CN-370000-CN645-T1CO7.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN645|36a776d29a3c87ca61eb0e52c637185a
Contract number
CN645
Issued by
Florida

About this file

This document is a Task Assignment Change Order Form from the Florida Department of Environmental Protection (FDEP) for the William J "Billy Joe" Rish Recreation Area Park Redevelopment project. The contract involves CPH, LLC. as the consultant, with Jason Toole, P.E. as the consultant representative, and Vu Nguyen as the FDEP Contract Manager. The change order is numbered CO7 and is associated with the contract CN645 and Task Assignment TA01.

The change order extends the project timeline by 563 days, moving the new task end date to 10/31/2027. It replaces the current subtask CN645 TA01 CO3 Subtask 22 to clearly identify subtasks and deliverables for accurate and timely submittal and invoicing. The scope includes multiple site meetings, civil and building inspections, construction administration services, and submittal reviews. The total fixed price cost for these services is $78,280.32, with no additional reimbursable costs. The services are broken down into 26 subtasks covering site visits, substantial inspections, field observations, and administrative support for the park redevelopment project.

View the file

Other files

File Type Posted
CN-370000-GC167.pdf PDF
CN-370000-CN645-T1CO3.pdf PDF
CN-370000-CN645-T1CO6.pdf PDF
CN-370000-CN645.pdf PDF
CN-370000-CN645-CMC1.pdf PDF
CN-370000-CN645-T1.pdf PDF
CN-370000-CN645-T1CO2.pdf PDF
CN-370000-CN645-T1CO4.pdf PDF
CN-370000-CN645-T1CO1.pdf PDF
CN-370000-CN645-T1CO5.pdf PDF
CN-370000-CN645.pdf.crdownload CRDOWNLOAD file
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN645 01 7 61437C

Park Redevelopment

CPH

Jason Toole, PE (850) 563-1490 jtoole@cphcorp.com

Vu Nguyen or successor (850) 245-2460 Vu.Nguyen@FloridaDEP.gov

This change order replaces current subtask CN645 TA01 CO3 Subtask 22 (exhibit attached) to clearly identify subtasks and deliverables to allow for accurate and timely deliverable submittal and invoicing; time extension for 563 days, per the attached proposal and time extension request dated July 3, 2025.

$ 28,844.76 $ 28,844.76 $ 9,100.00 $ 808,734.58 $ 817,834.58

$ 0.00 $ 9,100.00 $ 808,734.58 $ 817,834.58

12/13/2022

02/25/2024

04/16/2026

10/31/2027

Tamika Bass

Terry McCullum Jr. 07/22/2025

Vu Nguyen

Jason Toole, P.E.

Bryan Bradner

$ 0.00

July 3, 2025

Mr. Terry McCullum Pre-Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: William J Rish Park � RFSOQ BDC01-22/23 Change Order 7

Dear Terry:

For your review, CPH, LLC., has provided a proposal summary and man-hour documentation below. This proposal would replace the current approved Task 22. The purpose is to break out each of the proposed site visits so that they can be used as needed in order to match how construction is currently being handled. Since construction is being completed in phases, it is possible that an increased number of inspections and submittal reviews will be required. If inspections and/or submittal reviews are needed beyond the number included, then an amendment will be required.

Please review the attached Proposal Summary and deliverables.

Sincerely, Jason Toole, P.E.

CPH, LLC.

1031-C W. 23rd Street Panama City, FL 32405

Phone: 850.563.1490 Fax: 850.563.1495

William J. Rish Park Site and Campground Improvements

CN645 TA #01

TASK 22: CONSTRUCTION ADMINISTRATION SERVICES

Description: CPH will provide construction administration support services during the project construction. This scope of work is broken down to a set number of visits, RFIs and submittal reviews. In the event that additional visits, RFI responses, or Submittal reviews are required, there will be cause for an additional service.

Description:

Subtask 22.1 � Civil Site Meeting #1 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.2 � Civil Site Meeting #2 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.3 � Civil Site Meeting #3 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.4 � Civil Site Meeting #4 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.5 � Civil Site Meeting #5 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.6 � Civil Site Meeting #6 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.7 � Civil Site Meeting #7 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.8 � Civil Site Meeting #8 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.9 � Civil Site Meeting #9 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.10 � Civil Site Meeting #10 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.11 � Civil Site Meeting #11 � CPH will perform a Site Visit to meet onsite with FDEP BDC staff and/or Contractor to inspect construction activities.

Subtask 22.12 � Civil Site Substantial Inspection #1 � CPH will perform a Site Visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.13 � Civil Site Substantial Inspection #2 � CPH will perform a Site Visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.14 � Civil Site Substantial Inspection #3 � CPH will perform a Site Visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.15 � Civil Site Substantial Inspection #4 � CPH will perform a Site Visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.16 - Construction Administration Services � Submittal and RFI Reviews. CPH will provide construction administration support to include up to 20 RFI�s and up to 15 Submittals and/or Shop Drawing Reviews.

Subtask 22.17 - Building � Field Observation #1 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.18 - Building � Field Observation #2 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.19 - Building � Field Observation #3 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.20 - Building � Field Observation #4 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.21 - Building � Field Observation #5 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.22 - Building � Field Observation #6 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.23 - Building � Field Observation #7 - CPH will complete a Site visit to review construction progress. This visit will be coordinated with the Contractor and the Owner based upon project needs and will be conducted by Architectural, MEP or Structural staff as required.

Subtask 22.24 - Building � Substantial Inspection #1 - CPH will perform a site visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.25 - Building � Substantial Inspection #2 - CPH will perform a site visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Subtask 22.26 - Building � Substantial Inspection #3 - CPH will perform a site visit to complete a Substantial Inspection of the completed improvements. A punchlist will be provided based on the findings of the inspection.

Deliverable:

22.1 � Provide digital copy (PDF) of Site Inspection Report.

22.2 � Provide digital copy (PDF) of Site Inspection Report.

22.3 � Provide digital copy (PDF) of Site Inspection Report.

22.4 � Provide digital copy (PDF) of Site Inspection Report.

22.5 � Provide digital copy (PDF) of Site Inspection Report.

22.6 � Provide digital copy (PDF) of Site Inspection Report.

22.7 � Provide digital copy (PDF) of Site Inspection Report.

22.8 � Provide digital copy (PDF) of Site Inspection Report.

22.9 � Provide digital copy (PDF) of Site Inspection Report.

22.10 � Provide digital copy (PDF) of Site Inspection Report.

22.11 � Provide digital copy (PDF) of Site Inspection Report.

22.12 � Provide digital copy (PDF) of Site Punchlist and Substantial Inspection Report.

22.13 � Provide digital copy (PDF) of Site Punchlist and Substantial Inspection Report.

22.14 � Provide digital copy (PDF) of Site Punchlist and Substantial Inspection Report.

22.15 � Provide digital copy (PDF) of Site Punchlist and Substantial Inspection Report.

22.16 - Provide digital copies (PDF/emails) of shop drawing reviews, RFI responses, bidding correspondence, and site inspection reports as performed as part of the Construction Administration Services task.

22.17 - Provide digital copy (PDF) of building inspection report.

22.18 - Provide digital copy (PDF) of building inspection report.

22.19 - Provide digital copy (PDF) of building inspection report.

22.20 - Provide digital copy (PDF) of building inspection report.

22.21 - Provide digital copy (PDF) of building inspection report.

22.22 - Provide digital copy (PDF) of building inspection report.

22.23 - Provide digital copy (PDF) of building inspection report.

22.24 - Provide digital copy (PDF) of Building Punchlist and Substantial Inspection Report.

22.25 - Provide digital copy (PDF) of Building Punchlist and Substantial Inspection Report.

22.26 - Provide digital copy (PDF) of Building Punchlist and Substantial Inspection Report.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 22.1 � Civil Site Meeting #1 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.1 $1,229.61

Subtask 22.2 � Civil Site Meeting #2 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.2 $1,229.61

Subtask 22.3 � Civil Site Meeting #3 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32

CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.3 $1,229.61

Subtask 22.4 � Civil Site Meeting #4 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.4 $1,229.61

Subtask 22.5 � Civil Site Meeting #5 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.5 $1,229.61

Subtask 22.6 � Civil Site Meeting #6 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.6 $1,229.61

Subtask 22.7 � Civil Site Meeting #7 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.7 $1,229.61

Subtask 22.8 � Civil Site Meeting #8

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.8 $1,229.61

Subtask 22.9 � Civil Site Meeting #9 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.9 $1,229.61

Subtask 22.10 � Civil Site Meeting #10 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.10 $1,229.61

Subtask 22.11 � Civil Site Meeting #11 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 2 $322.32 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.11 $1,229.61

Subtask 22.12 � Civil Site Substantial Inspection #1 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 5 $805.80 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 1.75 $143.90

CPH, LLC. Administrative $73.14 4.5 $329.13

TOTAL TASK 22.12 $1,793.15

Subtask 22.13 � Civil Site Substantial Inspection #2 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 5 $805.80 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 1.75 $143.90 CPH, LLC. Administrative $73.14 4.5 $329.13

TOTAL TASK 22.13 $1,793.15

Subtask 22.14 � Civil Site Substantial Inspection #3 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 5 $805.80 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 1.75 $143.90 CPH, LLC. Administrative $73.14 4.5 $329.13

TOTAL TASK 22.14 $1,793.15

Subtask 22.15 � Civil Site Substantial Inspection #4 Firm Name Position Classification Hourly

Rate Hours Total Fixed Price

Cost CPH, LLC. Senior Project Manager $161.16 5 $805.80 CPH, LLC. Project Manager $128.58 4 $514.32 CPH, LLC. Senior Design Technician $82.23 1.75 $143.90 CPH, LLC. Administrative $73.14 4.5 $329.13

TOTAL TASK 22.15 $1,793.15

Subtask 22.16 � Construction Administration Services � Submittal and RFI Reviews

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 12 $2,484.72 CPH, LLC. Senior Architect $140.31 60 $8,418.60 CPH, LLC. Senior Architectural Designer $88.53 60 $5,311.80 CPH, LLC. Administrative $73.14 60 $4,388.40 CPH, LLC. Senior Structural Engineer $120.00 24 $2,880.00 CPH, LLC. Senior Design Technician $82.23 24 $1,973.52 CPH, LLC. Principal MEP Engineer $199.68 24 $4,792.32 CPH, LLC. Senior Design Tech (MEP) $82.23 24 $1,973.52

TOTAL TASK 22.16 $32,222.89

Subtask 22.17 � Building Field Observation #1

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.17 $1,950.39

Subtask 22.18 � Building Field Observation #2

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.18 $1,950.39

Subtask 22.19 � Building Field Observation #3

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.19 $1,950.39

Subtask 22.20 � Building Field Observation #4

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.20 $1,950.39

Subtask 22.21 � Building Field Observation #5

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.21 $1,950.39

Subtask 22.22 � Building Field Observation #6

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.22 $1,950.39

Subtask 22.23 � Building Field Observation #7

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 6 $1,242.36 CPH, LLC. Senior Structural Engineer $120.00 1.5 $180.00 CPH, LLC. Senior Design Technician $82.23 1 $82.23 CPH, LLC. Principal MEP Engineer $199.68 1.5 $299.52 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.23 $1,950.39

Subtask 22.24 � Building Substantial Inspection #1

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Structural Engineer $120.00 4.5 $540.00 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Principal MEP Engineer $199.68 4.5 $898.56 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.24 $3,902.13

Subtask 22.25 � Building Substantial Inspection #2

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Structural Engineer $120.00 4.5 $540.00 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Principal MEP Engineer $199.68 4.5 $898.56 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.25 $3,902.13

Subtask 22.26 � Building Substantial Inspection #3

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Structural Engineer $120.00 4.5 $540.00 CPH, LLC. Senior Design Technician $82.23 3 $246.69 CPH, LLC. Principal MEP Engineer $199.68 4.5 $898.56 CPH, LLC. Administrative $73.14 2 $146.28

TOTAL TASK 22.26 $3,902.13

Total Task 22: $78,280.32

Schedule:

No proposed changes to the Project Schedule.

Summary of Fees:

Subtask Subtask Fixed Price Cost Reimbursable Subtask 22.1 � Civil Site Meeting #1 $1,229.61

Subtask 22.2 � Civil Site Meeting #2 $1,229.61

Subtask 22.3 � Civil Site Meeting #3 $1,229.61

Subtask 22.4 � Civil Site Meeting #4 $1,229.61

Subtask 22.5 � Civil Site Meeting #5 $1,229.61

Subtask 22.6 � Civil Site Meeting #6 $1,229.61

Subtask 22.7 � Civil Site Meeting #7 $1,229.61

Subtask 22.8 � Civil Site Meeting #8 $1,229.61

Subtask 22.9 � Civil Site Meeting #9 $1,229.61

Subtask 22.10 � Civil Site Meeting #10 $1,229.61

Subtask 22.11 � Civil Site Meeting #11 $1,229.61

Subtask 22.12 � Civil Site Substantial Inspection #1

$1,793.15

Subtask 22.13 � Civil Site Substantial Inspection #2

$1,793.15

Subtask 22.14 � Civil Site Substantial Inspection #3

$1,793.15

Subtask 22.15 � Civil Site Substantial Inspection #4

$1,793.15

Subtask 22.16 � Construction Administration Services � Submittal and RFI Reviews

$32,222.89

Subtask 22.17 � Building Field Observation #1

$1,950.39

Subtask 22.18 � Building Field Observation #2

$1,950.39

Subtask 22.19 � Building Field Observation #3

$1,950.39

Subtask 22.20 � Building Field Observation #4

$1,950.39

Subtask 22.21 � Building Field Observation #5

$1,950.39

Subtask 22.22 � Building Field Observation #6

$1,950.39

Subtask 22.23 � Building Field Observation #7

$1,950.39

Subtask 22.24 � Building Substantial Inspection #1

$3,902.13

Subtask 22.25 � Building Substantial Inspection #2

$3,902.13

Subtask 22.26 � Building Substantial Inspection #3

$3,902.13

Total Fixed Price Cost: $78,280.32

Total Reimbursable Cost: $0.00

Overall Total Cost: $78,280.32

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

McCullum, Terry

From: Jason L. Toole (P.E.) <jtoole@cphcorp.com> Sent: Thursday, July 3, 2025 10:42 AM To: McCullum, Terry Cc: Jason L. Toole (P.E.)

Subject: RE: William J Rish - RFSOQ BDC01-22/23 - Time Extension

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Terry, Please accept this email as a request for a time extension for the above project. At this time, we are requesting a 563 day extension which would put the new date as 10/31/2027.

Thanks, Jason Toole, P.E., LEED AP

Senior Market Director jtoole@cphcorp.com o 850.563.1490 c 850.774.9575

BUILDING STRONGER COMMUNITIES TOGETHER

From: Jason L. Toole (P.E.) <jtoole@cphcorp.com> Sent: Thursday, July 3, 2025 9:41 AM To: McCullum, Terry <terry.mccullum@floridadep.gov> Cc: Jason L. Toole (P.E.) <jtoole@cphcorp.com> Subject: William J Rish - RFSOQ BDC01-22/23

Terry, I was able to go ahead and make the adjustment. Figured better to do it now rather than wait until Monday.

Please take a look and let me know if you need anything else.

Thanks, Jason Toole, P.E., LEED AP

Senior Market Director jtoole@cphcorp.com o 850.563.1490 c 850.774.9575

BUILDING STRONGER COMMUNITIES TOGETHER

File details come from the government source that posted it. Updated .