CN-550000-CAP39-W0020000.pdf
PDF 288 KB Posted
- Contract number
- CAP39
- Issued by
- Florida
About this file
This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) to Stanley Consultants, Inc., under Contract No. CAP39. The task work order is specifically for a Value Engineering (VE) Study for the Ellis Road Widening project located in Brevard County, covering the road segment from John Rhodes to West of Wickham Road.
The contract is for a lump sum fee of $55,253.06, with the primary objective of conducting a comprehensive value engineering study to identify alternatives that can help move the project forward more efficiently. The study will be conducted in-person from May 20-24, 2024, across two locations: the FDOT Oviedo Operations Office and the FDOT District 5 Office. Stanley Consultants will follow the SAVE International 8-step value engineering process, which includes information gathering, function analysis, creativity, evaluation, and development phases. The project will result in a draft report to be submitted by June 7, 2024, with final recommendations to be reviewed and potentially implemented by the FDOT project team.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CA660-00110000.pdf | ||
| CN-550000-CAP39-00010000.pdf | ||
| CN-550000-CAP39-W0010000.pdf | ||
| CN-550000-CAP39-00020000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CAP39-00030000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
12/31/2024
*Limiting or Estimating/Budgeted Amount.
Distribution:
Consultant Acceptance:
Signature
Vice-President
$55,253.06
$0.00
(name) (title)
John Lazzara, P.E.
$55,253.06
Total authorizations to date (including this one):
Departmental Approval:
$55,253.06 Limit
VE Study for 426905-2 and 426905-4: Ellis Road Widening, from John Rhodes to West of Wickham Road
Stanley Consultants, Inc.
1641 Worthington Road, Suite 400 West Palm Beach, FL 33409
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$55,253.06
(LS2) Lump sum paid based on % of completion
Page 1 Total
Page 2 thru 6 Subtotal
Total
Completion and submittal of final report
$119,600.94
(name) (title) Signature
Bobby Bull, P.E. State Value Engineer
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
Task Work Order No.:
Contract No.: Payment FM No.:
CAP39 426905-4-32-01
DocuSign Envelope ID: 3B0D4EC7-7828-4F85-9C7B-45F1A553F795
05/03/2024 | 9:26 AM EDT
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
CAP39
5/1/2024
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR JASON ADANK, CPA, COMPTROLLER ON 5/1/2024
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55053010541
Expansion Option: A1
Object Code: 131512
Amount: $55,253.06
Financial Project: 42690543201
Work Activity (FCT): 119
CFDA:
Fiscal Year: 2024
Budget Entity: 55100100
Category/Category Year: 088849/24
Amendment ID: W002
Sequence: 00
User Assigned ID: TWO2
Enc Line (6s)/Status: 0002/04
Total Amount: $55,253.06
Contract: CAP39
Contract Type: CA - ENGINEERING (ENGINEER)
Vendor Name: STANLEY CONSULTANTS, INC.
Vendor ID: F421320758003
Beginning Date of This Agreement: 08/18/2023
Ending Date of This Agreement: 08/17/2028
Contract Total/Budgetary Ceiling: bc = $5,000,000.00
Method of Procurement: C - REQUEST FOR PROPOSAL (287.55,F. S.)
Description: Professional Services - provide training sessions in the principles of Value Engineering
Page1 of 1
To: Janaia.Thomas@dot.state.fl.us
SCOPE OF SERVICES
Value Engineering Study
CONTRACT NO: CAP39
Task Work Order Number: 2
Task Work Order Title: VE on Ellis Road Widening, Brevard County
Value Engineering Study for 426905-2 and 426905-4: Ellis Road Widening, from John Rhodes to West of Wickham Road
This document contains a scope of work and fee estimate for the Value Engineering Study (VE) to be conducted by Stanley Consultants, Inc. for the Ellis Road Widening (A.K.A. St. Johns
Heritage Pkwy @ Ellis Road from John Rhodes to West of Wickham Road), FPID: 426905-2 and 426905-4.
The primary objectives of this VE are to identify alternatives to assist FDOT in moving the project forward with alternatives that offer the most value. In order to meet these objectives, Stanley will:
• Review relevant project documentation, including base cost estimates, schedule, plans set, and technical reports;
• Assist FDOT in identifying the required personnel for the VE study, including project and
VE team members.
• Facilitate the VE study by identifying and documenting alternatives for each project;
• Elicit risk response strategies and quantifying probable adjusted impacts to cost and schedule (as required);
• Prepare a presentation of initial results (see Task 2) for review by the project and management teams; and
• Draft and finalize a report summarizing the VE Study.
Value engineering follows FDOT’s Value Engineering guidelines and adheres to the latest value methodologies practices sanctioned by SAVE International.
In terms of schedule, the following meetings and deliverables dates are tentative, and they are subject to change based on key members participation. The VE study will be in-person, between two locations. Monday through Thursday will be located at the FDOT Oviedo Operations Office, 2400 Camp Rd, Oviedo, FL 32765. The Friday morning presentation will be located at FDOT District
5 Office, 719 S. Woodland Blvd., DeLand, FL 32720. These dates are as follows:
• VE Study:
o Information, Function Analysis, Creative, Evaluation, and Development Phases:
May 20-24, 2024 o Presentation Phase: May 24, 2024
• Draft report: June 7, 2024.
The steps to complete the analysis are discussed in further detail on the following pages.
VE Team Stanley will provide the following members of the VE team:
• VE Team Leader: Scott Eshleman, PE, SE, CVS
• VE Workshop Assistant
• Stanley’s subject matter experts will not be provided for this assignment.
The following subject experts are assumed to be provided by FDOT:
• Subject Matter experts: (tentative list) o Roadway o Drainage o Traffic Operations/ITS o Construction o Maintenance o Utilities o Geotechnical o Structures o Right of Way o Project Management
Tasks The following pages contain each of the key tasks Stanley anticipates performing to complete this study.
Task 1 Preparation Phase
As part of the Preparation Phase, Stanley Consultants will coordinate with FDOT and the design team to arrange for the logistics and expectations of the VE study.
Stanley will review existing documentation for the project, including:
• The base cost estimates, including Construction, Utilities and Right-of-way
• The base project schedule from time of workshop to project completion
• Relevant technical reports or memoranda
• Traffic Analysis files (Synchro/VISSM) and traffic report
• Set of plans, roll plots, KMZ files
• Environmental document (EIS/EA/CE), VE Report
• Existing Risk Register from CSRA analysis, and
• Others, as identified by the project team.
Task 2 VE Workshop
Meeting #2: VE Workshop –In-person – May 20th-24th, 2024
Stanley Consultants will facilitate VE study session in accordance with the SAVE 8-step process outlined below.
Information Phase:
• Site visit
• Verify project background
• Identify operational considerations
• Identify key agreements
• Identify critical assumptions
Function Analysis Phase:
• Create Cost Model
• Identify project functions
• Draft a FAST Diagram
• Determine functions to focus on Creative phase
Creativity Phase:
• Brainstorm alternative ways to perform the identified functions
• Identify risk response strategies
Evaluation Phase:
• Evaluate alternative concepts
Development Phase:
• Prepare preliminary recommendations – narrative, assumptions, drawings, calculations, lifecycle cost analysis
Meeting #3: Presentation of results (In person) – May 24th, 2024
Presentation Phase:
• The VE team will rehearse and present VE Study results to the Management and Project teams.
• The VE Facilitator will prepare a draft report (see Task 3) for the Project team to review and comment.
Implementation Phase:
• The project team responds to the recommendations, providing clear justification of the acceptance or rejection. The Management team will review the recommendations and the Project team’s review and decide on their implementation or not. Accepted recommendations then are included in project plans and specs as appropriate by the project team.
Task 3 Documentation and Reporting Following the VE workshop, a draft report will be prepared. The report will document all the steps in the study, the VE process, key inputs, and study findings. The Draft VE report will be sent to the
District’s project team two (2) weeks after the presentation for review and comment. The District’s project and management teams will provide comments within a two-week review period after the report submission. Proposed revisions to the draft report will be discussed with the project and VE team, and changes will be made as appropriate within three (3) weeks of receiving comments. The final report documenting the VE study proceedings, will be submitted to the project team for project management purposes.
FDOT will be responsible to review recommendations, decide resolution of recommendations, and further implement into design; CONSULTANT will support FDOT by providing resolution memorandum template to assist resolution.
Task 4 Project Management The objective of this task is to manage the work elements for purposes of controlling costs, maintaining schedule, providing quality products that are appropriate for meeting the goals of the study, and for coordinating work activities with other members of the study team.
Stanley will provide contract administration and team management, coordination, and direction for the duration of the project. Scott Eshleman will be the project manager and will serve as the consultant’s primary point of contact with FDOT for this Scope of Work.
Deliverables Draft and Final Reports
Fee Estimate The activities will be completed for a lump sum fee amount of $55,253.06 established by the billing rates of the contract. Refer to Exhibit A.
File details come from the government source that posted it. Updated .