This document is an Amendment (No. 3) to a Standard Professional Services Agreement between the State of Florida Department of Transportation and Peters and Yaffee, Inc. The contract involves a transportation project on State Road 200 in Marion County, spanning from 100 ft. E. of SW 38th Court (MP 14.720) to SW 36th Avenue (MP 15.070). The original contract was executed on March 29, 2016, with this amendment dated May 5, 2017.

The amendment adds $3,557.00 in omitted fees from a previous amendment, bringing the Total Maximum Limiting Amount to $887,623.00. The contract includes multiple subconsultants for various services such as Infrastructure Engineers, Inc., Laura Turner Planning Services, Pond & Company Corporation, Omni Communications, LLC, Geotechnical and Environmental Consultants, Inc., Amdrill, Inc., and DRMP, Inc. The services cover basic services, utility coordination, environmental services, geotechnical services, design, and right-of-way survey services. There are no changes to the Scope of Services, and the payment method remains consistent with the original agreement.

View the file

Other files

File Type Posted
CN-550000-CAV38-00020000.pdf PDF
ContractBudgetExport.csv CSV file
CN-550000-C9O60-00030000.pdf PDF
CN-550000-C9O60-00040000.pdf PDF
CN-550000-C9O60-00050000.pdf PDF
CN-550000-C9O60-S0010000.pdf PDF
CN-550000-C9O60-S0030000.pdf PDF
CN-550000-C9O60-S0040000.pdf PDF
CN-550000-C9O60-S0040100.pdf PDF
CN-550000-C9O60.pdf PDF
CN-550000-C9O60-00020000.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Florida Department of Transportation

AMENDMENT

TO

STANDARD PROFESSIONAL SERVICES AGREEMENT

Amendment No.: 3 Execution Date:

Original Contract No.: C-9O60 Original Execution Date: March 29, 2016

Consultant Name: Peters and Yaffee, Inc.

Agreement Description: SR 200 from 100 ft. E. of SW 38th Court (MP 14.720) to SW 36th Avenue (MP 15.070), Marion County

Purpose of Amendment: Add Omitted Fees

The terms of the original agreement, referenced above, are hereby amended as follows:

Fees in the amount of $3,557.00 were inadvertently omitted from Amendment No. 2. The Total Maximum Limiting Amount for all services under this agreement as supplemented is $887,623.00.

Compensation is summarized on Attachment No. 1, Summary of Contract Fees, and payments shall remain in accordance with the previously established method of compensation.

This amendment shall be in effect as of the execution date of Amendment No. 2, April 26, 2017.

There are no changes to the Scope of Services.

Except as hereby modified, amended or changed, all of the terms and conditions of said original agreement and any amendments thereto will remain in full force and effect.

The following attachments are hereby incorporated into this Amendment:

Attachment No. 1, Summary of Contract Fees

PETERS & YAFFEE, INC. STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

BY: BY:

Name: Name: Richard B. Morrow, P.E.

Title: Title: Director of Transportation Development District Five

PROCUREMENT SERVICES REVIEW LEGAL REVIEW

Michelle Sloan District Counsel Procurement Services Manager District Five District Five

DocuSign Envelope ID: 24AC5ABA-F4F0-4D3A-B483-C4A7A67FA330

Mike Molkenbur

Project Manager President

Dow Peters

May 5, 2017

Financial Project ID No. 435659-2-32-01

Original

Contract thru

Amendment 2

This

Amendment

No. 3

Revised

Contract

Totals

LUMP SUM

Basic Services* (LS-2)

Peters and Yaffee, Inc. (prime) $470,945 $3,557 $474,502

Infrastructure Engineers, Inc. (sub) $54,021 $0 $54,021

Laura Kathleen Turner d/b/a Laura Turner Planning Services (sub) $29,585 $0 $29,585

Pond & Company Corporation (sub) $94,842 $0 $94,842

Utility Coordination* (LS-2)

Omni Communications, LLC $17,275 $0 $17,275

Subtotal Lump Sum Amount $666,668 $3,557 $670,225

LIMITING AMOUNTS

Environmental Services (LA-4)

Geotechnical and Environmental Consultants, Inc. (sub) $11,774 $0 $11,774

Geotechnical Services (LA-4)

Amdrill, Inc. (sub) $5,109 $0 $5,109

Geotechnical and Environmental Consultants, Inc. (sub) $52,215 $0 $52,215

Authorized Design & Right Of Way Survey Services (LA-4)

DRMP, Inc. (sub) $135,014 $0 $135,014

Supplemental Survey Services (LA-4)

DRMP, Inc. (sub) $13,286 $0 $13,286

Subtotal Limiting Amount $217,398 $0 $217,398

TOTAL MAXIMUM LIMITING AMOUNT $884,066 $3,557 $887,623

Table 1: Summary of Contract Fees

Attachment No. 1, Summary of Contract Fees

C-9O60, Amendment No. 3

SR 200 from 100 ft. E. of SW 38th court (MP 14.720) to SW 36th Avenue (MP 15.070), Marion County