DARPA-PS-26-126_RAAPTR_Attachment_I_Schedule_of_Milestones_and_Payments.docx

DOCX document 44 KB Posted

Attached to
RF Architectures Applying Photonic Timing and Routing (RAAPTR)
Solicitation number
DARPA-PS-26-126
Issued by

About this file

This is a Schedule of Milestones and Payments template for the DARPA-PS-26-126 RAAPTR (RF Architectures Applying Photonic Timing and Routing) program. The document establishes a 42-month performance period with 15 milestone-based payment CLINs (Contract Line Item Numbers) that performers must complete to receive funding. Key milestones progress from Phase 1 activities including kickoff presentation and baseline integrated master schedule (Month 1), through design and procurement phases (Months 3-9), component characterization and testing (Months 12-21), and into Phase 2 brassboard prototype development including preliminary design review (Month 18), critical design review (Month 30), and integrated functional testing (Months 33-36). Final milestones encompass test readiness review and brassboard prototype delivery (Month 39), culminating in strap-down flight test of the brassboard on a Government-furnished platform (Month 42). Each milestone contains specific exit criteria and deliverables, such as presentations at Quarterly Program Review meetings, design review packages, prototype delivery, and test results. The template requires performers to insert task descriptions from the Task Description Document, fill in payment amounts split between DARPA and performer cost shares, and complete administrative fields including ACRN, funding line, and obligated amounts. All milestones are funded at time of award, with funding dates and PR codes to be determined at contract execution.

View the file

Other files

File Type Posted
DARPA-PS-26-126_RAAPTR_QA_v4.pdf PDF
DARPA-PS-26-126-Amendment-01.pdf PDF
DARPA-PS-26-126_RAAPTR_Attachment_D_Proposal_Instructions_and_Volume_I_Template_Amend01.docx DOCX document
DARPA-PS-26-126_RAAPTR_QA_v3.1.pdf PDF
DARPA-PS-26-126_RAAPTR_Q_A_V2_-_Final.pdf PDF
DARPA-PS-26-126_RAAPTR_QA_v1.pdf PDF
DARPA-PS-26-126_RAAPTR_Attachment_C_Proposal_Summary_Slide_Template.pptx PPTX presentation
RAAPTR_Proposers_Day_Slides.pdf PDF
DARPA-PS-26-126_RAAPTR_Attachment_G_Other_Transaction_Certifications.docx DOCX document
DARPA-PS-26-126.pdf PDF
DARPA-PS-26-126_RAAPTR_Attachment_E_Proposal_Instructions_and_Volume_II_Template_Price.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_K_Model_OT_Prototype.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_J_CUI_Guide.pdf PDF
DARPA-PS-26-126_RAAPTR_Attachment_H_Task_Description_Document.docx DOCX document
SAMPLE_OT_P__-_Fixed_Support_Nontraditional_-_2025.02.28.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_B_Abstract_Instructions_and_Template.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_F_DARPA_Price_Summary_Spreadsheet.xlsx XLSX spreadsheet
DARPA-PS-26-126_RAAPTR_Attachment_L_BAAT_Submission_Portal_Guide.docx DOCX document
SAMPLE_OT_P__-_Fixed_Support_Traditional_Cost-Share_-_2025.02.28.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_A_CUI_Materials_Request_Form.docx DOCX document
SAMPLE_OT_P__-_Streamlined__Fixed_-_2025.02.28.docx DOCX document
DARPA-PS-26-126_RAAPTR_Attachment_D_Proposal_Instructions_and_Volume_I_Template.docx DOCX document
SAMPLE_OT_P__-_Cost-Share_Expenditure_Based_-_2025.02.28.docx DOCX document
SAMPLE_OT_P__-_Expenditure_Based_Approach_-_2025.02.28.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DARPA-PS-26-126: RAAPTR

Attachment I

Instructions:

Please fill in the yellow highlighted text with the tasks from the Task Description Document (TDD), map them appropriately to the required milestones, and the associated payment/share amounts. Once complete unhighlight the text. Do not modify any other parts of the document. Delete these instructions before submitting.

SCHEDULE OF MILESTONES AND PAYMENTS

(NOTE: THIS DESCRIPTION IS INFORMATIONAL TO ADDRESS WHAT IS NECESSARY TO HAVE IN THE MILESTONE SCHEDULE. The following chart will detail the list of milestones. Each milestone will mark the completion of a measurable event (i.e., completing a baseline execution plan, completing development of a part of the prototype, completing a test plan, completing production of the prototype, completing and submitting the final report, etc.). The milestone description will show how the milestone will be demonstrably completed. Payments associated with each milestone must reflect the actual comprehensive costs to achieve milestone completion.)

A. Agreement Term:

The term of the Agreement commences on the effective date of the Agreement and continues for 42 months thereafter.

B. Deliverables and Payment Schedule:

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

1
XX
1
Milestone Name/Description

Exit Criteria:

· Kickoff meeting attendance and key hardware purchases plan completed

Deliverables:

· Presentation at the Program Kickoff Meeting, to include an overview of the project and a Baseline Integrated Master Schedule (IMS) for Phase 1

$
$

CLIN: 0001

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

PR: TBD

Funding Date: At time of award

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

2
XX
3
Milestone Name/Description

Exit Criteria:

· Revised oscillator and analog design completed

Deliverables:

· Presentation of the revised designs at the Quarterly Program Review meeting

$
$

CLIN: 0002

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

3
XX
6
Milestone Name/Description

Exit Criteria:

· Oscillator design traceability to metrics in simulation and expected interface requirements between subcomponents established

Deliverables:

· Presentation of the simulation results and interface requirements at the Quarterly Program Review meeting

$
$

CLIN: 0003

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

4
XX
9
Milestone Name/Description

Exit Criteria:

· Procurement completed for internal oscillator devices

· Updated IMS for Phase 1 incorporating key procurement delivery dates

· Test condition flow down requirements defined

Deliverables:

· Presentation on development status at the Quarterly Program Review meeting

$
$

CLIN: 0004

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

5
XX
12
Milestone Name/Description

Exit Criteria:

· Internal oscillator devices characterized for vibration sensitivity

· Ancillary analog-RF components characterized for phase noise performance

· Initial architecture design completed with full use case flow-down requirements

Deliverables:

· Presentation of results and initial architecture design at Quarterly Program Review meeting

$
$

CLIN: 0005

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

6
XX
15
Milestone Name/Description

Exit Criteria:

· Un-packaged oscillator functional test

Deliverables:

· Presentation of results and initial architecture design at Quarterly Program Review meeting

$
$

CLIN: 0006

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

7
XX
18
Milestone Name/Description

Exit Criteria:

· Un-packaged oscillator and analog signal chain functional on integrated breadboard

· PDR of Phase 2 brassboard prototype

Deliverables:

· Presentation of Preliminary Design Review (PDR) and development status at Quarterly Program Review meeting

· Brassboard PDR package

$
$

CLIN: 0007

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

8
XX
21
Milestone Name/Description

Exit Criteria:

· Packaged oscillator functional test

Deliverables:

· Presentation of test results and development status at the Quarterly Program Review meeting

$
$

CLIN: 0008

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

9
XX
24
Milestone Name/Description

Exit Criteria:

· Packaged oscillator prototype delivered and characterized under relevant environmental conditions in lab

· Integrated analog sub-system characterized under relevant environmental conditions in lab

· Interim design review and IMS for Phase 2 brassboard prototype development

· Final architecture design for Phase 2 flight test

· Initial design review for use-driven system concept and budget plan for functional demonstration concept

Deliverables:

· Presentation of test results and development status at Metrics Review meeting

· Delivery of one (1) packaged oscillator prototype

· Brassboard Interim Design Review package

$
$

CLIN: 0009

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

10
XX
27
Milestone Name/Description

Exit Criteria:

· Breadboard integration of oscillator and analog subsystem and functional test

Deliverables:

· Presentation of test results and development status at the Quarterly Program Review meeting

$
$

CLIN: 0010

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

11
XX
30
Milestone Name/Description

Exit Criteria:

· CDR of brassboard prototype

Deliverables:

· Brassboard Critical Design Review (CDR) package

· CDR presentation at the Quarterly Program Review meeting

$
$

CLIN: 0011

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

12
XX
33
Milestone Name/Description

Exit Criteria:

· Integrated brassboard functional test

Deliverables:

· Functional test results of the integrated brassboard

· Presentation of test results and development status at the Quarterly Program Review meeting

$
$

CLIN: 0012

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

13
XX
36
Milestone Name/Description

Exit Criteria:

· Integrated brassboard test under relevant environmental conditions in lab

Deliverables:

· Presentation of test results and development status at the Quarterly Program Review meeting

$
$

CLIN: 0013

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

14
XX
39
Milestone Name/Description

Exit Criteria:

· TRR and delivery of brassboard prototype completed

Deliverables:

· Brassboard Test Readiness Review (TRR) package

· TRR presentation at the Quarterly Program Review meeting

$
$

CLIN: 0014

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD

Milestone

Task(s)
Due Date (Months after award)
Milestone Definition
DARPA Payment
Performer

Share

15
XX
42
Milestone Name/Description

Exit Criteria:

· Strap-down flight test of brassboard on Government-furnished test platform

Deliverables:

· Integrated brassboard prototype in flight test-ready box with Government-specified test access points

· On-site support for flight test preparation and troubleshooting

$
$

CLIN: 0015

ACRN: TBD

Funding Line: TBD Amount of Funding Obligated: TBD