This document is a Consultant's Task Assignment Notification from the Florida Department of Environmental Protection's Division of Recreation and Parks, involving Stantec Consulting Services Inc. as the consultant for the Fakahatchee Strand Preserve State Park Janes Trail & Culvert Improvements project. The contract is identified as CN819, with involvement from Collier County, the South Florida Water Management District (SFWMD), and the U.S. Army Corps of Engineers (USACE).
The task assignment covers construction administration services for a 6-mile trail project, including 16 distinct subtasks ranging from bidding services and construction phase observations to final inspections and certifications. The total contract value is $90,714.49, comprised of a fixed price cost of $48,314.49 and reimbursable costs of $42,400.00. Reimbursable costs include $35,000 for Collier County construction fees, $1,900 for SFWMD permit fees, $5,000 for Collier County right-of-way permit fees, and $500 for USACE fees. The project is scheduled to be completed by September 30, 2026, with payment contingent upon approval of deliverables for each subtask by the Florida Department of Environmental Protection.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN819-T2.pdf | ||
| CN-370000-CN819-T3.pdf | ||
| CN-370000-GC921.pdf | ||
| CN-370000-CN819.pdf | ||
| CN-370000-GC892-T5.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division of Recreation and Parks
Consultant’s Task Assignment Notification
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Contract Manager, FDEP Signature Date
4.
Consultant Signature Date
5.
Contract Authority, FDEP Signature Date
CN819 61562C 01
Fakahatchee Strand Preserve State Park Janes Trail & Culvert Improvements
Stantec
Chris Brockmeier, PE
(239) 220-1460 chris.brockmeier@stantec.com
Vu Nugyen
(850) 245-2630 vu.nguyen@floridadep.gov
Moving from expired CN222 construction administration services and additional permit fee payments per the attached proposal dated March 7, 2025. Subtasks using CN222 rates are indicated by *.
Theresa Carron
Upon Execution 09/30/2026
$48,314.49 $42,400.00
$90,714.49
Tamika Bass
Theresa Carron
Vu Nugyen
Chris E. Brockmeier, PE
Michael W. Foster Jr., PE
03/14/2025
03/14/2025
03/14/2025
03/14/2025
03/14/2025
Division of Recreation and Parks
Consultant’s Task Assignment Notification
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total: $90,714.49
3510 Kraft Road, Suite 200, Naples, FL 34105
March 7, 2025
Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN-819 TBD
Jane’s Scenic Trail Roadway Improvements and Culvert Replacements
Dear Teri;
For your review, Stantec Consulting Services Inc., has provided a proposal summary and man-hour documentation for the service tasks identified below:
Construction Administration Services Description:
Subtask 1: Bidding Services Subtask 2: Construction Phase Services (RFIs and Shop Drawings) Subtask 3: Construction Phase Services (Construction Observation Site Visit #1) Subtask 4: Construction Phase Services (Construction Observation Site Visit #2) Subtask 5: Construction Phase Services (Construction Observation Site Visit #3) Subtask 6: Construction Phase Services (Construction Observation Site Visit #4) Subtask 7: Construction Phase Services (Construction Observation Site Visit #5) Subtask 8: Construction Phase Services (Construction Observation Site Visit #6) Subtask 9: Construction Phase Services (Construction Observation Site Visit #7) Subtask 10: Construction Phase Services (Construction Observation Site Visit #8) Subtask 11: Construction Phase Services (Construction Observation Site Visit #9) Subtask 12: Substantial Inspection Subtask 13: Collier County Final Inspection Subtask 14: SFWMD Certification Subtask 15: USACE Certification (Close out previous culvert permit) Subtask 16: Collier County Pre-Construction Services
Please review the attached Proposal Summary and deliverables.
Sincerely, Chris E. Brockmeier, P.E. Michelle Kelly, P. E.
Stantec Consulting Services Inc. Stantec Consulting Services Inc.
TA1
Jane’s Scenic Trail Roadway Improvements and Culvert Replacements Total length of project: 6 miles (does not include 5 miles less use)
CN819, TA TBD
Construction Administration Services Description:
Subtask 1: Bidding Services Subtask 2: Construction Phase Services (RFIs and Shop Drawings) Subtask 3: Construction Phase Services (Construction Observation Site Visit #1) Subtask 4: Construction Phase Services (Construction Observation Site Visit #2) Subtask 5: Construction Phase Services (Construction Observation Site Visit #3) Subtask 6: Construction Phase Services (Construction Observation Site Visit #4) Subtask 7: Construction Phase Services (Construction Observation Site Visit #5) Subtask 8: Construction Phase Services (Construction Observation Site Visit #6) Subtask 9: Construction Phase Services (Construction Observation Site Visit #7) Subtask 10: Construction Phase Services (Construction Observation Site Visit #8) Subtask 11: Construction Phase Services (Construction Observation Site Visit #9) Subtask 12: Substantial Inspection Subtask 13: Collier County Final Inspection Subtask 14: SFWMD Certification Subtask 15: USACE Certification (Close out previous culvert permit and proposed exemption) Subtask 16: Collier County Pre-Construction Services
Deliverable:
Subtask 1: Submit email to FDEP Project Manager with Pre-bid meeting comments Subtask 2: Copy of Stantec’s response to RFIs and Shop Drawings Subtask 3: Site Observation Memo (Site Visit #1) Subtask 4: Site Observation Memo (Site Visit #2) Subtask 5: Site Observation Memo (Site Visit #3) Subtask 6: Site Observation Memo (Site Visit #4) Subtask 7: Site Observation Memo (Site Visit #5) Subtask 8: Site Observation Memo (Site Visit #6) Subtask 9: Site Observation Memo (Site Visit #7) Subtask 10: Site Observation Memo (Site Visit #8) Subtask 11: Site Observation Memo (Site Visit #9) Subtask 12: Substantial Inspection Memo Subtask 13: Collier County Final Inspection Memo Subtask 14: Submittal of Certification to SFWMD Subtask 15: Submittal of Certification to USACE Subtask 16: Collier County Pre-Construction Services
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
TA1
Fixed Price Cost:
Subtask 1 – Bidding Services Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 4 $ 664.20
Stantec Project Engineer $ 118.68 7 $ 830.76
Stantec Staff Engineer $ 87.78 8 $ 702.24
Stantec CADD Designer $ 64.50 4 $ 258.00
Stantec Administrative Assistant $ 53.16 6 $ 318.96
Subtask 1 Total $ 2,774.16
Subtask 2 – Construction Phase Services (RFIs and Shop Drawings) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 8 $ 1,328.40
Stantec Project Engineer $ 118.68 36 $ 4,272.48
Stantec Staff Engineer $ 87.78 56 $ 4,915.68
Stantec CADD Designer $ 64.50 26 $ 1,677.00
Stantec Administrative Assistant $ 53.16 15 $ 797.40
Subtask 2 Total $ 12,990.96
Subtask 3 – Construction Phase Services (Site Visit #1) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 3 Total $ 1,955.62
Subtask 4 – Construction Phase Services (Site Visit #2) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 4 total $ 1,955.62
Subtask 5 – Construction Phase Services (Site Visit #3) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71
Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
1E Sub-Total $ 1,955.62
Subtask 6 – Construction Phase Services (Site Visit #4) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 6 Total $ 1,955.62
Subtask 7 – Construction Phase Services (Site Visit #5) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 7 Total $ 1,955.62
Subtask 8 – Construction Phase Services (Site Visit #6) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 8 Total $ 1,955.62
Subtask 9 – Construction Phase Services (Site Visit #7) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 9 Total $ 1,955.62
Subtask 10 – Construction Phase Services (Site Visit #8) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10
Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 10 Total $ 1,955.62
Subtask 11– Construction Phase Services (Site Visit #9) Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Principal Engineer $ 232.11 0.5 $ 116.05 Stantec Senior Project Engineer $ 166.05 2 $ 332.10 Stantec Project Engineer $ 118.68 3.25 $ 385.71 Stantec Senior Inspector $ 71.28 13.5 $ 962.28 Stantec Administrative Assistant $ 53.16 3 $ 159.48
Subtask 11 Total $ 1,955.62
Subtask 12 – Substantial Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 6 $ 996.30
Stantec Project Engineer $ 118.68 9 $ 1,068.12
Stantec CADD Designer $ 64.50 6 $ 387.00
Stantec Senior Inspector $ 71.28 16 $ 1,140.48
Stantec Administrative Assistant $ 53.16 6 $ 318.96
Subtask 12 Total $ 3,910.86
Subtask 13–Collier County Final Inspection Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 5 $ 830.25
Stantec Project Engineer $ 118.68 7 $ 830.76
Stantec CADD Designer $ 64.50 4 $ 258.00
Stantec Senior Inspector $ 71.28 12 $ 855.36
Stantec Administrative Assistant $ 53.16 10 $ 531.60
Subtask 13 Total $ 3,305.97
Subtask 14 – SFWMD Certification Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 2 $ 332.10
Stantec Project Engineer $ 118.68 6 $ 712.08
Stantec Senior Inspector $ 71.28 8 $ 570.24
Stantec Administrative Assistant $ 53.16 5 $ 265.80
Subtask 14 Total $ 1,880.22
Subtask 15 – USACE Certification Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 2 $ 332.10
Stantec Project Engineer $ 118.68 6 $ 712.08
Stantec Senior Inspector $ 71.28 8 $ 570.24
Stantec Administrative Assistant $ 53.16 5 $ 265.80
Subtask 15 Total $ 1,880.22
Subtask 16: Collier County Pre-Construction Services
Description: Stantec will coordinate with DEP staff and the selected Construction Contractor to prepare and submit a pre-construction notification package which will include an engineering affidavit, project schedule, points of contact and all necessary permits and approved construction plans. Coordinate NPDES-NOI and ROW Permit from Contractor and upload to Collier County Portal to allow for Pre-Con meeting request with Collier County. Stantec will schedule and attend one (1) meeting virtually with Collier County, DEP Project Manager and the selected Construction Contractor.
Deliverable: Stantec will provide a copy of the Collier County Pre-Construction submittal package in conformance with the Collier County Construction (CNST) Plan permit conditions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 16 – Collier County Pre-Construction Services Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost Stantec Senior Project Engineer $ 166.05 8 $ 1,328.40 Stantec Project Engineer $ 118.68 16 $ 1,898.88 Stantec Administrative Assistant $ 53.16 14 $ 744.24
Subtask 16 Total: $3,971.52
Subtask 17: Collier County Permit Fees
Reimbursable Cost:
Collier Co. Construction Fees (CNST) $35,000 SFWMD Permit Fee $1,900 Collier Co. ROW Permit Fee $5,000
USACE $500
TOTAL - $42,400.00
Summary of Fees:
Subtask Subtask Fixed
Price Cost Subtask Reimbursable
Subtask 1 – Bidding Services $2,774.18 Subtask 2 – Construction Phase Services (RFIs & Shop Drawings
$12,990.96
Subtask 3 – Construction Phase Services – Site Visit #1 $1,955.62 Subtask 4 – Construction Phase Services – Site Visit #2 $1,955.62 Subtask 5 – Construction Phase Services – Site Visit #3 $1,955.62 Subtask 6 – Construction Phase Services – Site Visit #4 $1,955.62 Subtask 7 – Construction Phase Services – Site Visit #5 $1,955.62 Subtask 8: - Construction Phase Services – Site Visit #6 $1,955.62 Subtask 9: Construction Phase Services – Site Visit #7 $1,955.62 Subtask 10: Construction Phase Services –Site Visit #8 $1,955.62 Subtask 11: Construction Phase Services –Site Visit #9 $1,955.62 Subtask 12: Substantial Inspection $3,910.86 Subtask 13: Collier County Final Inspection $3,305.97 Subtask 14: SFWMD Certification $1,880.22
Subtask 15: USACE Exemption Certification $1,880.22 Subtask 16: Collier County Pre-Con Services $3,971.52 Subtask 17: Collier County Permit Fees:
Collier Co. Construction Fees (CNST) $35,000, SFWMD Permit Fee $1,900 Collier Co. ROW Permit Fee $5,000
USACE $500
$42,400.00
Total Fixed Price Cost: $48,314.49
Total Reimbursable Cost: $42,400.00
Overall Total Cost: $90,714.49 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Project Schedule:
Activity Duration From NTP (Calendar Days)
Subtask 1: Bidding Services Based on construction schedule TBD Subtask 2: Construction Phase Services (RFIs and Shop Drawings)
Based on construction schedule TBD
Subtask 3: Construction Phase Services (Construction Observation Site Visit #1)
Based on construction schedule TBD
Subtask 4: Construction Phase Services (Construction Observation Site Visit #2)
Based on construction schedule TBD
Subtask 5: Construction Phase Services (Construction Observation Site Visit #3)
Based on construction schedule TBD
Subtask 6: Construction Phase Services (Construction Observation Site Visit #4)
Based on construction schedule TBD
Subtask 7: Construction Phase Services (Construction Observation Site Visit #5)
Based on construction schedule TBD
Subtask 8: Construction Phase Services (Construction Observation Site Visit #6)
Based on construction schedule TBD
Subtask 9: Construction Phase Services (Construction Observation Site Visit #7)
Based on construction schedule TBD
Subtask 10: Construction Phase Services (Construction Observation Site Visit #8)
Based on construction schedule TBD
Subtask 11: Construction Phase Services (Construction Observation Site Visit #9)
Based on construction schedule TBD
Subtask 12: Substantial Inspection Based on construction schedule TBD Subtask 13: Collier County Final Inspection Completed within 60 days of Final
Construction Duration Subtask 14: SFWMD Certification Completed within 60 days of Final
Construction Duration Subtask 15: USACE Certification Completed within 60 days of Final
Construction Duration Subtask 16: Collier County Pre-Construction Services Completed within 60 days of Final
Construction Duration