CTR053898_Contractors_Proposal.pdf

PDF 10 MB Posted

Attached to
Master Agreement AZ|CTR053898
Contract number
CTR053898
Issued by
Arizona

View the file

Other files

File Type Posted
ACCEPTED CTR053898 GL,AL,WC,PROFESSIONAL 08.29.23-08.29.24.pdf PDF
ADOT Usage Report 2024 Q3 CTR053898.xlsx XLSX spreadsheet
CTR053898_Contract_Amendment_Summary_Five__5_.pdf PDF
Post_Award_Sign_In_Sheet.pdf PDF
2025-Q3 ADOT Usage Report - Task Order CTR053898- CivTech .xlsx XLSX spreadsheet
ACCEPTED CTR053989 GL,AL,WC,PROF LIAB 08.29.25-08.29.26.pdf PDF
ADOT Usage Report 2023 Q3 CTR053898 (1).xlsx XLSX spreadsheet
ADOT Usage Report 2024 Q4 CTR053898.xlsx XLSX spreadsheet
ADOT Usage Report 2025 Q1 CTR053898.pdf PDF
CTR053898_Contract_Documents.pdf PDF
Q2 25 Task Order CTR053898-On Call Transit Consulting Services CivTech .xlsx XLSX spreadsheet
ADOT Usage Report 2023 Q2, CTR053898 (1).xlsx XLSX spreadsheet
ADOT Usage Report 2024 Q1 CTR053898.xlsx XLSX spreadsheet
APPROVED GL,AL,WC,PROFESSIONAL 05.12.21-05.12.22.pdf PDF
APPROVED GL,AL,WC,PROFESSIONAL 08.29.22-08.29.23.pdf PDF
CTR053898_Contract_Amendment_Summary_Four__4_.pdf PDF
ACCEPTED_CTR053898_GL_AL_WC_PROFESSIONAL_LIAB_08.29.24-08.29.25.pdf PDF
ADOT Usage Report 2023 Q1, CTR053898.xlsx XLSX spreadsheet
ADOT Usage Report 2023 Q4 CTR053898 (1).xlsx XLSX spreadsheet
ADOT Usage Report 2024 Q2 CTR053898.xlsx XLSX spreadsheet
APPROVED GL,AL,WC,PROFESSIONAL 05.12.20-05.12.21.pdf PDF
CTR053898_Contract_Amendment_Summary_1.pdf PDF
CTR053898_Contract_Amendment_Summary_2.pdf PDF
CTR053898_Contract_Amendment_Summary_Three__3_.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADOT

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

Discipline Qualifications CivTech Inc. is an Arizona-based transportation planning and engineering firm dedicated to providing quality transportation services with a special emphasis on transit planning, transportation planning, traffic engineering, and traffic design. For 18 years, we have been providing transportation planning and traffic engineering service on public works and private development projects through-out Arizona.

As an Arizona DBE/SBE/WBE certified firm founded in 2002, CivTech has a staff of twenty (20) in-house professionals – one professionally certified planner, six Arizona Registered Professional Engineers, three Engineers-in-Training, eight Engineering Technicians, and two support staff personnel. CivTech has provided similar services to rural and urban communities and understands the 5310 and 5311 grant process. We have the tools to provide ridership projections, alternative analysis and evaluations and have promoted transit and alternate mode transportation to the public for the last 18 years.

In the last two years, CivTech has significantly increased its transit experience and expertise by adding Mike James and Jay Yenerich in leadership positions.

� Mike James, CivTech’s Director of Planning, brings a wealth of transit experience from the public and private sector. Mike has served as the Transit Services Director for the City of Mesa, Rail and Transit Corridor Manager for the City of Seattle, and as the Bus Rapid Transit Project Manager for the City of Phoenix. As a consultant, Mike has conducted transit planning, design, and project implementation throughout Arizona.

� Jay Yenerich, CivTech’s Director of Design, brings significant experience designing and overseeing a vast portfolio of transit implementation projects and creation of design standards for Valley Metro in Phoenix. He previously served as Valley Metro’s Manager of Design.

CivTech includes a supporting team of subconsultants ready to address a comprehensive range of task orders demanded by ADOT.

Our subconsultants include:

• Wood Patel – providing supporting engineering and environmental analysis

• Architekton – providing architectural services

• Archaeological Consulting Services – providing environmental consulting and NEPA expertise

• Hózhó Engineering – providing tribal and northern Arizona experience

CivTech is proud to have been previously selected on

ADOT’s Transit & Rail On-Call Consultant Services contract and recently completed a transit planning task order for ADOT and Bullhead City, Arizona

Key points of the CivTech Team’s qualifications include the following.

� An understanding of ADOT MPD practices and procedures through both firm and individual experience

� Understanding of the federal process and working with FTA and

FWHA

� A clear communication approach that is critical for partnering and coordinating between jurisdictions, subconsultants, stakeholders, and ADOT

� Established procedures to keep projects on schedule and within budget

� Recent ADOT experience completing the Bullhead City Transit Site Selection Study and Environmental Clearance

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

For Discipline 1: Studies, Operations, and Planning; CivTech has proposed an experienced staff that is qualified to conduct Transit Planning and Studies, address the multiple Planning Tasks identified in the scope of work, including NEPA requirements, engage in Operations Planning, Performance Auditing, Strategic Planning, and Coordination and Mobility Projects for ADOT. We will fulfill ADOT’s need for tasks and projects by developing a specific project team with the most qualified and experienced staff members for each task.

Staffing Matrix

G ra nt

Ap pl ic ati on s

Tr an sit P la nn in g

Ri de rs hi p Pr oj ec tio ns

Tr an sit O pe ra tio ns

Pe rf or m an ce

A u-di tin g / S tr at eg ic

Pl an ni ng

Tr an sit M od el in g

St ak eh ol de r

In vo lv em en t

Pu bl ic In vo lv em en t /

Pr es en ta tio ns

O pe ra tio na l C os t

Ev al ua tio ns

Co st

/B en efi t A na ly sis

Pr oj ec t M an ag em en t

Co or di na tio n

M ob ili ty

M ag em en t

G ra ph ic

P re se nt ati on

Ti tle

V I C om pl ia nc e

Dawn Cartier, PE, PTOE a a a a a a a a a a a a

Mike James, AICP a a a a a a a a a a a a

Jay Yenerich, PE a a a a a a a a a a a a a a

Ruth Guterriez a a a a a

Diana Kelly, PE a a a a a

John Kane, FAIA a a a a a a a a a a a

Tracy McCarthy, BS a a a a

Alton Williams, PE a a a a a a a

Our team includes the following key staff for Discipline 1.

Dawn Cartier, PE, PTOE – Project Principal | CIVTECH

B.S. Civil Engineering | Northern Arizona University, 1996 | Professional Engineer Arizona 35879, PTOE 723 | 18 yrs CivTech, 24 yrs Industry | Industry Affiliations: ITE, Pinal Partnership, ACEC, APWA

Dawn is the president and founder of CivTech Inc. with 24 years of experience in traffic engineering, transportation planning and public involvement. She has been the project manager on multiple transit planning projects in which rights-of-way, planning levels of analysis, preliminary routes and alignments and facility types were determined or applied. She has worked with ADOT ECS and MPD and understands the process for project success.

Transit Development Plan, Casa Grande | MAG Rural Paratransit Assessment, Maricopa County | Downtown Tempe Core Small Area Transportation Study | Ultrastar Multi-tainment Center, Ak-Chin Indian Community

Mike James, AICP – Project Manager/Senior Transit Planner| CIVTECH

Master of Urban & Regional Planning | Eastern Washington University, 1995 | AICP # 013830 | 1 yr CivTech, 24 yrs Industry | Industry Affiliations: APA, AZPA, ACEC

Mike is the Director of Planning for CivTech Inc. with 24 years of experience in transit, transportation planning and public involvement. Mike will serve as the Transit Planning Project Manager for ADOT under this On Call.

He will provide strategic direction, strong communication, and be responsible for analysis and high-quality deliverables. He has been the project manager on transit planning projects for major and minor capital projects, site selections, operation planning and master plans. He has experience delivering multimodal plans emphasizing transit connectivity with bicycle, pedestrian, and new mobility travel options.

ADOT Bullhead City Transit Site Selection and Environmental Analysis | Taylor Street Pedestrianization Study, Phoenix | Peoria Transit Master Plan | Douglas Transit Site Selection and Environmental Analysis

Key Staff and Qualifications

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

Jay Yenerich, PE – Senior Transportation Engineer | CIVTECH

B.S. Civil Engineering | University of Texas, 1995 | Professional Engineer Arizona 37474 | 1 yr CivTech, 24 yrs Industry | Industry Affiliations: APTA, ASCE, ITE, T&DI, and WESTMARC

Jay is the Director of Design for CivTech Inc. with 24 years of experience in transit design, management, planning and implementation. He has been the project manager on transit planning projects for major and minor capital projects, conceptual plans and designs for pedestrian underpasses and bridges. His experience includes implementing transit signal priority, fiber optic design, corridor and environmental impact studies, and developing complex transportation models and visual simulations.

Valley Metro Avondale Bus Stop Improvements | Tempe Pedestrian Over and Underpasses | NAIPTA Mountain Line Improvements, Flagstaff | Tempe Bus Stop Improvements | Taylor Street Pedestrianization Study, Phoenix

Ruth Gutierrez – Senior Transportation Modeler | CIVTECH

Majored in Civil Engineering | Arizona State University | 15 yrs CivTech, 15 yrs Industry | Industry Affiliation: ACEC

Ruth Gutierrez is CivTech’s Senior Transportation Analyst and Transportation Modeler. In her 15 years at CivTech, she has secured a depth of knowledge and skill across multiple aspects of transit, traffic and transportation planning. Ruth will provide TransCad modeling expertise which is used to project transit ridership. Her experience allows her to predict transit mode share, passenger ridership by route and passenger boardings/alighting at stops.

Downtown Tempe Core Small Area Transportation Study | Transit Development Plan, Casa Grande | Ultrastar Multi-tainment Center, Ak-Chin Indian Community | Sahuarita Farms Master Transportation Plan, Sahuarita

Diana Kelly, PE – Civil Engineer | WOODPATEL

B.S. Civil Engineering | CA State Polytechnic, 1996 | Professional Engineer Arizona 46727 | <1 yrs WoodPatel, 24 yrs Industry | Industry Affiliations: ACEC, ASHE, ASCE

Diana is a senior project manager with 24 years of experience. Diana’s role on this contract is to support any civil engineering related tasks such as those related to transportation geometrics and earthwork modeling, analysis of drainage improvements, structural design, utility coordination, and preparation of special provisions and cost estimates.

John Kane, FAIA, LEED AP - Architect | ARCHITEKTON

B. Architecture | Arizona State University, 1985 | Architect: AZ 21395 | 31 yr Architekton, 39 yrs | Industry Affiliations: Tempe City Council Community Sustainability Committee Member 2009-present, USGBC, AIA

John Kane is a founding partner and design principal with Architekton. His designs are respected throughout the Southwest as a paradigm for an appropriate and sustainable architecture. He is integral in maintaining Architekton’s culture of creating award winning projects that optimize urban desert sites, consistently adhering to a rigorous architectural vocabulary that acknowledges issues of place involving climate, the physical and cultural landscape. He is a leader in the creation of sustainable, collaborative based projects including higher education, community centers, health/recreation centers, transportation centers, civic architecture, community amenities and urban/campus master planning.

Tracy McCarthey, B.S. – Environmental Consultant | ACS

B.S. Wildlife Biology | Arizona State University, 1988 | 17 yrs ACS, 27 yrs Industry

Tracy has 30 years of overall experience, including 17 years at ACS, and a background in broad wildlife management experience that includes 10 years at the AZGFD. Ms. McCarthey has managed many on-call contracts for ADOT and other agencies and has been responsible for project administration, work distribution, and quality assurance. In addition to serving as ACS’ contract task manager, Ms. McCarthey will serve as Environmental Coordinator/Program Manager, providing technical oversight for biological surveys, and will provide as-needed NEPA support.

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

Alton Williams, PE – Tribal Coordination | HOZHO

B.S. Civil Engineering | Northern Arizona University, 1995 | Hozho 10 yrs ACS, 24 yrs Industry

Alton is the firm’s principal and project manager for this contract. He brings 24 years of engineering and agency coordination experience. Alton has worked closely with agencies such as the Bureau of Indian Affairs (BIA), Navajo Housing Authority (NHA), Navajo Tribal Utility Authority (NTUA), Navajo Economic Development, Navajo Design and Engineering Services (NDES), Navajo EPA and Indian Health Services (IHS). He will provide tribal coordination and engineering support services.

Experience Working with FTA Transit Providers CivTech has recent experience working directly with the following FTA transit service providers: Bullhead City, AZ (Bullhead Area Transit System), Northern Arizona Intergovernmental Public Transportation Authority (NAIPTA), Valley Metro / Regional Public Transportation Authority (RPTA), and Douglas, AZ (Douglas Rides). Key staff also have prior experience working with the following FTA transit service providers: City of Phoenix, King County METRO (Seattle, WA), Sound Transit / Central Puget Sound Regional Transit Authority, and the City of Seattle (Seattle Streetcar).

Experience Working with Tribal Governments CivTech has recently worked for the Navajo Nation providing traffic analysis and planning support for the Kaibeto Chapter Commercial and Business Site Development at the intersection of State Route 98 (SR98) and BIA Routes 6331 and 6333 within the Navajo Nation. The future development will consist of travel-related services (hotel, restaurants) and a cultural/visitors’ center on the 10-acre site and retail and vehicle services on the 8-acre site. This project included coordination with ADOT and the Navajo Nation. CivTech also recently completed planning and analysis for a 110-acre Kayenta Industrial Park on the southeast corner of the intersection of United States Route 160 (US 160) and BIA Route 5912 within the Navajo Nation.

CivTech has experience working with the Salt River Pima-Maricopa Indian Community providing services in support of the Santeo 101, 83-acre commercial development east of Pima Road and south of McDonald Drive. Both Pima Road and McDonald Drive are within the jurisdictions of the Salt River Pima-Maricopa Indian Community and the City of Scottsdale, but are maintained by ADOT through an Intergovernmental Agreement.

CivTech also has experience working for the Ak-Chin Indian Community providing planning and traffic analysis for the Ultrastar Multi-tainment Center, which includes include retail, office, family entertainment, theater, bowling and hotel land uses along with an expansion of the existing Casino.

CivTech working closely with the Community, ADOT and the City of Maricopa to help relocate a traffic signal to a new location to support the recently completed Transportation Master Plan which emphasizes the importance of a new road to be located ¼-mile south of Farrell Road. This new road will provide through connectivity to major planning areas within the community west of SR-347.

CivTech has also worked with the Hopi Tribe providing transportation and traffic analysis and planning for more than 400,000 acres along I-40. CivTech also recently completed traffic analysis in support of an Emergency Medical Services substation within the Pawiki site on the Hopi Reservation in Kykotsmovi, Arizona.

Prior to joining CivTech, both Mike James and Jay Yenerich worked for FTA transit service providers, City of Phoenix and Valley Metro/RPTA, respectively.

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

Relevant Project Experience SCMPO Casa Grande Transit Development Plan, Casa Grande, AZ CivTech was retained to lead the Casa Grande Transit Development Plan for the City of Casa Grande and the Sun Corridor Metropolitan Planning Organization. Casa Grande is now an urbanized area and qualifies for formula federal transit funds. This project is developing options and selecting a preferred alternative for local service connected to regional service from Florence and Coolidge. The success of a new system lies within the ability for bikes and pedestrians to reach the transit corridors.

A multimodal assessment and master plan included within the preferred alternative recommendations to program to ensure that riders can get to the service. The project included a major public education and outreach effort that included a rigorous public education and outreach effort for this community which currently does not provide transit service. Using public outreach, demand was identified, major employers and pending new developments were interviewed, five and ten-year alternatives were presented. The effort included working with an advisory committee, one-on-one briefing sessions with city council members, and a series of comprehensive fact sheets developed to inform the council of details of the planning effort and alternatives considered.

ADOT Bullhead City Transit Site Selection and Environmental Analysis, Bullhead City, AZ CivTech was selected by ADOT to lead the Bullhead City Transit Site Selection & Environmental Analysis Study. The City of Bullhead City was seeking to identify and pursue the development of a new operational and maintenance facility for Bullhead Area Transit System (BATS), as well as, locate an adjacent passenger-transfer facility. This project included conducting a federally compliant environmental evaluation and site selection process and securing a NEPA compliant document for submission to the Federal Transit Administration. The project team worked with a Technical Advisory Committee and evaluated sites and conducted public outreach to inform the recommendation of a preferred location for the operations facility and passenger transfer facility.

Downtown Tempe Small Area Core Transportation Study, Tempe, AZ Downtown Tempe experiences more foot traffic than any other area within Arizona.

CivTech was retained to evaluate all modes of transportation within the downtown area and determine necessary changes to promote the multimodal environment.

A transportation model was developed in TransCAD for the area from Priest Drive to Loop 101 and the Loop 202 to Apache Boulevard which includes prediction for pedestrians, transit ridership and vehicles based on land use. The intent of the study is to determine the transportation network within ASU and along the surrounding roadway network to accommodate the entitlement density within the downtown core and best utilize City funds for infrastructure investment. Extensive coordination has been required with ASU and the City of Tempe to confirm and discuss potential recommended transportation improvements with the study area. Recommendations include traffic calming, Pedestrian separated crossings, park-and-ride locations, promotion of vehicle only corridors, and other options to increase safety and promote alternate modes. CivTech has entered into a long-term agreement to maintain the model and conduct ridership and pedestrian modal surveys to calibrate the values to be Tempe specific.

AREAS OF WORK

•Transit Feasibility
•Transit Operations Planning
•Transit Facility Planning
•Route Planning
•Travel Forecasting & Modeling
•Multimodal Assessments
•Implementation Cost Estimates
•Operational Cost Estimates
•Develop Support for Local Transit
•Public Participation
•Title VI Evaluation

AREAS OF WORK

•Transit Facility
•Facility Site Selection
•Fleet Storage and Transfer

Analysis

•Operational Analysis
•Environmental Clearance/NEPA
•Public Participation

AREAS OF WORK

•Travel Forecasting & Modeling
•Bike and Pedestrian Network

Studies

• Regional Mobility and

Coordination

• Capital Needs and Operational

Efficiency

•Infrastructure Recommendations
•Planning Agency Coordination

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

FIRMS EXPERIENCE

Arizona State University Downtown Phoenix Campus Taylor Street Pedestrianization Study, Phoenix, AZ The corridor is designed as a curbless pedestrian mall and dynamic civic space, serving the fast-growing Downtown Arizona State University (ASU) Campus. CivTech was responsible for analyzing existing conditions, traffic and road safety, developing design concepts, and preparing a cost estimate for the University. CivTech hosted a design charrette with ASU staff, facility managers, department stakeholders and the Dean of the University. This working session provided insight to the various needs, desires, and requirements for the re-envisioned streetscape. The conceptual design includes; a scramble intersection at 1st Street, bioswale plantings to capture street ponding during rain and monsoons events, moveable street furniture, shade canopies, a water wall providing literal and psychological cooling using water harvesting, variable lighting and base lighting for safety and security, and fire and security accessibility. This project was developed for ASU in coordination with the City of Phoenix Streets and Fire Department. It demonstrates CivTech’s understanding of integrating great pedestrian access to transit, education, and downtown amenities.

Ak-Chin Casino Expansion and Long-Term Master Plan - Ak-Chin Indian Community, AZ CivTech prepared a traffic and pedestrian circulation analysis and proposed circulation plans for pedestrian linkage and safety, traffic signal design and signing and marking plans for the new retail center located on the southwest corner of SR- 347 (Maricopa Road) and Farrell Road. The proposed plan included retail, office, family entertainment, theater, bowling and hotel land uses along with an expansion of the existing Casino.

MAG Rural Paratransit Needs Assessment, Maricopa County, AZ CivTech was retained to conduct an assessment of Rural Paratransit Needs in areas of the MAG region outside of the urbanized area. Cuts in LTAF II and state non-emergency medical transportation funds have lessened the abilities of agencies to provide mobility services in these areas. The assessment included an initial review of existing conditions and the existing rural paratransit service population. CivTech then developed ridership demand estimates for rural paratransit riders. Upon review of service demands and financial service costs, CivTech proposed an implementation plan to address unmet demands. Recommendations included operation strategies, funding opportunities, a travel training program, as well as, infrastructure and service extensions linking greater areas of the unserved county with local paratransit providers.

AREAS OF WORK

•Travel Forecasting & Modeling
•Bike and Pedestrian Network

Studies

•Safety Plans
•Conceptual Plan Development
•Cost Estimates
•Multiple Stakeholder Involvement
•Planning Agency Coordination

AREAS OF WORK

• Bike and Pedestrian Network Studies

•Safety Plans
•Conceptual Plan Development
•Multiple Stakeholder Involvement
•Planning Agency Coordination

AREAS OF WORK

• Regional Mobility and Coordination Planning

•Estimating Transit Needs
•Estimating Service Costs
•Regional Planning with a Transit

Component

• Strategic Planning

CivTech recently completed the Taylor Street Pedestrianization Corridor for the Arizona State University Downtown Campus.

DISCIPLINE 1: STUDIES, OPERATIONS, AND PLANNING

ORGANIZATIONAL CHART

Dawn Cartier, PE, PTOE* Project Principal CivTech | 18 yrs

Michael James, AICP Senior Transit Planner

CivTech | 1 yr

Jay Yenerich, PE Senior Transportation Engineer

CivTech | 1 yr

Ruth Gutierrez Transportation Modeler

CivTech | 15 yrs

David Duffy, PE Senior Safety Engineer

CivTech | 8 yrs

Diana Kelly, PE* Civil Engineering

WoodPatel | <1 yr

Briallen Rees, EIT Planning Analyst CivTech | 2 yrs

Alton Williams, PE* Tribal Coordination

Hozho Engineering | 8 yrs

Tracy McCarthey, B.S.* Environmental Consultant

ACS | 17 yrs

Brad Dilli, B.A.

GIS Analyst ACS | 20 yrs

Additional Support Staff

John Kane, FAIA* Architect

Architekton | 31 yrs

Michael Tickle Graphic Designer CivTech | 18 yrs

CivTech

WoodPatel

Hozho Engineering

Architekton

Archeological Consulting Services (ACS)

*Firm Primary Contact

Organizational Chart Our team, under the direction of Dawn Cartier, will provide a coordinated and collaborative approach to ensure that any transportation projects are efficiently scoped and staffed to provide the highest quality analysis and products and deliverables. Mike James will serve as our transit planning project manager leading day-to-day strategy, communication, and technical delivery of plans, programs, and projects. He offers an extensive background in transit and multimodal project experience. We look forward to working with you in fulfilling your transportation objectives.

Information Technology Solutions

Dawn is the president and principal of CivTech Inc. She uses her experience to create practical and constructible traffic engineering solutions. Her analysis and design experience include traffic impact analyses, capacity analysis, geometric design, signing concepts, pavement marking plans, signal design, ITS and detour design. Dawn has over 18 years of experience working with municipalities and private sector specialists. She often prepares and presents the results of projects publicly at council hearings and public meetings.

Representative Projects

DOWNTOWN TEMPE SMALL AREA MULTIMODAL STUDY, TEMPE. CivTech completed a small area transportation study for ASU and the City of Tempe that includes the north portion of Tempe. A transportation mode was developed in TransCAD for the area from Priest Drive to SR101 and the SR202 to Apache Boulevard. The intent of the study is to determine the transportation network within ASU and along the surrounding roadway network to accommodate the entitlement density within the downtown core. Extensive coordination has been required with ASU, City of Tempe and the developer of the Athletic Facilities District to confirm proposed development densities, calibrate the traffic demand model and discuss potential recommended transportation improvements with the study area.

THOMAS ROAD BICYCLE AND PEDESTRIAN IMPROVEMENTS, 64TH STREET TO PIMA ROAD, SCOTTSDALE. The goal of this project was to focus on the improvement of the walking and bicycling paths along the approximately three miles. Major elements of the project included sidewalk enhancement and widening, upgrading curb ramps and driveway entrances to current City standards, and adding bicycle lanes and grade separated crossings. CivTech evaluated the existing accident experience, number of access locations, provisions for access management, transit ridership and stop locations, speed limits, ADA accessibility of sidewalk, and lane widths to determine what changes could be implemented along the corridor. This project has enabled CivTech to explore alternatives for obtaining additional roadway space while still providing necessary improvements for pedestrians, bicyclists, landscaping and public art.

CASA GRANDE TRANSIT DEVELOPMENT PLAN AND MULTIMODAL ASSESSMENT, CASA GRANDE. CivTech was retained to lead the Casa Grande Transit Development Plan for the City of Casa Grande and the Sun Corridor Metropolitan Planning Organization. Casa Grande is now an urbanized area and qualifies for formula federal transit funds. This project is developing alternatives and a selected option for local service connected to regional service from Florence and Coolidge. The project includes a major public education and outreach effort.

ARIZONA CANAL PATH, SCOTTSDALE. Dawn performed a traffic/pedestrian analysis for the proposed Arizona Canal Path crossings of Chaparral Road and McDonald Drive. The analysis will evaluate three alternative crossing at each location, including the evaluation of a signalized pedestrian crossing (HAWK signal).

METROCENTER CORRIDOR DRAFT ENVIRONMENTAL IMPACT STATEMENT (EIS), PHOENIX. CivTech was contracted with Valley Metro to undertake the exciting challenge of connecting the Central Phoenix/East Valley Light Rail Transit (LRT) with the northwest portion of the City. In order to meet this challenge, CivTech completed a traffic evaluation for the EIS and New Starts Report for the LRT extension from the Spectrum Mall. The traffic related scope of services included a heavy transit element to evaluate a preferred public mode of transportation and alignment within the study area. A detailed analysis of predictive priority signal preference as part of the implementation of ITS technologies was also performed. More detailed analyses prepared in later phases included the evaluation of park-and-ride lots and garages with an emphasis on pedestrian and vehicular safety.

TEMPE STREETCAR – VALLEY METRO, TEMPE. The first of its kind in the Valley, the 3-mile Tempe Streetcar system is an important addition to the region's current transit network. It will operate on tracks, primarily mixed with automobile traffic. As a subconsultant to Stantec, CivTech is leading the traffic engineering design for this line. CivTech’s portion of the work includes: new and modified traffic signals; new pedestrian crossing signals; signing; pavement marking; roadway lighting; and fiber optic interconnect.

EDUCATI ON

Bachelor of Science in

Civil Engineering

Northern Arizona

University, 1996

RE GI STRATI ON

Professional Engineer

Arizona 35879

Nevada 020382

Professional Traffic

Operations Engineer 723

CIVTECH TENURE

17 years

INDUSTRY TENURE

23 years

PROFESSI ONAL

MEMBERSHI PS

American Society of Civil

Engineers (ASCE)

Institute of Transportation

Engineers (ITE)

Pinal Partnership

American Council of

Engineering Companies

(ACEC)

American Public Works

Association (APWA)

SOFTWARE

PROFI CIENCI ES

Traffix, Highway Capacity

Software, Synchro, SIMTraffic, Rodel, AutoCAD/LDD, Microstation, InRoads, Softdesk/Civil Design

10605 North Hayden Road, Suite 140 Scottsdale, Arizona 85260 Office 480-659-4250 Fax 480-659-0566

DAWN CARTIER, PE, PTOE

Principal / Senior Transportation Engineer / QA/QC

Mike is a community-focused transportation professional and project manager with over 24 years of private and public sector experience. His project management, planning, analysis, and design experience includes master transportation and transit plans, neighborhood area street plans, urban design frameworks, high-capacity transit corridor studies, light rail, bus rapid transit, and streetcar facility design, and right-of-way policy development. Mike recently served as the BRT Administrator for the City of Phoenix, the Rail and Transit Corridor Manager for the City of Seattle, and the Deputy Transportation Director/Transit Services Director for the City of Mesa, AZ. He has conducted public sector planning work for the Arizona cities of Phoenix, Tucson, Scottsdale, Mesa, Chandler, Peoria, as well as, agency work for Valley Metro and the State Lands Department.

Representative Projects and Qualifications

TAYLOR STREET PEDESTRIAN MALL EXPANSION, PHOENIX, AZ – Mike is the project manager for a traffic study, analysis and conceptual plan development for expansion of the Taylor Street pedestrian mall from 1st Street west to 3rd Street in Downtown Phoenix. This work includes evaluating a 2-block street closure, traffic and pedestrian circulation analysis and conceptual urban design for the redesigned curbless street.

TRANSIT SITE SELECTION & ENVIRONMENTAL ANALYSIS, BULLHEAD CITY, AZ - Mike was the project manager for this transit site selection study. Bullhead City is seeking to site and pursue the develop a new operational and maintenance facility for Bullhead Area Transit (BAT), as well as, locate an adjacent passenger transit center facility. This project includes conducting a federally compliant environmental evaluation and site selection process and securing a NEPA compliant document for submission to the Federal Transit Administration. The project team is working with a Technical Advisory Committee to consider and evaluate sites and is conducting public outreach to inform the recommendation of a preferred location for the operations facility and passenger transfer facility. Sites for consideration include a range of ownership including privately-owned commercial property, City-owned property, and property controlled by the BLM.

BUS RAPID TRANSIT PROGRAM INITIATION, PHOENIX, AZ – Mike developed the scope of work and led the consultant selection process for multiple consultant teams to collaboratively conduct planning, capital systems development, operational planning, community engagement and preliminary engineering for a new Bus Rapid Transit program identified in the City’s Transportation 2050 program.

He was responsible for developing and presenting program information to community groups, a citizen’s transportation commission, and the City Council.

ACCESSIBLE MT. BAKER, SEATTLE, WA – Mike managed the first project in the City that adopted a pedestrian, bicycle, and transit modal hierarchy. This project utilized NACTO Urban Street Design Guide alternative performance measures to direct an innovative concept plan. This effort utilized an innovative outreach engagement liaison program and worked with seven language groups and a high school youth group. This inspiring plan received $6 million in local levy funding and $900,000 in the Washington State Transportation Plan.

SEATTLE TRANSIT MASTER PLAN UPDATE (2016) – After approval of a local levy to fund transit service and transportation improvements, Mike led an update to the Seattle Transit Master Plan. This update included policy updates to direct local investment in the upcoming Sound Transit 3 funding plan, incorporation of new transit investments including several new Bus Rapid Transit lines, and incorporation of new street and intersection plans to ensure access and mobility for safe routes to schools, transit hubs, and light rail stations.

MESA GATEWAY STRATEGIC DEVELOPMENT PLAN, MESA, AZ – Mike managed the development of this plan that included transportation, land use, and economic development strategies for 32 square-mile area encompassing the Phoenix-Mesa Gateway Airport, Arizona State University Polytechnic campus, and a fast growing residential and commercial area along the Loop 202 freeway and State Route 24. This plan received a 21st Century Award from the Arizona Chapter of the American Planning Association.

EDUCATION

Master of Urban & Regional Planning Eastern Washington University, 1995

Landscape Architecture Washington State University, 1993

ACCREDITATION

American Institute of Certified Planners # 013830

CIVTECH TENURE

Less than 1 year

INDUSTRY TENURE

24 years

PROFESSIONAL

MEMBERSHIPS

American Planning Association (APA)

Arizona Planning Association (AZPA)

American Council of Engineering Companies of Arizona (ACEC Arizona)

10605 North Hayden Road Suite 140 Scottsdale, Arizona 85260 Office 480-659-4250 Fax 480-659-0566

MIKE JAMES, AICP

Director of Transportation Planning

Jay Yenerich is the Director of Design for CivTech. He is experienced on a wide variety of ITS, transit and highway projects participating in the planning, design and construction of projects. At Valley Metro, Jay led procurements and negotiated scope and fees for over $50 million of design and construction work. Additionally, his experience includes implementing transit signal priority, ITS design, fiber optic design, corridor and environmental impact studies, construction cost estimation, and intersection, roadway, and freeway interchange design.

Representative Projects

DIRECTOR OF DESIGN, CIVTECH (OCTOBER 2018 – PRESENT) – Jay is responsible for the design team at CivTech. Projects include both public and private clients such as ADOT, Town of Paradise Valley, City of Scottsdale, City of Buckeye, City of Glendale, Pulte, Nationwide, and Ritz Carlton.

Current projects are Cavasson – Hayden Road, Scottsdale that involve ITS Design elements of CCTV, DMS, and traffic signal interconnect and StoneHaven – Cardinals Way, Glendale that include Its traffic signal interconnect.

MANAGER, CAPITAL DEVELOPMENT, VALLEY METRO (JUNE 2013 – OCTOBER 2018) – Jay managed consultants, staff and an annual budget of over $30 million. He was responsible for all design packages and modifications that were released for construction. His group was responsible for developing the Project Management Plan and Real Estate Management Plans for the Federal Transit Administration (FTA) for all projects. He provided feedback and input on budgetary concerns for senior management. He completed the Design Criteria Manual and provided an update to the CADD Manual and Standard Drawings for upcoming projects. He was active in the following projects covering all aspects of initial, preliminary, final design and construction services:

Northwest Light Rail Extension (CMAR) Central Mesa Light Rail Extension (D/B) OMC Solar Project Design Build (D/B)

Gilbert Road Light Rail Extension (CMAR) 50th Street Station (CMAR) South Central Light Rail Extension (CMAR)

Jay was responsible for the managing three key contracts for Valley Metro:

o Consulting Support Services: $11.8 million contract over 5 years to provide design and consulting support for a variety of Valley Metro projects. Task Orders included cost estimating, design of transit facilities, environmental site assessments, CADD support, and various staff augmentation needs.

o Systems Design Services: $30 million contract over 7 years to provide light rail systems design for major capital projects.

o Miscellaneous Construction Services Contract: $12 million contract over 5 years to provide Job Order Contractor (JOC) services. Various work included upgrade or repair of existing facilities and construction of new transit facilities.

SR 51 FMS DESIGN PROJECT, PHOENIX, AZ – Senior ITS Engineer. Jay lead Quality Assurance/Quality Control engineer on 6-mile FMS upgrade and new design project. Project elements included upgrading or adding 13 ramp metering locations. The project contained other FMS elements including CCTV, DMS, and mainline detection. The project added new fiber optic splices and cables throughout the corridor.

RIVERSIDE COUNTY/I-10 LIFE-LINE ANALYSIS, PALM SPRINGS, CALIFORNIA - Lead ITS Engineer.

Traffic Incident Management analysis modeling lead for a project for Riverside County. The project provided a relief for Interstate 10 near Palm Springs. Various alternatives were developed for 1, 2, 3 or 4 lane (full) closures. Models determined impact of closures and benefit that could expected from relief routes. Recommendations included Traffic Incident Management plan with upgraded signal system to enable emergency schedules. Additionally, fuel consumption and idling time values were calculated and presented to air quality staff for determination of environmental benefits of the project.

MESA ITS ON-CALL, MESA, AZ – ITS Project Manager for ITS on-call projects. Jay was responsible for on-call services that included developing new ASC/3 controller logic to mimic existing Siemens LRT logic and replication of conditional lagging left turns as well as phase extension. Controllers were then tested in the shop and subsequently installed in the field.

EDUCATION

Bachelor of Science in Civil Engineering University of Texas at Austin, 1995

Master of Science in Civil Engineering University of Texas at Austin, 1997

CIVTECH TENURE

1 year

INDUSTRY TENURE

24 years

PROFESSIONAL

REGSITRATIONS

Arizona #37474 (2002) Idaho #10209 (2001)

PROFESSIONAL

MEMBERSHIPS

American Public Transit Association (APTA)

American Society of Civil Engineers (ASCE)

Institute of Engineers, Arizona Chapter (ITE)

Transportation and Development Institute

(T&DI)

Scottsdale, Arizona 85260 Office 480-659-4250 Fax 480-659-0566

JAY A. YENERICH, PE

Senior Transportation Engineer / ITS

Ruth Gutierrez, currently majoring in Civil Engineering at ASU, has been CivTech’s Traffic Analyst and Transportation Designer for her 15 years of engineering industry tenure. She has secured a depth of knowledge and skill across multiple aspects of traffic and transportation planning, transportation operations, and public participation, as well as broad coordination with many municipalities, and public interests, Ruth has been instrumental In the City of Glendale’s Loop 303 Master Planning Report where the purpose was to document and compare existing traffic conditions to the planned future conditions within the study area. Ruth assisted in the coordination with multiple agencies/consultants, including MAG, City of Glendale, area property owners, Northern Parkway Planning Owners, and the loop 303 planning efforts to accurately reflect interests in the area.

Ruth’s familiarity with tasks such as collecting data, utilizing intensive excel spreadsheets to conduct data within study areas, creation of transportation models using TransCAD, TransModeler Synchro and SIMtraffic, calculating future volumes using MAG projected 2030 volumes and the added proposed site traffic, calculating intersection turn movements, determining roadway classification, and future lane geometry in projects such as the Sahuarita Farms Master Transportation Plan, City of Phoenix’s 7th Street and 7th Avenue Microsimulation, and the Crossroads East Area Plan ensures a continuous quality when it comes to her project tasks.

TEMPE SMALL CORE AREA TRANSPORTATION STUDY, TEMPE. Ruth is currently working on the ASU/Tempe TransCAD model which incorporates updated ASU student population, new commercial, office and student housing land uses within the Tempe downtown core area. The study area encompasses the SR202 to the north, Apache Boulevard to the south, Priest Drive to the west and SR101 to the east. Tasks included extensive coordination with City of Tempe staff and ASU, utilizing intensive Excel spreadsheets to calculate TAZ information within study area, developing a gravity based TransCAD model, running/calibrating several iterations of the TransCAD model. Part of the travel demand model will also include all existing and proposed Transit in and around the study area to help determine areas within the model used by pedestrians and bikes.

COOPERLEAF TRAFFIC INTERCHANGE TRAFFIC REPORT AND AREA TRANSPORTATION MODEL,

TONOPAH. The Copperleaf T.I. traffic report and change of access report were prepared by CivTech to document the existing and future traffic conditions of the study area that includes a four mile stretch of Interstate 10. CivTech, through extensive coordination with the Maricopa Association of Governments (MAG), Arizona Department of Transportation, the Hassayampa Framework Study, and planned developments in the area, developed the TransCAD model to project future traffic conditions.

The modeling process included several roadway alignment changes, land use changes, and coordination with multiple agencies. The reports supplemented the Design Concept Report and the Environmental Categorical Exclusion for this proposed roadway project.

SAHUARITA FARMS MASTER TRANSPORTATION PLAN, SAHUARITA. Ruth worked with Crown Community Development, the Town of Sahuarita, ADOT, Pima County, and PAG to study the future build-out conditions within the Town of Sahuarita. The model Ruth prepared encompassed a 10-mile diameter study area, and has been developed using assumptions approved by the Towns General Plan. As a result of developing the TransCAD model, extensive coordination with the Town is operations of the proposed Sahuarita Farms development. Tasks included extensive coordination, data collections, utilizing intensive Excel spreadsheets to calculate TAZ information within the study area, developing a gravity based TransCAD traffic model, running/ calibrating several iterations of the TransCAD model to establish projecting future ADT volumes, and using the ADT volumes to calculate peak hour turning movements for each study intersection within the study area.

EDUCATION

Majored in Civil Engineering Arizona State University

15 years

15 years

SOFTWARE

PROFICIENCIES

Traffix Highway Capacity Software Synchro TransCAD/TransModeler AutoCAD/LDD SIM Traffic Microstation AutoTurn

Scottsdale, Arizona 85260 Office 480-659-4250 Fax 480-659-0566

RUTH GUTIERREZ

Senior Traffic / Transportation Analyst /Senior Transportation Modeling

David is a Project Manager and a Senior Traffic Engineer at CivTech Inc. He has over 28 years of traffic engineering and transportation planning experience with the Arizona Department of Transportation and CivTech, working both with municipalities and private sector specialists. Dave has performed and overseen numerous crash analyses, warrant studies, speed studies, operational studies, no passing zone studies and data collection efforts. He has continued his career at CivTech, performing and overseeing Traffic Impact Studies, Road Safety Assessments, project scoping reports and other safety analyses.

Relevant Project Experience

MARICOPA ASSOCIATION OF GOVERNMENTS (MAG) ROAD SAFETY ASSESSMENTS (RSA) 67TH

AVENUE/GLENDALE AVENUE. CivTech has been selected under the safety on-call contracts with MAG to perform the RSAs for local jurisdictions. CivTech lead the RSA effort with the City of Glendale for the intersection of 67th Avenue/Glendale Avenue. CivTech created the power point presentation for the kick-off meeting and lead the team to perform field observations to document good safety practices and short, medium, and long-range improvements to address crash and potential safety issues at this intersection. There have been 173 total crashes over 5 years at this intersection including 11 bicycle and pedestrian crashes. CivTech presented the findings on day 3 of the RSA and a final report documenting findings observations and recommendations. Significant recommendations included putting the pedestrian phase in recall, pedestrian access improvements, clear zone short and long-term improvements and sight distance improvements.

ADOT ROADWAY SAFETY ASSESSMENT, ADOT/US 60 IN GLOBE. As a subconsultant, CivTech participated as a team member for an RSA on US 60 in Globe MP 247.5 to MP 248.6. CivTech also provided the traffic counts at the intersection of US 60 and Radanovich Blvd. There were 74 recorded crashes in this section in 5 years. There was 1 fatal and 4 incapacitating crashes; nearly 75% of the crashes were either rear-end or angle crashes. Our observation of sight distance issues, lack of lighting and access control led to recommending mitigations to improve these areas.

ADOT I-10 DETOUR ROUTE TO US70 STUDY. CivTech assisted WSP in a study on US70 from Safford to the New Mexico State Line to determine the feasibility of routing traffic from I-10 to US70 when shutdowns of I-10 occurred due to weather or crash incidents. CivTech reviewed crash data and used the ADOT photolog to recommended safety improvements and locations of the improvements on US

70. CivTech also provided a planning level cost estimate for the recommended improvements.

Improvements included pavement markings, centerline rumble strips, extending culverts, slope layback, shoulder widening and passing lanes.

ADOT HSIP SAFETY EVALUATIONS. Pedestrian night time crashes were evaluated on US70, SR86 and SR264 as a result of these locations appearing on the list for high crash locations. Pedestrian paths close to the highways were observed between housing areas and school and commercial areas. In some cases where bridges were present on US 70 and SR 86 pedestrians traversed the bridge to cross the wash. Most crashes occurred in darkness. Recommended countermeasures were continuous lighting and sidewalks. As US 70 and SR 86 are near astronomical observatories, consideration for reducing light emissions that affected the observatories was a part of the lighting designs.

ADOT Traffic Safety Roadway Departure Safety Implementation Program (RDSIP). CivTech, as a subconsultant, research, develop standards and develop safety project to address the emphasis areas Enhanced Signing and Marking on Curves, Centerline Rumble Strips, Shoulder Rumble Strips and Edge Line Rumble Stripes, Alignment Delineation with Flexible Delineators, Wet Weather Treatments, Guardrail Delineation, Cross Median Crash Treatments. CivTech lead the research efforts, assisted with meeting presentations and developed the draft Policies, Guidelines and Procedures (renamed Traffic Guidelines and Processes) for each of the emphasis areas.

Civil Engineering

Northern Arizona

University, 1981

REGI STRATI ON

Professional Engineer

Arizona 30813

8 years

38 years

Scottsdale, Arizona 85260 Office 480-659-4250 Fax 480-659-0566

DAVID DUFFY, P.E.

Senior Transportation Engineer / Safety

Diana is a Senior PM responsible for the proactive management and coordination of disciplines, including traffic engineering, geotechnical engineering, utility and right-of-way clearances, specifications and estimates, environmental updates, constructability review, and quality assurance/quality control for multidiscipline transportation projects. Her experience ranges from streets and arterials to rural highways and urban freeways. Diana has extensive experience in roadway and traffic interchange geometrics and earthwork modeling, analysis and design of drainage improvements, structural design, utility coordination, and preparation of special provisions and cost estimates.

RELEVANT PROJECT EXPERIENCE

ON-CALL PROJECT DEVELOPMENT – STATEWIDE, AZ; ADOT*

Senior Project Manager and Senior Project Engineer responsible for the development of scoping letters and final construction documents and engineer’s estimates for various projects throughout the state. Projects included development of scoping letters and final construction documents for the following projects:

• 67th Avenue/Orangewood Avenue Sidewalks, Glendale AZ | Project Manager for development of scoping and final design documents for the installation of sidewalks, ADA-compliant sidewalk ramps, traffic signal modifications and street/pedestrian lighting to expand pedestrian connectivity along 67th and Orangewood Avenues.

• Flagstaff Urban Trail System, Fourth Street Trail Extension, Flagstaff AZ | Project Manager for the development of scoping and final design documents for the construction of the extension of the urban trail system, ADA compliant sidewalk ramps, traffic signal modifications and street lighting along Fourth Street while minimizing through-away trail improvements in anticipation of the future I-40 overpass reconstruction.

• SR 72 at Joshua Drive, Intersection Improvements, Bouse, AZ | Project Manager for the development of turn lanes at the intersection of SR 72 and Joshua Drive. Design included coordination with ADOT in-house design staff for packaging adjacent project together into one; coordination with the Arizona & California Railroad (Genesee & Wyoming; and significant utility coordination in relocation of telecommunication lines and APS OH 69kV lines.

• 24th Street West; 7th Street South to 15th Street North Pavement Preservation, St Johns, AZ | Senior Project Engineer responsible for the development of scoping letter and construction plans for the mill/overlay of approximately 2 miles of two-lane roadway. Based on review of the pavement condition, the design team recommended full depth pavement replacement for the outside 3-foot wide roadway width (in wheel path) to further extend the life of the existing roadway pavement; this was completed within the original programmed amount.

• Coconino Street Pavement Replacement, Springerville, AZ. Senior Project Engineer responsible for the development of scoping letter and construction plans rehabilitation along Coconino Street from East…