design plan is provide a new panelboard, 1LP-G-CHE, that is to be located in the newly constructed mechanical room. This panel will be feed from an existing spare breaker in the basement switchgear, and will service all new equipment and receptacles being installed as part of this project. Any receptacles that are existing to remain, will stay on their existing circuits.
For lighting, the proposed design plan is to provide new LED lights with occupancy sensors throughout. All new lighting will be powered from the existing lighting circuit. Additionally, users in the main lab will have the ability to dim the lighting.
G. Plumbing
This project will require minor plumbing alterations. Work will include demolishing old fixtures
(sinks, eyewash station, etc.) and piping, installing new plumbing fixtures, and providing new domestic, sanitary and vent piping. All domestic service will be brought up from the basement as seen in figures 9 and 10 above.
H. Fire Protection
The design plan for the fire protection systems can be broken down into two parts. The first area of concern being the fire alarm system and the second being the sprinkler system. As mentioned previously, the current fire alarm system was updated as part of a campus wide renovation in
2008. For this reason, the design plan is to leave all existing devices and to relocate or add new ones that may be required to maintain 100% coverage of the space. The existing fire alarm control panel is located in the basement of building 1 in room 013 Switchboard (as seen in figure
11 above), and will be existing to remain with additions as needed to meet current life safety requirements. For the sprinkler system the proposed plan is to leave the layout as is, and to relocate or add heads as needed to maintain 100% coverage. See FX (Fire Protection) and ES
(Electrical) series drawings for more information.
I. Energy Efficiency
All new pieces of equipment have been selected to meet the latest ASHRAE and AHRI requirements for energy efficiency
J. Tie-In Points (Electrical, HVAC, Plumbing, Fire Protection, Etc.)
All tie in points will be reviewed by the VA FMS staff.
K. Asbestos/Hazardous Materials
Due to the age of this building, it was suspected that asbestos containing material (ACM) could be present and after further testing this was confirmed true. Therefore, this project will involve traditional asbestos removal. For more information see the asbestos series drawings (HA) and section 8 below (VII. Asbestos Survey) which contains the asbestos survey performed for this area.
V. Project Cost Estimate
History
B-1 Lab Hood and HVAC
Lyons VA Medical Center TO: Gary Boehner, COR
Project Title: B-1 Lab Hood and HVAC Consultant: Fellenzer Engineering LLP Project No.: 20-477
Building: 1 Estimator: EDF/JDD Date: 3-Dec-21
Lyons, NJ Phone: 845-343-1481 Phase: 100%
Client Agency: VA
New/Rehab: Renovation Prepared by: EDF
Building GSF: CLIENT APPROVED CURRENT CURRENT ESTIMATE SUMMARY sq.ft. ESTIMATE Bldg. 1 ESTIMATED FIELD ORDER
(date) Date 3-Dec-21 BID PACKAGES: BID AMOUNT ALLOWANCES
Construction 1250 $0 Arhc. $254,426
HVAC 1250 $0 HVAC $367,746 Construction: $254,426 $12,600
Plumbing 1250 $0 Plum. $91,699 HVAC: $367,746 $16,700
Electric 1250 $0 Elect. $107,224 Plumbing: $91,699 $4,200
Structural 0 $0 Struct. $0 Electric: $107,224 $4,900
Other: $0 $0
TOTAL ESTIMATED
Project Budget $795,306 BID AMOUNT $821,095
BUILDING SUBTOTAL $795,306 Total $821,095 Valid until expected bid:
Sitework $0 $0 COMMENTS & REFERENCES:
Env. Eng. $0 $0 Project Budget: $795,306
Elec.Service $0 $0
HVAC Sitework $0 $0
Other $0 $0
SITE SUBTOTAL $0 $0
CLIENT APPROVED
BID AMOUNT: $795,306
ANCILLARY COST ESTIMATE:
Change Order 0% $0 $0
Bonus 0% $0 $0
Other $0 $0
ANCILLARY TOTAL $0 $0
CONSTRUCTION TOTAL $795,306 $0
ADDITIONAL COSTS:
Equipment (8%) $0 $0
Other $0 $0
ADDITIONAL TOTAL $0 $0
Bid ALTERNATES
Pk. # Amount Description
OTHER ALLOWANCES (included in Bid Amount)
Reviewed By: Date
BDC177(4/14/99) g\costfile\data\forms\consultE 3-Dec-21
FE-CE-1
Architectural Estimate
Estimate B-1 Lab Hood and HVAC
Lyons VA Medical Center TO: Gary Boehner, COR CONSULTANT ESTIMATE 1 sheet 1 of 1
Project Title: B-1 Lab Hood and HVAC Consultant: Fellenzer Engineering LLP Project No.: 20-477
Building: 1 Estimator: EDF/JDD Date: 6-Aug-21
Lyons, NJ Phone: 845-343-1481 Phase: 100%
Trade: Architectural Client Agency: VA
New/Rehab: Renovation Bid Package: C
DIV. 1 GENERAL CONDITIONS & ADMINISTRATION
Bonds & Permits 2% $4,200
Supervision 8% $16,801
Submittals 1% $2,100
Insurance 1.5% $3,150
Home Office Overhead 6% $12,601
Profit 6% $12,601
Equipment, Tools, Field Office 2% $4,200
1020 Field Order Allowance 6% $12,600
Activity QUANTITY MATERIAL LABOR TOTAL MATERIAL
CSI Note DESCRIPTION: UNIT TOTAL MAN HRS UNIT COST TOTAL UNIT & LABOR
Number Ref. UNIT PRICE COST /UNIT HRLYWAGE COST COST TOTAL COST
EXTERIOR WORK
New equipment pad 1 LS $400.00 $400.00 12.00 $125.00 $1,500.00 $1,900.00 $1,900.00
INTERIOR WORK
Replace acoustical ceiling 1250 SF $5.00 $6,250.00 0.05 $125.00 $7,812.50 $11.25 $14,062.50
Replace flooring - LVT 1250 SF $2.50 $3,125.00 0.10 $125.00 $15,625.00 $15.00 $18,750.00
Replace lab benches and tops 38 LF $1,000.00 $38,000.00 5.00 $125.00 $23,750.00 $1,625.00 $61,750.00
Refinish and paint exist walls 2000 SF $0.50 $1,000.00 0.06 $125.00 $15,000.00 $8.00 $16,000.00
New mech room partitions 25 LF $125.00 $3,125.00 4.00 $125.00 $12,500.00 $625.00 $15,625.00
New mech room door 1 EA $400.00 $400.00 12.00 $125.00 $1,500.00 $1,900.00 $1,900.00
New door hardware 1 EA $1,000.00 $1,000.00 12.00 $125.00 $1,500.00 $2,500.00 $2,500.00
MISC. ITEMS
Temporary dumpster rental 1 LS $2,000.00 $2,000.00 8.00 $125.00 $1,000.00 $3,000.00 $3,000.00
Asbestos Removal (See attached Asbestos Estimate) 1 LS $66,000.00 $66,000.00 0.00 $125.00 $0.00 $66,000.00 $66,000.00
Page One Subtotals $121,300 $80,188 0.00 $201,488
Page Two Subtotals
Page Three Subtotals
Security / Occupied Facility (labor only) 3% 2405.625 $2,406
100% Contingency 3% $3,639 $2,478 $6,117
Summary General Conditions & Administraton $55,653 20.0%
Allowance $12,600 4.5%
Material Cost $124,939 44.9%
Total Labor $85,071 30.6%
Total Cost $278,263 100% $254,426
HVAC Estimate
Lyons VA Medical Center TO: Gary Boehner, COR CONSULTANT ESTIMATE 1 sheet 1 of 1
Project Title: B-1 Lab Hood and HVAC Consultant: Fellenzer Engineering LLP Project No.: 20-477
Building: 1 Estimator: EDF/JDD Date: 3-Dec-21
Lyons, NJ Phone: 845-343-1481 Phase: 100%
Trade: HVAC Client Agency: VA
New/Rehab: Renovation Bid Package: H (HVAC)
DIV. 1 GENERAL CONDITIONS & ADMINISTRATION
Bonds and Permits 2% $5,550
Supervision 8% $22,201
Submittals 1% $2,775
Insurance 1.5% $4,163
Home Office Overhead 6% $16,650
Profit 6% $16,650
Equipment, Tools, Field Office 2% $5,550
1020 Field Order Allowance 6% $16,700
Activity QUANTITY MATERIAL LABOR TOTAL MATERIAL
CSI Note DESCRIPTION: UNIT TOTAL MAN HRS UNIT COST TOTAL UNIT & LABOR
Number Ref. UNIT PRICE COST /UNIT HRLYWAGE COST COST TOTAL COST
23 00 00 Common Work Results 1 LS $1,500.00 $1,500.00 40.00 105.00$ $4,200.00 5,700.00$ $5,700.00
HVAC Insulation 1 LS $3,000.00 $3,000.00 80.00 105.00$ $8,400.00 11,400.00$ $11,400.00
Testing, Adjusting and Balancing 1 LS $500.00 $500.00 20.00 105.00$ $2,100.00 2,600.00$ $2,600.00
DDC Controls for HVAC 105 PT $200.00 $21,000.00 4.00 105.00$ $44,100.00 620.00$ $65,100.00
Comissioning of HVAC 1 LS $500.00 $500.00 30.00 105.00$ $3,150.00 3,650.00$ $3,650.00
Demo ext. HVAC systems, ductwork, piping, etc. 1 LS $2,000.00 $2,000.00 40.00 105.00$ $4,200.00 6,200.00$ $6,200.00
New lab fume hood 1 EA $8,660.00 $8,660.00 30.00 105.00$ $3,150.00 11,810.00$ $11,810.00
New 100% OA stacked AHU (1,900 CFM) 1 EA $80,000.00 $80,000.00 60.00 105.00$ $6,300.00 86,300.00$ $86,300.00
New plume exhaust fan with controls 1 LS $17,000.00 $17,000.00 30.00 105.00$ $3,150.00 20,150.00$ $20,150.00
New ductwork 300 LBS $10.00 $3,000.00 0.30 105.00$ $9,450.00 41.50$ $12,450.00
New diffusers, grilles and registers 10 EA $75.00 $750.00 1.00 105.00$ $1,050.00 180.00$ $1,800.00
New hws/hwr hyrdonic piping <2" w/ valves & insulation 70 LF $15.00 $1,050.00 0.20 105.00$ $1,470.00 36.00$ $2,520.00
New steam/condenstate piping w/ vavles & insulation 95 LF $15.00 $1,425.00 0.20 105.00$ $1,995.00 36.00$ $3,420.00
New refirgerant piping to AHU 50 LF $5.00 $250.00 0.20 105.00$ $1,050.00 26.00$ $1,300.00
Misc. valves and actuators 1 LS $3,000.00 $3,000.00 40.00 105.00$ $4,200.00 7,200.00$ $7,200.00
CO2 transmitter 1 EA $600.00 $600.00 8.00 105.00$ $840.00 1,440.00$ $1,440.00
Fan inlet volume probe 3 EA $882.00 $2,646.00 3.00 105.00$ $945.00 1,197.00$ $3,591.00
Shipping and rigging equipment 1 LS $2,500.00 $2,500.00 20.00 105.00$ $2,100.00 4,600.00$ $4,600.00
Cutting & patching roof allowance 20 SF $10.00 $200.00 2.00 105.00$ $4,200.00 220.00$ $4,400.00
Structrual support allowance 1 LS $2,500.00 $2,500.00 75.00 105.00$ $7,875.00 10,375.00$ $10,375.00
Page One Subtotals $152,081 $113,925 0.00 $266,006
Page Two Subtotals
Page Three Subtotals
Security / Occupied Facility (labor only) 3% 3417.75 $3,418
100% Contingency 3% $4,562 $3,520 $8,083
Summary General Conditions & Administraton $73,539 20.0%
Allowance $16,700 4.5%
Material Cost $156,643 42.6%
Total Labor $120,863 32.9%
Total Cost $367,746 100% $367,746
Plumbing Estimate
Lyons VA Medical Center TO: Gary Boehner, COR CONSULTANT ESTIMATE 1 sheet 1 of 1
Project Title: B-1 Lab Hood and HVAC Consultant: Fellenzer Engineering LLP Project No.: 20-477
Building: 1 Estimator: EDF/JDD Date: 3-Dec-21
Lyons, NJ Phone: 845-343-1481 Phase: 100%
Trade: Plumbing Client Agency: VA
New/Rehab: Renovation Bid Package: P
DIV. 1 GENERAL CONDITIONS & ADMINISTRATION
Bonds & Permits 2% $1,383
Supervision 8% $5,534
Submittals 1% $692
Insurance 1.5% $1,038
Home Office Overhead 6% $4,150
Profit 6% $4,150
Equipment, Tools, Field Office 2% $1,383
1020 Field Order Allowance 6% $4,200
Activity QUANTITY MATERIAL LABOR TOTAL MATERIAL
CSI Note DESCRIPTION: UNIT TOTAL MAN HRS UNIT COST TOTAL UNIT & LABOR
Number Ref. UNIT PRICE COST /UNIT HRLYWAGE COST COST TOTAL COST
22 00 00 Commissioning of plumbing 1 LS $100.00 $100.00 20.00 $105.00 $2,100.00 $2,200.00 $2,200.00
Demo ext. piping and fixtures 1 LS $500.00 $500.00 40.00 $105.00 $4,200.00 $4,700.00 $4,700.00
Relocation of ext. pipe (allowance) 1 LS $1,000.00 $1,000.00 40.00 $105.00 $4,200.00 $5,200.00 $5,200.00
New lab sinks 3 EA $800.00 $2,400.00 8.00 $105.00 $2,520.00 $1,640.00 $4,920.00
Replace eye wash 1 EA $900.00 $900.00 8.00 $105.00 $840.00 $1,740.00 $1,740.00
New domestic piping 190 LF $18.00 $3,420.00 0.55 $105.00 $10,972.50 $75.75 $14,392.50
New sanitary & vent piping 115 LF $35.00 $4,025.00 0.75 $105.00 $9,056.25 $113.75 $13,081.25
New valves allowance 1 LS $500.00 $500.00 24.00 $105.00 $2,520.00 $3,020.00 $3,020.00
21 00 00 Commissioning of fire protection 1 LS $100.00 $100.00 20.00 $105.00 $2,100.00 $2,200.00 $2,200.00
Relocation of ext. sprinkler heads 3 EA $200.00 $600.00 4.00 $105.00 $1,260.00 $620.00 $1,860.00
New sprinkler heads 4 EA $50.00 $200.00 8.00 $105.00 $3,360.00 $890.00 $3,560.00
Fire protection shop drawings 1 LS $200.00 $200.00 32.00 $105.00 $3,360.00 $3,560.00 $3,560.00
Temporary cutting and patching allowance 1 LS $1,000.00 $1,000.00 40.00 $105.00 $4,200.00 $5,200.00 $5,200.00
Page One Subtotals $14,945 $50,689 0.00 $65,634
Page Two Subtotals
Page Three Subtotals
Security / Occupied Facility (labor only) 3% $1,521 $1,521
100% Contingency 3% $448 $1,566 $2,015
Summary General Conditions & Administraton $18,330 20.0%
Allowance $4,200 4.6%
Material Cost $15,393 16.8%
Total Labor $53,776 58.6%
Total Cost $91,699 100% $91,699
Electrical Estimate
Lyons VA Medical Center TO: Gary Boehner, COR CONSULTANT ESTIMATE 1 sheet 1 of 1
Project Title: B-1 Lab Hood and HVAC Consultant: Fellenzer Engineering LLP Project No.: 20-477
Building: 1 Estimator: EDF/JDD Date: 3-Dec-21
Lyons, NJ Phone: 845-343-1481 Phase: 100%
Trade: Electrical Client Agency: VA
New/Rehab: Renovation Bid Package: E
DIV. 1 GENERAL CONDITIONS & ADMINISTRATION
Bonds & Permits 2% $1,618
Supervision 8% $6,471
Submittals 1% $809
Insurance 1.5% $1,213
Home Office Overhead 6% $4,853
Profit 6% $4,853
Equipment, Tools, Field Office 2% $1,618
1020 Field Order Allowance 6% $4,900
Activity QUANTITY MATERIAL LABOR TOTAL MATERIAL
CSI Note DESCRIPTION: UNIT TOTAL MAN HRS UNIT COST TOTAL UNIT & LABOR
Number Ref. UNIT PRICE COST /UNIT HRLYWAGE COST COST TOTAL COST
26 00 00 Commissioning of electrical 1 LS $100.00 $100.00 20.00 $105.00 $2,100.00 $2,200.00 $2,200.00
Demo existing electrical and lighting systems 1 LS $500.00 $500.00 40.00 $98.00 $3,920.00 $4,420.00 $4,420.00
New fan and equipment disconnects 4 EA $200.00 $800.00 2.00 $98.00 $784.00 $396.00 $1,584.00
New VFD's 3 EA $2,000.00 $6,000.00 16.00 $98.00 $4,704.00 $3,568.00 $10,704.00
New conduit & wire (HVAC) 200 LF $30.00 $6,000.00 0.50 $98.00 $9,800.00 $79.00 $15,800.00
New receptacles/circuits - per circuit 6 EA $450.00 $2,700.00 10.00 $98.00 $5,880.00 $1,430.00 $8,580.00
Controls & Comm. 1 LS $2,500.00 $2,500.00 40.00 $98.00 $3,920.00 $6,420.00 $6,420.00
Add data points - computer and phone (Allowance) 16 EA $50.00 $800.00 2.00 $98.00 $3,136.00 $246.00 $3,936.00
New A fixtures, circuiting and controls 10 EA $200.00 $2,000.00 4.00 $98.00 $3,920.00 $592.00 $5,920.00
New B fixtures, circuiting and controls 2 EA $200.00 $400.00 4.00 $98.00 $784.00 $592.00 $1,184.00
28 00 00 Commissioning of fire alarm 1 LS $100.00 $100.00 20.00 $105.00 $2,100.00 $2,200.00 $2,200.00
FAS Conduit and Wire 100 LF $10.00 $1,000.00 0.30 $98.00 $2,940.00 $39.40 $3,940.00
FAS Duct Smoke Detectors 2 EA $200.00 $400.00 4.00 $98.00 $784.00 $592.00 $1,184.00
FAS Strobe Lights 3 EA $250.00 $750.00 4.00 $98.00 $1,176.00 $642.00 $1,926.00
Fire alarm shop drawings 1 LS $100.00 $100.00 16.00 $105.00 $1,680.00 $1,780.00 $1,780.00
Temporary cutting and patching allowance 1 LS $1,000.00 $1,000.00 40.00 $105.00 $4,200.00 $5,200.00 $5,200.00
Page One Subtotals $25,150 $51,828 0.00 $76,978
Page Two Subtotals
Page Three Subtotals
Security / Occupied Facility (labor only) 3% $1,555 $1,555
100% Contingency 3% $755 $1,601 $2,356
Summary General Conditions & Administraton $21,436 20.0%
Allowance $4,900 4.6%
Material Cost $25,905 24.2%
Total Labor $54,984 51.3%
Total Cost $107,224 100% $107,224
VI. ICRA Form
VII. Asbestos Survey
| 100% Estimates.pdf |
| (#1) Cover |
| (#2) Arch |
| (#2.5) Asbestos Cost Estimate |
| (#3) HVAC |
| (#4) Plumbing |
| (#5) Electrical |
File details come from the government source that posted it. Updated .