CN-370000-WQ179-T8.pdf
PDF 383 KB Posted
- Contract number
- WQ179
- Issued by
- Florida
About this file
This is a Task Assignment (TA No. 8) issued by the State of Florida Department of Environmental Protection under Contract Number WQ179. The contractor is SediVision, LLC, with Denver J. Stutler, Jr. serving as the contractor's project manager. The Department's project manager is Michael Barr. The task assignment is effective through December 31, 2025, and was digitally signed by Angela Knecht, Secretary or Designee, on April 14, 2025.
The scope of work requires SediVision, LLC to provide mapping services and estimate the loss of capacity in wastewater tanks due to accumulated debris at two oxidation ditches located at the City of Clewiston Wastewater Treatment Plant (Project Number FL0040665). The contractor must submit a mapping plan within 30 days of assignment for Department approval, then complete the mapping process within 10 days of plan approval. Within 90 days of completion, the contractor must deliver a debris location map with supporting data and calculations showing volume-proportioning amounts and capacity loss as a percentage. The total task assignment value is $39,937.00 on a cost reimbursement basis. No bonds, retainage, or liquidated damages are required. The Department reserves the right to reject deliverables and may assess invoice reductions of 1% per day for missed timelines, with the option to require re-performance at no additional cost or terminate the contract for unsatisfactory performance.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Digitally signed by Angela Knecht Date: 2025.04.14 15:55:19 -04'00'
Attachment 1, Page 1 of 2
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment (TA) No.: 8 Scope of Work
ATTACHMENT 1
1. Scope of Work.
The Contractor shall provide services to map and estimate the loss of capacity in publicly owned utilities’ wastewater tanks due to accumulated debris at two (2) Oxidation Ditches at the City of Clewiston Wastewater Treatment Plant.
Sediment sampling may be included upon request from the public utility and written approval from the Department's Contract Manager.
2. Definitions.
In this Contract, the following terms shall be defined as set forth below:
a. Debris: Solid material (sand and grit) that accumulates at the bottom of wastewater tanks.
b. Publicly Owned Utilities: utilities owned by governmental entities or political subdivisions/public utility districts.
3. Contractor Responsibilities.
a. Tasks and timeline. Contractor will provide a mapping plan to the Department for each tank assigned within 30 days of assignment. The plan will include a price, estimated timeline and schedule of events. Once a plan is submitted, the Department will have ten (10) days to review and approve the plan. Once a plan is approved, Contractor may begin the mapping process in accordance with the agreed upon schedule.
Within ten (10) days of an approved plan, Contractor will use its scientifically-backed method of determining the amount of debris within an assigned tank and its loss of capacity according to the plan submitted to the Department.
b. Deliverables. Within 90 days of completion of the mapping process, Contractor will provide to the Department and the public utility:
i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved.
c. Performance Measures. The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
Maximum Budget for TA 8: $39,937.00
4. Department Responsibilities.
The deliverables must be received and accepted in writing by the Department’s Contract Manager before payment. If Department’s Contract Manager does not accept the deliverables within 15 days of receipt, they will be deemed rejected.
5. Enforcement.
The Department reserves the right to reject deliverables as incomplete, inadequate, or unacceptable due, in whole or in part, to the Contractor’s lack of satisfactory performance under the terms of the Contract. Failure to fulfill the applicable technical requirements or complete all tasks or activities in accordance with the Scope of Work will result
Attachment 1, Page 2 of 2 in rejection of the deliverable and the associated invoice. No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall: a. Re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within thirty (30) days of being notified of the unsatisfactory deliverable. b. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or Task Assignments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved; and/or 4) terminate the Contract for failure to perform. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
6. Additional Insurance Requirements.
None.
7. Payment and Performance Bonds.
There are no bonds required under this TA.
8. Liquidated Damages.
There are no liquidated damages under this TA.
9. Retainage.
No retainage is required under this TA.
10. Additional Terms.
None.