CN-370000-WQ179-T12.pdf
PDF 361 KB Posted
- Contract number
- WQ179
- Issued by
- Florida
About this file
This is a Task Assignment (TA No. 12) executed between the State of Florida Department of Environmental Protection and SediVision, LLC, with an expiration date of January 31, 2026. The contract is issued under Contract Number WQ179. The Department's Project Manager is Michael Barr, and the contractor's Project Manager is Denver J. Sutler, Jr. The project is located at the St Johns County Utilities Department North Beach Wastewater Treatment Plant (FLA011765).
The contractor shall provide services to map and estimate the loss of capacity in publicly owned utilities' wastewater tanks due to accumulated debris at one oxidation ditch, with sediment sampling available upon written request and Department approval. The contractor must submit a mapping plan within 30 days of assignment, with Department approval required within 10 days. Following approval, the contractor has 10 days to begin the mapping process using a scientifically-backed method. Deliverables, due within 90 days of completion, include a debris location map with supporting quantitative and visual data and calculations of volume-proportioning amounts and capacity loss as a percentage with detailed explanations. The contract is structured on a cost reimbursement basis with a Total TA Value of $22,297.00. The Department reserves the right to reject incomplete or inadequate deliverables, and failure to meet agreed timelines will result in invoice reductions of 1% per day unless the timeline is extended in writing. No bonds, retainage, liquidated damages, or additional insurance requirements apply under this task assignment.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sandra Waters Digitally signed by Sandra Waters Date: 2025.05.22 12:23:34 -04'00'
Attachment 1, Page 1 of 2
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment (TA) No.: 12 Scope of Work
ATTACHMENT 1
1. Scope of Work.
The Contractor shall provide wastewater tanks due to accumulated debris at one (1) oxidation ditch at the St Johns County Utilities Department s North Beach Wastewater Treatment Plant. Sediment sampling is may be added upon request from the public utility and written approval from the Department's Contract Manager.
2. Definitions.
In this Contract, the following terms shall be defined as set forth below:
a. Debris: Solid material (sand and grit) that accumulates at the bottom of wastewater tanks.
b. Publicly Owned Utilities: utilities owned by governmental entities or political subdivisions/public utility districts.
3. Contractor Responsibilities.
a. Tasks and timeline. Contractor will provide a mapping plan to the Department for each tank assigned within 30 days of assignment. The plan will include a price, estimated timeline and schedule of events. Once a plan is submitted, the Department will have ten (10) days to review and approve the plan. Once a plan is approved, Contractor may begin the mapping process in accordance with the agreed upon schedule.
Within ten (10) days of an approved plan, Contractor will use its scientifically-backed method of determining the amount of debris within an assigned tank and its loss of capacity according to the plan submitted to the Department.
b. Deliverables. Within 90 days of completion of the mapping process, Contractor will provide to the Department and the public utility:
i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved.
c. Performance Measures.
Manager, the Contractor may proceed with payment request submittal.
Maximum Budget for TA 12: $22,297.00
4. Department Responsibilities.
The before payment. If of receipt, they will be deemed rejected.
5. Enforcement.
The Department reserves the right to reject deliverables as incomplete, inadequate, or unacceptable due, in whole or
Contract. Failure to fulfill the applicable technical requirements or complete all tasks or activities in accordance with the Scope of Work will result
Attachment 1, Page 2 of 2 in rejection of the deliverable and the associated invoice. No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall: a. Re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within thirty (30) days of being notified of the unsatisfactory deliverable. b. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or Task Assignments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved; and/or 4) terminate the Contract for failure to perform. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
6. Additional Insurance Requirements.
None.
7. Payment and Performance Bonds.
There are no bonds required under this TA.
8. Liquidated Damages.
There are no liquidated damages under this TA.
9. Retainage.
No retainage is required under this TA.
10. Additional Terms.
None.