CN-370000-CN665-T1CO3.pdf
PDF 446 KB Posted
- Contract number
- CN665
- Issued by
- Florida
About this file
This document is a Task Assignment Change Order form from the Florida Department of Environmental Protection (FDEP) for the Keys Tidal Connection Restoration project at Curry Hammock State Park. The primary consultant is Gresham Smith, with involvement from the Florida Keys Aqueduct Authority (FKAA). The contract involves the Florida Department of Transportation (FDOT) and is focused on waterline and culvert design work.
The contract change order authorizes Gresham Smith to complete design services for a new waterline, including traffic control revisions, culvert design modifications, and waterline design phases from preliminary through issued construction documents. The total budget is $235,750.84, with $230,272.84 in fixed labor costs and $5,478.00 in reimbursable expenses. The project involves redesigning a 30-inch waterline within FDOT right-of-way, with FDEP responsible for design costs and FKAA responsible for permitting and construction administration. The design will be completed in multiple phases, including preliminary design, 60% and 90% plan development, final plan submission, and issued construction documents, with a total project duration of approximately 175 calendar days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN665-T1.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-370000-CN665-T1CO1.pdf | ||
| CN-370000-CN665.pdf | ||
| CN-370000-GC121-T04-01.pdf | ||
| CN-370000-CN665-T1CO2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
665 1 3 FLTC 23
Keys Tidal Connection Restoration
Gresham Smith
Jody Braswell, PE (678) 836-9864 jody.braswell@greshamsmith.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
This Task Assignment is to perform the necessary actions needed to complete the design for the waterline relocation design necessary to allow for construction of the culverts in the Keys Tidal Connection Restoration project. Per proposal dated 3/26/2025.
$ 13,404.58 $ 102,553.43 $ 115,958.01 $ 46,366.83 $ 1,038,812.71 $ 1,085,179.54 $ 5,478.00 $ 230,272.84 $ 235,750.84 $ 51,844.83 $ 1,269,085.55 $ 1,320,930.38
05/02/2023
01/19/2025
06/30/2025
06/30/2025
Lisa Yarborough Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2025.03.26 13:49:59 -04'00' 03/26/2025
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2025.03.26 14:23:17 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2025.03.27 09:00:12 -04'00'
Jody Braswell Braswell, Jody Digitally signed by Braswell, Jody Date: 2025.03.27 15:54:52 -04'00'
Alexis A. Lambert
FLTC23 37538010007 100025/00 000286 U1621 131300 AG $ 92,985.16
FLTC23 37010100001 103259/00 000286 131300 AF $ 142,765.68
$ 235,750.84(37-10-1-000286-37500400-00-100025-00) and (37-10-1-000286-37200100-00-103259-00)
Curry Hammock State Park
Digitally signed by Mara Gambineri Date: 2025.04.22 16:18:25 -04'00'
Mr. Garland Sandel - FDEP March 26, 2025
Page | 1
Project Description: Curry Hammock State Park Waterline Design -
CN665, Task Assignment 1, Change Order 3
This Task Assignment is to perform the necessary actions needed to complete the preliminary and final design the waterline relocation design necessary to allow for construction of the culverts in the Keys Tidal Connection Restoration project. The existing 30” waterline is owned by Florida Keys Aqueduct Authority (FKAA) and is within the Florida Department of Transportation’s right-of-way. Tentative agreement between FKAA and FDEP required FDEP to be responsible for all design costs, and FKAA would be responsible for permitting and the materials portion of the construction costs, as well as construction administration related to the waterline. Also included in this task assignment is modifications to the proposed concrete culverts to be phased for the waterline construction and also for phasing the construction into two contracts to optimize budgeting.
The final design of the waterline will be included in a future Task Assignment.
The following summarizes the revisions to this Task Assignment:
Item Reimbursement Fixed Fee Total
Original Task Amount $13,404.58 $102,553.43 $115,958.01 Task Amount including all previous Change Orders $46,366.83 $1,038,812.71 $1,085,179.54 Net increase/decrease in task amount for this Change Order $5,478.00 $230,272.84 $235,750.84 Total Amounts with all Change Orders $51,844.83 $1,269,085.55 $1,320,930.38
This task assignment includes the services and design of the following facilities at Curry Hammock State Park:
8. Traffic Control Revisions – 2 Construction Contracts
9. Culvert Design Revisions- Waterline Phasing
a. West Culvert Design Modifications
b. East Culvert Design Modifications
10. Waterline Design
a. Waterline Design – Preliminary Design
b. Waterline Design – 60% Phase
c. Waterline Design – 90% Phase
d. Waterline Design – Final Plan Submission
e. Waterline Design – Issued for Construction Documents
Page | 2
Task 8: Traffic Control Revisions
Description FDEP has determined that available construction funding could best be optimized by providing for 2 separate construction phases. The eastern portion of the project, including the east culvert would be constructed in the first construction advertisement while the western portion, including the west culvert, would be included in a second construction contract. The temporary traffic control plan, already developed beyond 60% phase must be revised to account for the different construction phases and limits of work.
Deliverables: Final traffic control plans in pdf format, to be submitted to FDOT for approval with the 90% roadway design plans.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Company Classification Hours Billable Rate Revenue
Gresham Smith (GS) Principal/Chief Engr. 8 $226.27 $1,810.16 Gresham Smith (GS) Project Manager 0 $171.92 $0.00 Gresham Smith (GS) Project Engineer 24 $180.77 $4,338.48 Gresham Smith (GS) Engineer 48 $117.95 $5,661.60 Gresham Smith (GS) Engineering Intern 24 $80.25 $1,926.00 Gresham Smith (GS) Engineering Tech 50 $90.98 $4,549.00 Gresham Smith (GS) Administrative 6 $83.38 $500.28
Subtotal = $18,785.52
Task 8 – Traffic Control Revisions - 2 Construction Contracts
Page | 3
Task 9 Culvert Design Revisions – Waterline Phasing
Description: The project scope initially included concrete box culverts constructed in two phases; the “Gulf” side as Phase 1 and the “Ocean” side as Phase 2, with temporary shoring designed along the phasing line to support highway traffic. In order to avoid a temporary waterline construction with a large construction cost, FKAA requested that the initial Phase 1 of the culvert construction be divided in Phase 1A and 1B. This would allow for the new waterline to be constructed on top of Phase 1A culvert while the existing line remains in service. Then Phase 1B would remove the old waterline and complete the Phase 1 portion of the culverts.
Subtask 9A – West Culvert Design Revisions – Waterline Phasing: Gresham Smith will modify the design for the culverts to account for the multiphase construction, including re-performing the FDOT culvert design program to account for revised quantities, additional splices, and additional phasing requirements. This task will also consider additional details for dewatering the excavation and support of the existing waterline and the retaining wall design along the outside of the realigned trail.
Deliverables: The 90% culvert plans will include the redesign of the culverts, including signed and sealed design calculations in pdf format.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Gresham Smith (GS) Project Manager 0 $171.92 $0.00 Gresham Smith (GS) Project Engineer 20 $180.77 $3,615.40 Gresham Smith (GS) Engineer 24 $117.95 $2,830.80 Gresham Smith (GS) Engineering Intern 24 $80.25 $1,926.00 Gresham Smith (GS) Engineering Tech 52 $90.98 $4,730.96 Gresham Smith (GS) Administrative 4 $83.38 $333.52
Subtotal = $15,246.84
Subtask 9A – West Culvert Design Revisions - Waterline Phasing
Page | 4
Subtask 9B – East Culvert Design Revisions – Waterline Phasing: Ebbstone will modify the design for the culverts to account for the multiphase construction, including re-performing the FDOT culvert design program to account for revised quantities, additional splices, and additional phasing requirements. This task will also consider additional details for dewatering the excavation and support of the existing waterline and the retaining wall design along the outside of the realigned trail.
Deliverables: The 90% culvert plans will include the redesign of the culverts, including signed and sealed design calculations in pdf format.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Ebbstone Chief Engineer 16 $215.16 $3,442.56 Ebbstone Senior Project Manager 16 $186.91 $2,990.56 Ebbstone Senior Project Engineer 80 $164.47 $13,157.60
Subtotal = $19,590.72
Subtask 9B – East Culvert Design Revisions - Waterline Phasing
Page | 5
Task 10 Waterline Design
Description: Gresham Smith will design a new waterline on behalf of the Florida Keys Aqueduct Authority (FKAA) within the full construction limits of the FDEP’s Keys Tidal Restoration project. The new waterline could be constructed in phases along with the culvert and embankment construction in order to allow the existing 30” line to remain in service during construction.
Construction Administration, bidding support, and as-built drawings are not included in this task assignment and would be required to be added in a subsequent task assignment.
It is assumed that all state and federal environmental permitting will be included in the overall project permitting phase and no additional environmental permitting will be required. All local permitting including drinking water permitting will be procured by FKAA.
Subtask 10A – Waterline Design – Preliminary Design: Following the approval of this task assignment and Notice to Proceed, Gresham Smith will begin preliminary design phase to include consultation with FKAA and FDEP, develop and document the design criteria, develop preliminary plans including the limits of construction and phasing requirements, prepare outline specifications, a written description of the work and prepare an Opinion of Probable Cost (OPC).
This subtask will include a kickoff meeting with FDEP and FKAA, development of preliminary route and layout, and a virtual design review with FKAA.
Deliverables: A design memorandum will be submitted in pdf format to include the design criteria, preliminary plans/layout, outline specifications and the OPC.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Gresham Smith (GS) Project Manager 48 $171.92 $8,252.16 Gresham Smith (GS) Project Engineer 120 $180.77 $21,692.40 Gresham Smith (GS) Engineer 24 $117.95 $2,830.80 Gresham Smith (GS) Engineering Intern 24 $80.25 $1,926.00 Gresham Smith (GS) Engineering Tech 24 $90.98 $2,183.52 Gresham Smith (GS) Administrative 8 $83.38 $667.04
Subtotal = $39,362.08
Subtask 10A – Waterline Design - Preliminary Design
Page | 6
Subtask 10B – Waterline Design – 60% Phase: Following authorization to proceed with the final waterline design, Gresham Smith will further develop the necessary drawings and forms needed to move the design to a 60% level of completion.
This subtask will include:
A site visit by key design staff, Creation of plan and profile sheets, Creation of plan detail sheets (standard details to be provided by FKAA in cadd format) Internal plan review and quality assurance review, An updated OPC, Development of regulatory approval requirements, Development of material specifications.
Deliverables: Design drawings will be presented to 60% level of detail and provided in pdf format. The OPC will be refined and updated. Draft construction specifications will be submitted in pdf format.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection
Gresham Smith (GS) Project Manager 48 $171.92 $8,252.16 Gresham Smith (GS) Project Engineer 160 $180.77 $28,923.20 Gresham Smith (GS) Engineer 160 $117.95 $18,872.00 Gresham Smith (GS) Engineering Intern 80 $80.25 $6,420.00 Gresham Smith (GS) Engineering Tech 24 $90.98 $2,183.52 Gresham Smith (GS) Administrative 8 $83.38 $667.04
Subtotal = $67,128.08
Reimbursable Costs Task Description Unit Quantity Unit Cost Subtotal Gresham Smith - Car Rental Days 8 $55.00 $440.00 GS - Fuel for Rental Gal 30 $5.00 $150.00 GS - Lodging/Hotel Nights 8 $225.00 $1,800.00 GS - Per Diem Days 8 $36.00 $288.00 GS - Air Fare Round Trip 4 $700.00 $2,800.00
Total for Subtask 10B $72,606.08
Subtask 10B – Waterline Design - 60% Phase
Reimbursable Total Cost for Subtask 10B $5,478.00
Page | 7
Subtask 10C – Waterline Design – 90% Phase: Following authorization to continue with the final waterline design, Gresham Smith will further develop the necessary drawings and forms needed to move the design to a 90% level of completion.
This subtask will include:
Refinement of plan and profile sheets, Refinement of plan detail sheets, Internal plan review and quality assurance review, An updated OPC, Completion of regulatory approval requirements, Completion of material specifications.
Deliverables: Design drawings will be presented to 90% level of detail and provided in pdf format. The OPC will be refined and updated. Revised construction specifications will be submitted in pdf format.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Company Classification Hours Billable Rate Revenue Gresham Smith (GS) Principal/Chief Engr. 8 $226.27 $1,810.16 Gresham Smith (GS) Project Manager 40 $171.92 $6,876.80 Gresham Smith (GS) Project Engineer 120 $180.77 $21,692.40 Gresham Smith (GS) Engineer 120 $117.95 $14,154.00 Gresham Smith (GS) Engineering Intern 60 $80.25 $4,815.00 Gresham Smith (GS) Engineering Tech 24 $90.98 $2,183.52 Gresham Smith (GS) Administrative 8 $83.38 $667.04
Total for Subtask 10C $52,198.92
Subtask 10C – Waterline Design - 90% Phase
Page | 8
Subtask 10D – Waterline Design – Final Plan Submission: Following authorization to continue with the final waterline design, Gresham Smith will perform any final plan changes requested by the FKAA to meet local requirements and policies; and submit draft version of the final construction documents for final signoff by all review parties.
This subtask will include:
Completion of all plans and construction documents.
Deliverables: Design drawings will be completed, but not signed, nor sealed. A pdf version will be submitted to FDEP and FKAA for final approval.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Company Classification Hours Billable Rate Revenue Gresham Smith (GS) Principal/Chief Engr. 6 $226.27 $1,357.62 Gresham Smith (GS) Project Manager 20 $171.92 $3,438.40 Gresham Smith (GS) Project Engineer 32 $180.77 $5,784.64 Gresham Smith (GS) Engineer 12 $117.95 $1,415.40 Gresham Smith (GS) Engineering Intern 12 $80.25 $963.00 Gresham Smith (GS) Engineering Tech 12 $90.98 $1,091.76 Gresham Smith (GS) Administrative 1 $83.38 $83.38
Total for Subtask 10D $14,134.20
Subtask 10D– Waterline Design - Final Plan Submission
Page | 9
Subtask 10E – Waterline Design – Issued for Construction Documents: Following authorization to finalize and submit the plans for construction, any final minor updates will be completed; and final construction documents will be signed and sealed for use in bidding and construction.
This subtask will include:
Completion of all plans and construction documents.
Deliverables: Design drawings will be completed, signed, and sealed. A pdf version will be digitally signed and submitted and cadd files will be provided to both FDEP and FKAA.
Performance Measure: Deliverables will be reviewed by the Florida Department of Environmental Protection (FDEP) within two weeks of submittal to confirm they are complete, accurate, and timely.
Company Classification Hours Billable Rate Revenue Gresham Smith (GS) Principal/Chief Engr. 2 $226.27 $452.54 Gresham Smith (GS) Project Manager 4 $171.92 $687.68 Gresham Smith (GS) Project Engineer 8 $180.77 $1,446.16 Gresham Smith (GS) Engineer 4 $117.95 $471.80 Gresham Smith (GS) Engineering Intern 4 $80.25 $321.00 Gresham Smith (GS) Engineering Tech 4 $90.98 $363.92 Gresham Smith (GS) Administrative 1 $83.38 $83.38
Total for Subtask 10E $3,826.48
Subtask 10E– Waterline Design - Issued for Construction Documents
Page | 10
Project Schedule: Contract Execution Date – TBD
Activity Duration (calendar Days)
Dates
Task 8 – Traffic Control Revisions 45 Days Start at Task 9A – West Culvert Design Revisions 30 Days Concurrent with
Task 8 Task 9B – East Culvert Design Revisions 30 Days Concurrent with
Task 8 Task 10A – Waterline Design – Preliminary Design 30 Days Start at
Task 10B – Waterline Design – 60% Phase 30 Days Following Task 10A
Task 10C – Waterline Design - 90% Phase 30 Days Following Task 10B
Task 10D – Waterline Design – Final Plan Submission 15 Days Following Task 10C
Task 10E – Waterline Design – Issued for Construction Documents
15 Days Following Task 10D
Summary of Fees:
Fix Labor Costs Task Reimbursable
$18,785.52 $0.00
$15,246.84 $0.00
$19,590.72 $0.00 $39,362.08 $0.00 $67,128.08 $5,478.00 $52,198.92 $0.00 $14,134.20 $0.00
$3,826.48 $0.00 $230,272.84 $0.00
$5,478.00 $235,750.84
Total Reimbursables, Not to Exceed Budget Total Budget (Labor and Expenses)
Subtask 9A – West Culvert Design Revisions - Waterline Phasing
Task
Task 8 – Traffic Control Revisions - 2 Construction Contracts
Subtask 9B – East Culvert Design Revisions - Waterline Phasing
Subtask 10E– Waterline Design - Issued for Construction Documents
Subtask 10A – Waterline Design - Preliminary Design Subtask 10B – Waterline Design - 60% Phase Subtask 10C – Waterline Design - 90% Phase Subtask 10D– Waterline Design - Final Plan Submission
Total Fixed Price Cost
Page | 11
Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified. The agreement is a Lump Sum Agreement plus reimbursable expenses.
All expense costs are estimated. Expenses will be reimbursed at actual costs with receipts, except for the daily meals/subsistence costs specified as a daily rate noted above. The subsistence will be paid for all full days of travel and field work in accordance with FDEP and Florida travel regulations and prorated accordingly for partial travel days. Expenses will be submitted utilizing the FDEP Travel Voucher form.