This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under DEP Contract No. HW554 with APTIM Environmental & Infrastructure, LLC. The task assignment, designated DC008L, pertains to operations and maintenance services at the Former One Stop Cleaners facility located at 3303 University Drive East, Coral Springs, Broward County, Florida. Melissa A Walsh serves as the DEP Contract Manager, while Eric Kramer, P.E., represents the contractor. The DEP Site number is ERIC_4123.
Task Assignment DC008L encompasses six months of operation and maintenance (O&M) of the soil vapor extraction (SVE) system from September 2021 through February 2022. The scope includes system maintenance, field and system data collection, verification of efficient system operation, and collection of quarterly vapor influent samples for laboratory analysis. Deliverables consist of a Quarterly O&M Report due March 25, 2022, and Paid Utility Invoices. The total task assignment value is $17,255.43, comprising three subtasks: Subtask 1 (Project Management) at $1,201.79; Subtask 2 (O&M Activities) at $13,113.64 with a fixed price of $14,315.43; and Subtask 3 (Utilities) at $2,940.00 under a Cost Plus Fixed Fee arrangement with utilities not to exceed $2,700 plus a handling fee of $240. Retainage is $0.00. The task completion date is May 25, 2022.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW554
D000 N/ADC008L
APTIM
Eric Kramer, P.E.
(850)-245-8960Melissa A Walsh
ERIC_4123
Former One Stop Cleaner
3303 University Dr E, Coral Springs, Broward
Operations and Maintenance
APTIM will conduct 6 months O&M of the soil vapor extraction system.
The payment of utility invoices associated with these O&M activities is the only portion of this Task Assignment which is Cost Plus Fixed Fee.
Quarterly O&M Report
03/25/2022
05/25/2022
$ 14,555.43 $ 0.00 $ 2,700.00
$ 0.00
Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.08.31 11:02:43 -04'00'
Melissa Walsh Digitally signed by Melissa Walsh Date: 2021.08.31 11:02:50 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.08.31 11:50:20 -04'00'
Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2021.08.31 13:07:22 -04'00'
$ 17,255.43
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Walsh_M Highlight
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Quarterly O&M Report 03/25/2022
Paid Utility Invoices 03/25/2022
Upon completion of all semi-annual O&M activities and FDEP approval of Quarterly O&M Report: Subtasks 1 & 2 $ 14,315.43
Upon receipt of Paid Utility Invoices Utilities (Cost Plus Fixed Fee): not to exceed $2700 Handling Fee: $240.00 Subtask 3
$ 2,940.00
$ 17,255.43
HW554
DC008L
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: APTIM Contract File Contract No. HW554
FROM: Melissa A Walsh, Project Manager
SUBJECT: Clothes Doctor
FAC # ERIC_4123
Task Assignment #DC008L Monitoring
DATE: August 31, 2021
Under this Task Assignment, APTIM will conduct 6 months of O&M. Work will be done according to the attached scope of work dated August 18, 2021.
Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate.
Subtask 2: Annual O&M Activities APTIM and DEP agreed to the proposed scope of work and level of effort. Subtask 2 includes six months of O&M
Subtask 3: Utilities APTIM and DEP agreed to the proposed scope of work and level of effort. Subtask 3 includes six months of utility service. The utility invoices will be submitted to the Department for reimbursement.
Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the APTM proposal. The final deliverable due date is March 25, 2022, and the completion date for the Task Assignment is May 25, 2022.
The final cost total for DC008L is $17,255.43
FDEP COST ESTIMATE
Contractor: APTIM Environmental & Infrastructure, LLC
Date: 8/18/2021
Task #: HW554-DC008L SubTask 1 Project Management SubTask 6
Site: One Stop Cleaners ERIC_4123 SubTask 2 2-O&M Sept 2021 - Feb 2022 SubTask 7
Activity/Phase: O&M and Annual GW Sampling SubTask 3 3-Utilities Sept 2021 - Feb 2022 SubTask 8
Project Manager: Eric Kramer SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$63.32 Client Program Manager E. Kramer 6 6.2 $63.32 Engineer/Scientist 5 E. Kramer 8 8 0 0 0 0 0 0 0 0 $60.61 Engineer/Scientist 5 G. Roberts 4 4 0 0 0 0 0 0 0 0 $25.92 Engineer/Scientist 1 K. McDonald 36 36 0 0 0 0 0 0 0 0 $25.53 Engineering Technician 2 J. Bell 52 52 0 0 0 0 0 0 0 0 $31.69 Designer 2 S. Ferianc 3 3 0 0 0 0 0 0 0 0 $25.04 Tech Publications Specialis H. Vining 2 2 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 Total Hours 111 6 105 0 0 0 0 0 0 0 0
Direct Labor $3,549.18 $394.35 $3,154.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 119.00% $4,223.53 $469.28 $3,754.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Overhead 20.90% $741.78 $82.42 $659.36 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 32.60% $1,157.03 $128.56 $1,028.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $9,671.52 $1,074.61 $8,596.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $177.46 $19.72 $157.74 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $582.00 $582.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $582.00 $582.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Equipment Procurement)
Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 (Services Procurement)
Subcontractor Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $2,700.00 $0.00 $2,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Broward Cty Permit/Fee $180.00 $180.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $2,880.00 $180.00 $2,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $258.00 $18.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $3,138.00 $198.00 $2,940.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $400.00 $400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $400.00 $400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 5 Copy of DC008L est
FDEP COST ESTIMATE
Contractor: APTIM Environmental & Infrastructure, LLC
Date: 8/18/2021
Task #: HW554-DC008L SubTask 1 Project Management SubTask 6
Site: One Stop Cleaners ERIC_4123 SubTask 2 2-O&M Sept 2021 - Feb 2022 SubTask 7
Activity/Phase: O&M and Annual GW Sampling SubTask 3 3-Utilities Sept 2021 - Feb 2022 SubTask 8
Project Manager: Eric Kramer SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Expendables $195.00 $195.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $2,124.30 $2,124.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,319.30 $2,319.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$16,288.28 $1,094.33 $12,253.95 $2,940.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subtotal $967.15 $107.46 $859.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee
Total Estimated Cost $17,255.43 $1,201.79 $13,113.64 $2,940.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost Estimate Page 2 of 5 Copy of DC008L est
LEVEL OF EFFORT / EXPENSE WORKSHEET
SITE :
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
TITLE STAFF WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer
Engineer/Scientist 5 G. Roberts 4
Engineer/Scientist 1 K. McDonald
Engineering Technician 2 J. Bell
Designer 2 S. Ferianc Semi-Annual O&M Report (Drafting) 3 Tech Publications Specialist 3H. Vining 2
TOTAL LABOR: 105
EQUIPMENT ITEM RATE UNIT USAGE
Expendables $32.50 Day 6 $195.00 Construction/O&M Kit $291.00 Day 6 $1,746.00 Construction/O&M Supplies $63.05 Day 6 $378.30 Well Caps (2") $10.20 each 0 $0.00 Well Locks $3.40 each 0 $0.00 55-gallon Drum $58.20 each 0 $0.00
TOTAL EQUIPMENT: $2,319.30
VEHICLE TYPE RATE UNIT USAGE
Automobile $68.00 Day 0 $0.00 Van or Truck $97.00 Day 6 $582.00
TOTAL VEHICLE: $582.00
Monthly Base Work - {Mob (1 hr), Travel Round Trip (2 hrs), SVE O&M (5 hrs) {total = 8 hrs x 6 mo = 48 hrs}. Additional work (each quarter) includes SVE Vacuum Readings (total 4 hrs).
Semi-Annual O&M Report (Document Production)
Preparation of CEF/LOE (3 hrs), Update GIS Database Files (1 hr) Daily telemetry checks to verify the SVE system is operating as scheduled (3 hrs per month x 6 months = 18 hrs). SVE performance evaluation and system optimization (6 hrs).
Preparation of Semi-Annual O&M Report (12 hrs which includes preparation of SVE operational tables, calculations, figures, O&M site visit summary, SVE system operation & performance).
One Stop Cleaners 2-O&M Sept 2021 - Feb 2022
August 18, 2021
PE Review of monthly O&M checklists for submittal (6 hrs), Compilation and Submittal of O&M Checklists and analytical (2 hrs)
2-Q1&Q2 O&M wRpt Page 3 of 5 Copy of DC008L est
PER DIEM STAFF RATE UNIT USAGE
Hotel $99.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day One Leave Between 6:00 - Noon $30.00 Day 0 $0.00 Day One leave before 6:00 PM $19.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00
TOTAL PER DIEM: $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA Method 8260 (Halos Only) $66.00 0 0 $0.00 EPA Method 8260 (Volatiles) $135.00 0 0 $0.00 EPA Method TO-15 (VOCs) (SVE Influent) $200.00 2 $400.00 Ice Appendix E, page 9 $5.00 0 $0.00 Sample Shipping (small) $63.00 0 $0.00 Sample Shipping (large) $104.00 0 $0.00
TOTAL LAB: $400.00
SUBCONTRACTOR COSTS
NAME PURPOSE Rate UNIT USAGE TOTALS Misc. Supplies Home Depot/Lowes/Equivilent $33.86 each 0 $0.00 Broward County Board of Commissioners (Air Permit Fee) $180.00 each 1 $180.00
TOTAL SUB: $180.00
2-Q1&Q2 O&M wRpt Page 4 of 5 Copy of DC008L est
SITE :
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
TITLE STAFF WORK DESCRIPTION HOURS
Engineer/Scientist 5 E. Kramer Engineer/Scientist 5 G. Roberts Engineer/Scientist 1 K. McDonald Engineering Technician 2 J. Bell Designer 2 S. Ferianc Tech Publications Specialist 3 H. Vining
TOTAL LABOR 0
EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS
TOTAL EQUIPMENT $0.00
VEHICLE TYPE RATE UNIT USAGE TOTALS
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USAGE TOTALS
TOTAL PER DIEM $0.00
LABORATORY COSTS PC&B
PARAMETER RATE # SAMPLES #QA/QC
TOTAL LAB $0.00
SUBCONTRACTOR
NAME PURPOSE Rate Unit Usage TOTALS FPL-Electricity (Sept, Oct, Nov, Dec, Jan, Feb) $260.00 Month 6 $1,560.00 AT&T-Phone (Sept, Oct, Nov, Dec, Jan, Feb) $190.00 Month 6 $1,140.00 handling fee Electrical Service $20.00 each 6 $120.00 handling fee Telephone Service $20.00 each 6 $120.00
TOTAL $2,940.00
One Stop Cleaners 3-Utilities Sept 2021 - Feb 2022
August 18, 2021
3-Q1&2 Utilities Page 5 of 5 Copy of DC008L est
Proposed Scope of Work One Stop Cleaners Task Assignment DC008L FAC ID No. 069501160 (ERIC_4123) APTM Environmental & Infrastructure, Inc. (APTIM) 08/18/21
Task Assignment (TA) DC008L is for six months of operation and maintenance (O&M) for the soil vapor extraction (SVE) system at the former One Stop Cleaners located in Coral Springs. The proposed level of effort continues SVE operation from September 2021 through February 2022.
The services include system maintenance, field and system data collection, verification of efficient system operation and collection of two quarterly vapor influent samples from the remediation system for field screening with a PID and fixed base laboratory analysis. The TA includes the O&M services from September 2021 through February 2022). A semi-annual remedial system operation report will be prepared under this TA. APTIM proposes submittal of five monthly O&M checklists and vapor influent analysis as the deliverables for this TA with a due date for the submittal of March 25, 2022.
The LOE and proposed scope of work do not include system diagnostics and repairs. Required diagnostic and repair services will be estimated, approved and funded individually, as required and based on O&M findings. An air license with a two-year duration is issued by Broward County for operation of the system was renewed in January 2020, so renewal fees are included in this Task. A task completion date of April 29, 2022 is recommended.
APTIM proposes to perform this scope of work in accordance with the terms and conditions of the Contract between the Florida Department of Environmental Protection and APTIM dated February 16, 2011 (DEP Contract No. HW554). APTIM will begin the proposed scope of work upon issuance of the Task Assignment Notification.
If you have any questions, please do not hesitate to call.
| Cost Estimate |
| 2-Q1&Q2 O&M wRpt |
| 3-Q1&2 Utilities |