Construction_Schedule.pdf

PDF 84 KB Posted

Attached to
443395-1-58-01 Hungerford Elementary School Sidewalk Gaps SRTS (LAP)
Solicitation number
IFB26-8
Issued by
Orange County, Florida

About this file

This is a Construction Schedule document for the City of Winter Park, Florida, related to the Hungerford Elementary School Sidewalk Gaps SRTS Financial Project. The project involves installing and repairing sidewalks and pedestrian crossings to facilitate access to Hungerford Elementary School, with project limits extending from the intersection of E. Kennedy Boulevard and S. College Avenue to the intersection of Monroe Avenue and Margaret Square. Two sets of Rectangular Rapid Flashing Beacon systems are proposed as part of this work. The advertisement date is January 12, 2026, with a bid opening scheduled for February 11, 2026. FDOT and City of Winter Park bid review concludes by March 11, 2026, followed by City Commission consideration by March 17, 2026 and approval by March 25, 2026. The project award date is March 30, 2026, with contract execution on April 17, 2026. The Notice to Proceed is scheduled for April 21, 2026, following a pre-construction meeting on April 20, 2026. The construction duration is 140 days, with substantial completion targeted for August 9, 2026 and final acceptance by September 8, 2026.

The document does not contain information regarding pricing terms, set-asides, incumbents, funding requirements, or financial sources. This project is identified as a LAP (Local Agency Program) initiative and is assigned Project Number 443395-1-58-01. The schedule was prepared by Charles Ramdatt on October 14, 2025.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: Hungerford Elementary School Sidewalk Gaps SRTS Financial Project #: 443395-1-58-01 Agency: City of Winter Park Prepared by: Charles Ramdatt Date: 10/14/2025

Construction Schedule

Advertisement Date : 1/12/2026

Bid Opening Date : 2/11/2026

FDOT & CWP End Bid Review : 3/11/20264

CWP Commission Item by : 3/17/2026

CWP Commission Approval : 3/25/2026

Award Date : 3/30/2026

Executed Contract Date : 4/17/2026

Pre-Construction Date : 4/20/26

NTP Date : 4/21/2026

Construction Duration : 140 days

Substantial Completion Date : 8/09/2026

Final Acceptance Date : 9/08/2026