About this file

This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT), involving CORE Engineering Group, LLC as the consultant. The task work order is associated with Contract No. CAQ78 and has a specific Financial ID No. of 451083-1-32-01, dated 06/06/2024.

The task work order covers design services for lighting improvements along SR-824/Pembroke Road, specifically focusing on two signalized intersections from NW 8 Ave to NW 2 Ave. The total compensation for these services is $82,941.24, paid as a lump sum based on percentage of completion. The scope includes project general activities, utilities coordination, lighting design improvements, and basic survey work. The project is characterized as a safety improvement initiative, with design services to be completed by 11/27/2028. The services will involve evaluating lighting at two intersections, coordinating with maintaining agencies, and preparing utility certification packages, all in accordance with FDOT Design Manual Section 231.

View the file

Other files

File Type Posted
CN-550000-CAQ78-00040000.pdf PDF
CN-550000-CAQ78-W0040000.pdf PDF
CN-550000-CAQ78.pdf PDF
CN-550000-DON55-W0080000.pdf PDF
ContractBudgetExport.csv CSV file
CN-550000-CAQ78-W0020000.pdf PDF
CN-550000-CAQ78-00020000.pdf PDF
CN-550000-CAQ78-00030000.pdf PDF
CN-550000-CAQ78-W0030000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

11/27/2028

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

Consultant, Procurement, Financial Services, FDOT Project Manager, File

Senior Project Manager/Principal

$82,941.24

$0.00

(name) (title)

Md Rahman

$82,941.24

Total authorizations to date (including this one):

Departmental Approval:

$82,941.24 Limit

Design Services for lighting Improvements along SR-824/Pembroke Rd. from NW 8 Ave to NW 2 Ave.

CORE Engineering Group, LLC

101 N. State Road 7, Suite 4, Margate, FL 33063

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$82,941.24

(LS2) Lump sum paid based on % of completion

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Services

$82,941.24

(name) (title) Signature

Ashley Dixon Contract Coordinator

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAQ78 451083-1-32-01

DocuSign Envelope ID: 54CCB826-27A3-4AFE-A63F-C3E5C70CEA06

06/06/2024 | 8:12 AM EDT

Contract No.: CAQ78

Financial ID No. 440455-8-32-01

CONTINUING SERVICES FOR PROJECT DESIGN

Scope of Services Task Work Order (TWO) No. 1 Financial ID No. 451083-1-32-01

The Lighting Improvements along

SR-824/Pembroke Rd. from S-26 Ave./NW 8 Ave. and S-22 Ave./NW 2 Ave.

The CONSUTANT shall provide design services for lighting upgrades at two (2) signalized intersections and EB/WB approaches, in accordance with FDOT Design Manual (FDM) Section

231. The nature of this project is safety improvements:

The key applicable design services are as follows:

1. Project General (Activities 3)

2. Utilities Coordination (Activity 7)

a. Two (2) utility contacts – Initial contact, Final Contact

b. Prepare Utility Certification Package

3. Lighting (Activities 23 & 24)

a. Lighting improvements to be evaluated at two signalized intersections and

EB/WB approaches (SR-824 at S-22 Ave and SR-824 at S-26 Ave.) per FDM 231 criteria for intersection illumination.

b. Coordinate a lighting agreement with the maintaining agency to provide proposed roadway lighting.

4. Survey (Activity 27)

27.03 Alignment and Existing R/W Lines

A basic alignment and existing r/w will be established per FDOT Maps and platted information (No baseline review meeting and PNC sheets).

27.10 Underground Utilities

a. Not Included.

5. Geotechnical (Activity 35)

a. Not Included.