This document is a detailed professional services proposal from CPH, LLC to the Florida Department of Environmental Protection (FDEP) for comprehensive design and environmental services for the William J Rish Recreation Area Redevelopment project in Gulf County, Florida. The proposal involves multiple regulatory agencies including the Northwest Florida Water Management District (NWFWMD) and the U.S. Army Corps of Engineers (ACOE), with CPH serving as the primary consulting firm.
The proposal outlines a comprehensive scope of work spanning 23 distinct subtasks covering civil engineering, architectural design, environmental permitting, geotechnical services, and construction administration for various park infrastructure improvements. These include designing 30 RV campsites, a campground bathhouse, camper cottage renovations, a fixed dock with kayak launch, multiple buildings (staff residence, 3-bay shop, pole barn), and associated site utilities and civil works. The total contract value is $639,828.04, comprised of $630,728.04 in fixed-price services and $9,100 in reimbursable expenses. The project is scheduled to run from September 2023 to April 2025, with design, permitting, and environmental assessment phases preceding a 365-day construction administration period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN645-CMC1.pdf | ||
| CN-370000-CN645-T1.pdf | ||
| CN-370000-CN645-T1CO2.pdf | ||
| CN-370000-CN645-T1CO4.pdf | ||
| CN-370000-CN645-T1CO6.pdf | ||
| CN-370000-CN645.pdf | ||
| CN-370000-CN645-T1CO1.pdf | ||
| CN-370000-CN645-T1CO5.pdf | ||
| CN-370000-CN645.pdf.crdownload | CRDOWNLOAD file | |
| CN-370000-CN645-T1CO7.pdf | ||
| CN-370000-GC167.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN645 01 03 61437C
William J Rish Recreation Area Rish Park Redevelopment
CPH, Inc.
Jason Toole, PE (850) 563-1490 jtoole@cphcorp.com
Ralph Perkins (850) 245-2640 Ralph.Perkins@FloridaDEP.gov
Professional services for the remaining park improvements including geotech, environmental, architectural, mechanical, electrical, plumbing, and construction administration per the attached proposal dated 8/7/2023.
$ 28,844.76 $ 28,844.76 $ 159,709.60 $ 159,709.60
$ 9,100.00 $ 630,728.04 $ 639,828.04 $ 9,100.00 $ 790,437.64 $ 799,537.64
12/13/2022
2/25/2024
2/25/2024
4/16/2025
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.08.18 16:12:55 -04'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.08.18 16:14:58 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.08.18 16:18:50 -04'00'
Jason Toole, PE
Mara Gambineri
61437C 37501017177 087157/23 423001 U3100 134000 QZ $ 639,828.04
$ 639,828.04
Digitally signed by Jason L Toole DN: C=US, O=Florida, dnQualifier=A01410C0000017E5468FDBE00018735, CN=Jason L Toole Reason: I am the author of this document Location: Florida Date: 2023.08.21 12:52:06-05'00' Foxit PhantomPDF Version: 10.1.0
Jason L Toole
Mara Gambineri Digitally signed by Mara Gambineri Date: 2023.10.03 15:57:45 -04'00'
August 7, 2023
Ms. Theresa Carron, Pre-Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3800 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: William J Rish Park – RFSOQ BDC01-22/23, CN645 Task Assignment 01 Change Order 03
Dear Theresa:
For your review, CPH, LLC., has provided a proposal summary and man-hour documentation for the services tasks identified below:
TASK DESCRIPTION FEE
9 CIVIL AND ELECTRICAL DESIGN FOR 30 RV CAMPSITES $74,968.32
10 CAMPGROUND BATHHOUSE BUILDING $44,195.91
11 BOARDWALK ADA SURVEY, IMPROVEMENTS AND REPAIRS $ 9,345.06
12 CAMPER COTTAGE RENOVATION / REMODELS $101,478.18
13 FIXED DOCK WITH ADA KAYAK LAUNCH $32,162.88
14 BEACHSIDE DAY USE RESTROOM BUILDING $45,471.15
15 BAY SHOP BUILDING $36,113.37
16 STAFF RESIDENCE BUILDING $45,477.57
17 POLE BARN $12,291.00
18 CIVIL SITE AND UTILITY DESIGN FOR STAFF RESIDENCE, 2 BAY SHOP
BUILDING AND POLE BARN
$14,849.16
19 CIVIL SITE DESIGN FOR DAY USE PARKING LOT $25,510.80
20 PERMITTING $18,388.98
21 GEOTECHNICAL SERVICES $28,348.83
22 CONSTRUCTION ADMINISTRATION SERVICES $78,280.32
23 ENVIRONMENTAL / ECOLOGICAL SERVICES $63,846.51
TOTAL FIXED FEE $630,728.04
Please review the attached Proposal Summary and deliverables.
Sincerely, Jason Toole, P.E.
CPH, LLC.
1031-C W. 23rd Street Panama City, FL 32405
Phone: 850.563.1490 Fax: 850.563.1495
William J. Rish Park Site and Campground Improvements
CN645 TA01 CO3
TASK 9: CIVIL AND ELECTRICAL DESIGN FOR 30 RV CAMPSITES
Description: CPH will design and prepare construction plans for the addition of thirty (30) Recreational Vehicle (RV) Campsites. The Design will include grading of the Campsite pad area, design of water and sewer services to each Campsite, design of a sewer liftstation to accommodate the flow from the sites.
CPH will also coordinate with in house MEP for an electrical design to service the campsites. The panel will be sized to accommodate 30 (50A) RV Campsites and will need to be sited somewhat central to the final RV Park. The panel will be approximately an 800 Amp service panel.
Description: SUBTASK 9A
Subtask 9A.1 – CPH will prepare 30% civil design and construction plans for the addition of 30 RV Campsites.
Subtask 9A.2 – CPH will prepare 30% Electrical design and construction plans for servicing the proposed 30 RV Campsites.
Deliverable: SUBTASK 9A
Subtask 9A.1 – PDF copy of 30% Civil design plans.
Subtask 9A.2 – PDF copy of 30% Electrical plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 9A.1 – Civil Design Plans for 30 RV Campsites Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 6 $966.96 CPH, LLC. Project Manager $128.58 60 $7,714.80 CPH, LLC. Senior Design Technician $82.23 60 $4,933.80 CPH, LLC. Administrative $73.14 8 $585.12 Subtask 9A.2 – Electrical Design Plans for 30 RV Campsites Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 CPH, LLC. Senior Design Tech – MEP $82.23 32 $2,631.36
TOTAL SUBTASK 9A $19,228.20
Description: SUBTASK 9B
Subtask 9B.1 –CPH will prepare 60% Civil design and construction plans for the addition of 30 RV Campsites. Plans will include Cover Sheet, General Notes, SWPPP E&S Control Plans, Grading, Paving, and Drainage Plans, BDC Campsite Details, General Details, Drainage Details, Pavement/Marking Details, and Liftstation Plans.
Subtask 9B.2 – CPH will prepare 60% Electrical design and construction plans for servicing the proposed 30 RV Campsites.
Subtask 9B.3 – CPH will prepare an opinion of probable cost for the scope of this task.
Deliverable: SUBTASK 1B
Subtask 9B.1– PDF copy of 60% design plans Subtask 9B.2– PDF copy of 60% electrical plans.
Subtask 9B.3 – PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 9B.1 – Civil Design Plans for 30 RV Campsites Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 40 $6,446.40 CPH, LLC. Project Manager $128.58 60 $7,714.80 CPH, LLC. Senior Design Technician $82.23 120 $9,867.60 CPH, LLC. Project Engineer $90.90 60 $5,454.00 CPH, LLC. Administrative $73.14 8 $585.12 Subtask 9B.2 – Electrical Design Plans for 30 RV Campsites Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 CPH, LLC. Senior Design Tech – MEP $82.23 32 $2,631.36 Subtask 9B.3 – Opinion of Probable cost for 30 RV Campsites Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Project Manager $128.58 12 $1,542.96 CPH, LLC. Senior Design Technician $82.23 12 $986.76
TOTAL SUBTASK 9B $37,625.16
Description: SUBTASK 9C
Subtask 9C.1 – CPH will prepare 100% Civil design and construction plans for the addition of 30 RV Campsites. Design will include grading of the Campsite pad area, ADA connection of sites to the existing boardwalks, design of water and sewer services to each Campsite, and design of a sewer lift station to accommodate the flow from the sites. CPH will also coordinate with inhouse MEP for an electrical design to service the campsites. A final cost estimate will be prepared upon completion of the final plans.
Subtask 9C.2 – CPH will prepare 100% Electrical design for servicing the 30 RV Campsites. Panel will need to be sited somewhat central to the final RV Park. The panel will be approximately an 800 Amp service panel. Electric service to 30 Campsites and Sanitary Lift station will be provided as part of this design.
Subtask 9C.3 – CPH will prepare an updated opinion of probable cost for the scope of this task.
Deliverable: SUBTASK 9C
Subtask 9C.1 – PDF copy of 100% design plans and a copy of Final OPC.
Subtask 9C.2 – PDF copy of 100% electrical plans.
Subtask 9C.3 – PDF copy of updated Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 9C.1 – Civil Design Plans for 30 RV Campsites – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 10 $1,611.60 CPH, LLC. Project Manager $128.58 20 $2,571.60 CPH, LLC. Senior Design Technician $82.23 40 $3,289.20 CPH, LLC. Project Engineer $90.90 40 $3,636.00 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 9C.2 – Electrical Design Plans for 30 RV Campsites – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 CPH, LLC. Senior Design Tech – MEP $82.23 32 $2,631.36 Subtask 9C.3 – Opinion of Probable cost for 30 RV Campsites – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Project Manager $128.58 8 $1,028.64 CPH, LLC. Senior Design Technician $82.23 8 $657.84
TOTAL SUBTASK 9C $18,114.96
TOTAL TASK 9 $74,968.32
Task 10: CAMPGROUND BATHHOUSE BUILDING
Description: CPH will prepare design and construction documents for a new approximately 1,250 SF campground bathhouse building to be located at the new 30 RV Campsite. The basis of design for the bathhouse will be the concept that was developed as part of the concept design phase modified per the FDEP comments. The bathhouse will have eight (8) single-user restrooms with showers and adult changing tables. Interior pipe chases will be provided for maintenance and service access and space will provided for laundry equipment and vending. Fixtures will also include a water bottle filler/fountain.
The building will be designed to provide an overhanging roof for weather protection. CPH will provide architectural, structural, mechanical, plumbing and electrical design and documentation for this scope of work.
Description: SUBTASK 10A
Subtask 10A.1 – CPH will prepare 30% architectural design and construction plans for the campground bathhouse building.
Deliverable: SUBTASK 10A
Subtask 10A.1 – PDF copy of 30% architectural design plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 10A.1 – Architectural Design for Campground Bathhouse Building – 30% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 20 $2,806.20 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56
TOTAL SUBTASK 10A $5,697.60
Description: SUBTASK 10B
Subtask 10B.1 – CPH will prepare 60% architectural design and construction plans for the campground bathhouse building.
Subtask 10B.2 – CPH will prepare a written design narrative description of the MEP systems and fixtures for the campground bathhouse building.
Subtask 10B.3 – CPH will prepare a written design narrative description of the Structural systems and design loads for the campground bathhouse building.
Subtask 10B.4 – CPH will prepare an opinion of probable cost for the campground bathhouse building.
Deliverable:
Subtask 10B.1 – PDF copy of 60% architectural design plans.
Subtask 10B.2 – PDF copy of MEP narrative Subtask 10B.3 – PDF copy of the structural narrative Subtask 10B.4 – PDF copy of Opinion of Probable Cost.
accurate, and timely.
Fixed Price Cost:
Subtask 10B.1 – Architectural Design for Campground Bathhouse Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 20 $2,806.20 CPH, LLC. Senior Architectural Designer $88.53 40 $3,541.20 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 10B.2 – MEP Design Narrative for Campground Bathhouse Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 Subtask 10B.3 – Structural Design Narrative for Campground Bathhouse Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 2 $424.98 Subtask 10B.4 – Opinion of Probable Cost for campground bathhouse building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC Senior Architectural Designer $88.53 8 $708.24 CPH, LLC Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 8 $1,699.92
TOTAL SUBTASK 10B $14,749.38
Description: SUBTASK 10C
Subtask 10C.1 – CPH will prepare 100% architectural design and construction plans for the campground bathhouse building.
Subtask 10C.2 – CPH will prepare 100% MEP design and construction plans for the campground bathhouse building.
Subtask 10C.3 – CPH will prepare 100% Structural design and construction plans for the campground bathhouse building.
Subtask 2C.4 – CPH will prepare an updated opinion of probable cost for the campground bathhouse building.
Deliverable:
Subtask 10C.1 – PDF copy of 100% architectural design plans.
Subtask 10C.2 – PDF copy of 100% MEP design plans.
Subtask 10C.3 – PDF copy of 100% structural design plans.
Subtask 10C.4 – PDF copy of Opinion of Probable Cost.
accurate, and timely.
Fixed Price Cost:
Subtask 10C.1 – Architectural Design for Campground Bathhouse Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 20 $2,806.20 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 10C.2 – MEP Design for Campground Bathhouse Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 24 $4,792.32 CPH, LLC. Senior Design Tech – MEP $82.23 80 $6,578.40 Subtask 10C.3 – Structural Design for Campground Bathhouse Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 5 $1,062.45 CPH, LLC. Structural Engineer $86.55 8 $692.40 CPH, LLC. Senior Design Tech – Structural $82.23 16 $1,315.68 Subtask 10C.4 – Opinion of Probable Cost for campground bathhouse building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC Senior Architectural Designer $88.53 8 $708.24 CPH, LLC Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 4 $849.96 CPH, LLC. Administrative $73.14
TOTAL SUBTASK 10C $23,748.93
TOTAL TASK 10 $44,195.91
TASK 11: BOARDWALK ADA SURVEY, IMPROVEMENTS AND REPAIRS
Description:
CPH will conduct a site visit / visual survey to identify the locations and extents of railings requiring replacement of the top plate. This survey will include all existing handrails within the park with the exception of the recently designed sensory trail boardwalk and the newly constructed boardwalk to the beach. CPH will prepare design plans to indicated the extent of repairs and develop a standard detail for the replacement of the top plate on existing railings and note linear footage of replacement required.
CPH will prepare design plans for sidewalk repair and the addition of a retaining wall on the North side of the walkway as it comes under the tunnel. Grading will be adjusted as needed to prevent sediment from over-topping the wall onto the sidewalk area.
Deliverable:
PDF copy of Final design plans and Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Task 11 – Boardwalk ADA Survey, Improvements and Repairs
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC. Sr. Project Manager $161.16 18 $2,900.88 CPH, LLC. Project Manager $128.58 16 $2,057.28 CPH, LLC. Senior Design Technician $82.23 30 $2,466.90 CPH, LLC. Senior Structural Engineer $120.00 16 $1,920.00
TOTAL TASK 11 $9,345.06
TASK 12: CAMPER COTTAGE RENOVATION / REMODELS
Description:
CPH will prepare final design and construction drawings for the renovation & remodel of the existing six (6) Camper Cottages CC-1, CC-2, CC-3, CC-4, CC-5 & CC-6 to update them and convert them to Family Cabins. The Basis of Design for the renovation/remodel will be the Concept 2A as submitted with the concept design phase and approved with comments in the Memorandum dated April 10, 2023. CPH will provide Architectural, Structural, Mechanical, Plumbing and Electrical design for this scope of work. It is anticipated that the existing structural foundation system and piles will require some level of repair or remediation which will be included in the design. In order to establish the existing conditions for use in developing the As-Built documents and to determine the scope of work for each cottage CPH will conduct an existing conditions survey.
Description: Subtask 12A – Existing Conditions Survey and Assessment
CPH will conduct an existing conditions survey. The survey will include an assessment of the existing architectural, structural, mechanical, electrical and plumbing systems. This scope anticipates one trip for three (3) persons from CPH.
Deliverable:
Copies of Field Notes, Photos and markup of existing plans will be provided.
Performance Measure: Completion of the on-site survey by CPH staff.
Fixed Price Cost:
Subtask 12A – Existing Conditions Survey and Assessment Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 12 $1,683.72 CPH, LLC. Structural Engineer $86.55 20 $1,731.00 CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16
TOTAL SUBTASK 12A $5,810.88
Description: SUBTASK 12B
Subtask 12B.1 – CPH will prepare 30% architectural design and construction plans for the Camper Cottages.
Deliverable: SUBTASK 12B
Subtask 12B.1 – PDF copy of 30% architectural design plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12B.1 – Architectural Design for Camper Cottage Renovation & Remodel – 30% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Architect $140.31 20 $2,806.20 CPH, LLC. Architect $126.00 40 $5,040.00 CPH, LLC. Senior Architectural Designer $88.53 50 $4,426.50
CPH, LLC Administrative $73.14 8 $585.12
TOTAL SUBTASK 12B $14,928.42
Description: SUBTASK 12C
Subtask 12C.1 – CPH will prepare 60% architectural design and construction plans for the Camper Cottage Renovation & Remodel - 60%.
Subtask 12C.2 – CPH will prepare a written design narrative description of the MEP systems and fixtures for the Camper Cottage Renovation & Remodel - 60%.
Subtask 12C.3 – CPH will prepare a written design narrative description of the Structural systems and design loads for the Camper Cottage Renovation & Remodel - 60%.
Subtask 12C.4 – CPH will prepare an opinion of probable cost for the Camper Cottage Renovation & Remodel - 60%.
Deliverable:
Subtask 12C.1 – PDF copy of 60% architectural design plans.
Subtask 12C.2 – PDF copy of MEP narrative Subtask 12C.3 – PDF copy of the structural narrative Subtask 12C.4 – PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12C.1 – Architectural Design for Camper Cottage Renovation & Remodel - 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Architect $140.31 24 $3,367.44 CPH, LLC. Architect $126.00 80 $10,080.00 CPH, LLC. Senior Architectural Designer $88.53 80 $7,082.40 CPH, LLC Administrative $73.14 8 $585.12 Subtask 12C.2 – MEP Design Narrative for Camper Cottage Renovation & Remodel - 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 Subtask 12C.3 – Structural Design Narrative for Camper Cottage Renovation & Remodel - 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 2 $424.98 Subtask 12C.4 – Opinion of Probable Cost for Camper Cottage Renovation & Remodel Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 8 $1,122.48 CPH, LLC Senior Architectural Designer $88.53 8 $708.24 CPH, LLC Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 8 $1,699.92
TOTAL SUBTASK 12C $31,027.98
Subtask 12D.1 – CPH will prepare 100% Architectural design and construction plans for the Camper Cottage Renovation & Remodel
Subtask 12D.2 – CPH will prepare 100% MEP design and construction plans for the Camper Cottage Renovation & Remodel
Subtask 12D.3 – CPH will prepare 100% Structural design and construction plans for the Camper Cottage Renovation & Remodel
Subtask 12D.4 – CPH will prepare an updated opinion of probable cost for the Camper Cottage Renovation & Remodel
Deliverable:
Subtask 12D.1 – PDF copy of 100% architectural design plans.
Subtask 12D.2 – PDF copy of 100% MEP design plans.
Subtask 12D.3 – PDF copy of 100% structural design plans.
Subtask 12D.4 – PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 12D.1 – Architectural Design for Camper Cottage Renovation & Remodel - 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 10 $2,070.60 CPH, LLC. Senior Architect $140.31 24 $3,367.44 CPH, LLC. Architect $126.00 60 $7,560.00 CPH, LLC. Senior Architectural Designer $88.53 80 $7,082.40 CPH, LLC Administrative $73.14 8 $585.12 Subtask 12D.2 – MEP Design for Camper Cottage Renovation & Remodel - 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 24 $4,792.32 CPH, LLC. Senior Design Tech – MEP $82.23 80 $6,578.40 Subtask 12D.3 – Structural Design for Camper Cottage Renovation & Remodel - 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 10 $2,124.90 CPH, LLC. Senior Structural Engineer $120.00 40 $4,800.00 CPH, LLC. Senior Design Tech – Structural $82.23 80 $6,578.40 Subtask 12D.4 – Opinion of Probable Cost for Camper Cottage Renovation & Remodel Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 8 $1,122.48
CPH, LLC Senior Architectural Designer $88.53 8 $708.24 CPH, LLC Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 4 $849.96 CPH, LLC. Administrative $73.14
TOTAL SUBTASK 12D $49,710.90
TOTAL TASK 12 $101,478.18
TASK 13: FIXED DOCK WITH BOAT LANDING & ADA FLOATING KAYAK LAUNCH
Description:
CPH will design and prepare construction documents for an ADA accessible permanent fixed dock approximately 500 feet in length on the bay side of Rish Park. The dock will long enough to allow for boats from St. Peninsula Park to tie up and ferry guests. The structural design will utilize the recommendations of the Geotechnical Engineer – included in task 13 of this proposal. Additionally, CPH will include in the design and documentation of a floating ADA accessible kayak launch to be located adjacent the dock in shallow water.
Deliverable:
Task 13 PDF copy of 100% Civil design plans.
Task 13 PDF copy of 100% structural design plans.
Task 13 PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
TASK 13 – Fixed Dock with Boat Landing & ADA floating Kayak Launch Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 10 $1,611.60 CPH, LLC. Project Manager $128.58 24 $3,085.92 CPH, LLC. Senior Design Technician $82.23 40 $3,289.20 CPH, LLC. Project Engineer $90.90 40 $3,636.00 CPH, LLC. Principal Structural Engineer $212.49 10 $2,124.90 CPH, LLC. Senior Structural Engineer $120.00 55 $6,600.00 CPH, LLC. Senior Design Tech – Structural $82.23 80 $6,578.40 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC Senior Architectural Designer $88.53 40 $3,541.20 CPH, LLC. Administrative $73.14 4 $292.56
TOTAL TASK 13 $32,162.88
TASK 14: BEACHSIDE DAY USE RESTROOM BUILDING
Description:
CPH will provide design and documentation for an approximately 1,200 SF Beachside Day Use Restroom building. The program will include eight (8) ADA compliant single user restrooms with adult changing tables. Pipe chases shall be provided to support the maintenance of the plumbing fixtures and exterior rinse off showers shall be included in the design. There is not a Basis of Design concept plan that meets these program requirements, however, the 4 QUADRANT BATHOUSE – PLAN #08 will serve as a general guide. Due to the location, the bathhouse will be an off-grade structure and will be accessed by the existing boardwalk system. The proposed design will include Cold formed metal stud or wood walls with light gauge or wood roof trusses and standing seam metal roof system. Exterior finish will be painted fiber cement siding and fiber cement board soffits. Exterior doors and coiling doors will be aluminum for corrosion resistance. The structural foundation shall be wood or concrete piles and will be designed in accordance with the recommendation of the geotechnical report. CPH will provide Architectural, Structural, Mechanical, Plumbing and Electrical design for this scope of work.
Description: SUBTASK 14A
Subtask 14A.1 – CPH will prepare 30% architectural design and construction plans for the beachside day-use restroom building.
Deliverable: SUBTASK 14A
Subtask 14A.1 – PDF copy of 30% architectural design plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 14A.1 – Architectural Design for Beachside day-use restroom Building – 30% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56
TOTAL SUBTASK 14A $4,294.50
Description: SUBTASK 14B
Subtask 14B.1 – CPH will prepare 60% architectural design and construction plans for the beachside day-use restroom building.
Subtask 14B.2 – CPH will prepare a written design narrative description of the MEP systems and fixtures for the beachside day-use restroom building.
Subtask 14B.3 – CPH will prepare a written design narrative description of the Structural systems and design loads for the beachside day-use restroom building.
Subtask 14B.4 – CPH will prepare an opinion of probable cost for the beachside day-use restroom building.
Subtask 14B.5 – CPH will prepare a civil utility plan for water, sewer, and electric connection to proposed restroom building.
Deliverable:
Subtask 14B.1 – PDF copy of 60% architectural design plans.
Subtask 14B.2 – PDF copy of MEP narrative Subtask 14B.3 – PDF copy of the structural narrative Subtask 14B.4 – PDF copy of Opinion of Probable Cost.
Subtask 14B.5 – PDF copy of 60% Civil Utility Plan.
Fixed Price Cost:
Subtask 14B.1 – Architectural Design for Beachside day-use restroom building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 40 $3,541.20 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 14B.2 – MEP Design Narrative for Beachside day-use restroom building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 Subtask 14B.3 – Structural Design Narrative for Beachside day-use restroom building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 2 $424.98 Subtask 14B.4 – Opinion of Probable Cost for beachside day-use restroom building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC. Senior Architectural Designer $88.53 8 $708.24 CPH, LLC. Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 8 $1,699.92 Subtask 14B.5 – Civil Utility Plan for water, sewer, and electrical connection to proposed restroom Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Project Manager $161.16 4 $644.64 CPH, LLC. Project Manager $128.58 8 $1,028.64 CPH, LLC. Senior Design Technician $82.23 12 $986.76
TOTAL SUBTASK 14B $16,006.32
Description: SUBTASK 14C
Subtask 14C.1 – CPH will prepare 100% architectural design and construction plans for the beachside day-use restroom building.
Subtask 14C.2 – CPH will prepare 100% MEP design and construction plans for the beachside day-use restroom building.
Subtask 14C.3 – CPH will prepare 100% Structural design and construction plans for the beachside day-use restroom building.
Subtask 14C.4 – CPH will prepare an updated opinion of probable cost for the beachside day-use restroom building.
Subtask 14C.5 – CPH will prepare final civil utility plan for restroom building.
Deliverable:
Subtask 14C.1 – PDF copy of 100% architectural design plans.
Subtask 14C.2 – PDF copy of 100% MEP design plans.
Subtask 14C.3 – PDF copy of 100% structural design plans.
Subtask 14C.4 – PDF copy of Opinion of Probable Cost.
Subtask 14C.5 – PDF copy of 100% Civil Utility Plan.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 14C.1 – Architectural Design for Beachside day-use restroom building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 14C.2 – MEP Design for Beachside day-use restroom building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 24 $4,792.32 CPH, LLC. Senior Design Tech – MEP $82.23 80 $6,578.40 Subtask 14C.3 – Structural Design for Beachside day-use restroom building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 5 $1,062.45 CPH, LLC. Structural Engineer $86.55 8 $692.40 CPH, LLC. Senior Design Tech – Structural $82.23 20 $1,644.60 Subtask 14C.4 – Opinion of Probable Cost for Beachside day-use restroom building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC. Senior Architectural Designer $88.53 8 $708.24
CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08
CPH, LLC. Principal Structural Engineer $212.49 4 $849.96 Subtask 14C.5 – CPH will prepare final civil utility plan for restroom building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Project Manager $161.16 4 $644.64 CPH, LLC. Project Manager $128.58 8 $1,028.64 CPH, LLC. Senior Design Technician $82.23 10 $822.30
TOTAL SUBTASK 14C $25,170.33
TOTAL TASK 14 $45,471.15
TASK 15: 3-BAY SHOP BUILDING
Description:
CPH will provide design and documentation for a 1,792 SF Standard 3-bay shop building. The basis of design shall be in accordance with the 3 BAY SHOP BUILDING - PLAN #25 as provided by the CLIENT and updated to meet all current codes. The proposed design will include Cold formed metal stud or wood walls with light gauge or wood roof trusses and standing seam metal roof system. Exterior finish will be painted fiber cement siding and fiber cement board soffits. Exterior finish will we painted smooth-faced and split faced CMU and fiber cement board soffits. Exterior doors and coiling doors will be aluminum for corrosion resistance. CPH will provide Architectural, Structural, Mechanical, Plumbing and Electrical design for this scope of work. It is anticipated that the structure will be on-grade construction and the foundation will be a typical shallow spread foundation. If geotechnical analysis indicates a specialized foundation for this structure, it will be an additional service.
Description:
Subtask 15.1 – CPH will prepare 100% architectural design and construction plans for the 3 bay shop building.
Subtask 15.2 – CPH will prepare 100% MEP design and construction plans for the 3 bay shop building.
Subtask 15.3 – CPH will prepare 100% Structural design and construction plans for the 3 bay shop building.
Subtask 15.4 – CPH will prepare an updated opinion of probable cost for the 3 bay shop building.
Deliverable:
Subtask 15.1 – PDF copy of 100% architectural design plans.
Subtask 15.2 – PDF copy of 100% MEP design plans.
Subtask 15.3 – PDF copy of 100% structural design plans.
Subtask 15.4 – PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 15.1 – Architectural Design for 3-bay shop building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 20 $2,806.20 CPH, LLC. Senior Architectural Designer $88.53 80 $7,082.40 CPH, LLC. Administrative $73.14 8 $585.12 Subtask 15.2 – MEP Design for 3-bay shop building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 30 $5,990.40 CPH, LLC. Senior Design Tech – MEP $82.23 80 $6,578.40 Subtask 15.3 – Structural Design for 3-bay shop building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost
CPH, LLC. Principal Structural Engineer $212.49 13 $2,762.37 CPH, LLC. Structural Engineer $86.55 20 $1,731.00 CPH, LLC. Senior Design Tech – Structural $82.23 40 $3,289.20 Subtask 15.4 – Opinion of Probable Cost for 3-bay shop building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC. Senior Architectural Designer $88.53 8 $708.24 CPH, LLC. Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08
TOTAL TASK 15 $36,113.37
TASK 16: STAFF RESIDENCE BUILDING
Description:
CPH will provide design and documentation for an approximately 1,600 SF Standard Staff Residence building. The basis of design shall be in accordance with the SITE BUILT RANGER RESIDENCE - PLAN #23 as provided by the CLIENT and updated to meet all current codes. The proposed design will include Cold formed metal stud or wood walls with light gauge or wood roof trusses and standing seam metal roof system. Exterior finish will be painted fiber cement siding and fiber cement board soffits. Exterior finish will we painted smooth-faced and split faced CMU and fiber cement board soffits. Exterior doors and coiling doors will be aluminum for corrosion resistance. CPH will provide Architectural, Structural, Mechanical, Plumbing and Electrical design for this scope of work. It is anticipated that the structure will be off-grade construction and the structural foundation shall be wood or concrete piles and will be designed in accordance with the recommendation of the geotechnical report.
Description: SUBTASK 16A
Subtask 16A.1 – CPH will prepare 30% architectural design and construction plans for the Staff Residence Building.
Deliverable: SUBTASK 16A
Subtask 16A.1 – PDF copy of 30% architectural design plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 16A.1 – Architectural Design for Staff Residence Building – 30% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56
TOTAL SUBTASK 16A $4,294.50
Description: SUBTASK 16B
Subtask 16B.1 – CPH will prepare 60% architectural design and construction plans for the Staff Residence Building.
Subtask 16B.2 – CPH will prepare a written design narrative description of the MEP systems and fixtures for the Staff Residence Building.
Subtask 16B.3 – CPH will prepare a written design narrative description of the Structural systems and design loads for the Staff Residence Building.
Subtask 16B.4 – CPH will prepare an opinion of probable cost for the Staff Residence Building.
Deliverable:
Subtask 16B.1 – PDF copy of 60% architectural design plans.
Subtask 16B.2 – PDF copy of MEP narrative Subtask 16B.3 – PDF copy of the structural narrative
Subtask 16B.4 – PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 16B.1 – Architectural Design for Staff Residence Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 40 $3,541.20 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 16B.2 – MEP Design Narrative for Staff Residence Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 12 $2,396.16 Subtask 16B.3 – Structural Design Narrative for Staff Residence Building – 60% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 2 $424.98 Subtask 16B.4 – Opinion of Probable Cost for Staff Residence Building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC. Senior Architectural Designer $88.53 8 $708.24 CPH, LLC. Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 8 $1,699.92
TOTAL SUBTASK 16B $13,346.28
Description: SUBTASK 16C
Subtask 16C.1 – CPH will prepare 100% architectural design and construction plans for the Staff Residence Building.
Subtask 16C.2 – CPH will prepare 100% MEP design and construction plans for the Staff Residence Building.
Subtask 16C.3 – CPH will prepare 100% Structural design and construction plans for the Staff Residence Building.
Subtask 16C.4 – CPH will prepare an updated opinion of probable cost for the Staff Residence Building.
Deliverable:
Subtask 16C.1 – PDF copy of 100% architectural design plans.
Subtask 16C.2 – PDF copy of 100% MEP design plans.
Subtask 16C.3 – PDF copy of 100% structural design plans.
Subtask 16C.4 – PDF copy of Opinion of Probable Cost.
Subtask 16C.1 – Architectural Design for Staff Residence Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 48 $4,249.44 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 16C.2 – MEP Design for Staff Residence Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal MEP Engineer $199.68 24 $4,792.32 CPH, LLC. Senior Design Tech – MEP $82.23 80 $6,578.40 Subtask 16C.3 – Structural Design for Staff Residence Building – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 5 $1,062.45 CPH, LLC. Structural Engineer $86.55 20 $1,731.00 CPH, LLC. Senior Design Tech – Structural $82.23 40 $3,289.20 Subtask 16C.4 – Opinion of Probable Cost for Staff Residence Building Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 4 $561.24 CPH, LLC. Senior Architectural Designer $88.53 8 $708.24 CPH, LLC. Administrative $73.14 4 $292.56 CPH, LLC. Principal MEP Engineer $199.68 6 $1,198.08 CPH, LLC. Principal Structural Engineer $212.49 4 $849.96
TOTAL SUBTASK 16C $27,836.79
TOTAL TASK 16 $45,477.57
TASK 17: POLE BARN
Description:
CPH will provide design and documentation for an approximately 1,100 SF Standard 3-bay Pole Barn with a fenced maintenance yard. The basis of design shall be in accordance with the POLE BARN - PLAN #27 as provided by the CLIENT. The proposed design will include timber framing with wood roof trusses and standing seam metal roof system. . CPH will provide Architectural and Structural design for this scope of work. It is anticipated that the foundation will be a typical shallow column/post foundation. If geotechnical analysis indicates a specialized foundation for this structure, it will be an additional service.
Description:
Subtask 17.1 – CPH will prepare 100% architectural design and construction plans for the 3 bay pole barn.
Subtask 17.2 – CPH will prepare 100% Structural design and construction plans for the 3 bay pole barn.
Subtask 17.3 – CPH will prepare an updated opinion of probable cost for the 3 bay pole barn.
Deliverable:
Subtask 17.1 – PDF copy of 100% architectural design plans.
Subtask 17.2– PDF copy of 100% structural design plans.
Subtask 17.3– PDF copy of Opinion of Probable Cost.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 17.1 – Architectural Design for 3 bay pole barn – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Architect $207.06 4 $828.24 CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Senior Architectural Designer $88.53 20 $1,770.60 CPH, LLC. Administrative $73.14 4 $292.56 Subtask 17.2– Structural Design for 3 bay pole barn – 100% Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Principal Structural Engineer $212.49 5 $1,062.45 CPH, LLC. Structural Engineer $86.55 15 $1,298.25 CPH, LLC. Senior Design Tech – Structural $82.23 40 $3,289.20 Subtask 17.3– Opinion of Probable Cost for 3 bay pole barn Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architectural Designer $88.53 4 $354.12 CPH, LLC Administrative $73.14 4 $292.56
TOTAL TASK 17 $12,291.00
TASK 18: CIVIL SITE AND UTILITY DESIGN FOR STAFF RESIDENCE, 3 BAY SHOP BUILDING AND POLE
BARN
Description:
CPH will prepare design plans for the Staff Residence, 2 Bay Shop Building, and Pole Barn. Design plans will include Site Plans, Grading Plan, and Utility Plans to serve the 3 structures. CPH will also include the design of a fenced-in Service Yard that will be combined with the Shop and Pole Barn areas. This fee covers two reviews and modifications by FDEP Staff.
Deliverable:
PDF copies of the Site, Grading and Utility Plans will be provided to FDEP for review.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Task 18 – Civil Site and Utility Design for Staff Residence, 2 Bay Shop Building and Pole Barn Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 18 $2,900.88 CPH, LLC. Project Manager $128.58 24 $3,085.92 CPH, LLC. Senior Design Technician $82.23 60 $4,933.80 CPH, LLC. Project Engineer $90.90 40 $3,636.00
TOTAL TASK 18 $14,849.16
TASK 19: CIVIL SITE DESIGN FOR DAY USE PARKING LOT
Description:
CPH will prepare design plans for the Day Use Parking Lot. Design plans will include Erosion Control Plan, Site Plan, Grading Plan, Landscape Plan and Paving and Striping Plan. This fee covers two reviews and modifications by FDEP Staff.
Deliverable:
PDF copies of the Erosion Control, Site, Grading, Landscape and Paving and Striping Plans will be provided to FDEP for review.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
TASK 19 – Civil Site Design For Day Use Parking Lot Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Sr. Project Manager $161.16 24 $3,867.84 CPH, LLC. Project Manager $128.58 32 $4,114.56 CPH, LLC. Senior Design Technician $82.23 80 $6,578.40 CPH, LLC. Project Engineer $90.90 60 $5,454.00 CPH, LLC. Principal Landscape Architect $154.68 16 $2,474.88 CPH, LLC. Landscape Architect $87.00 28 $2,436.00 CPH, LLC. Administrative $73.14 8 $585.12
TOTAL TASK 19 $25,510.80
TASK 20: PERMITTING
Description:
20A –Gulf County Permitting – CPH will coordinate improvements with the County. It is currently assumed that a Site Permit will be required for the connection of Utilities and Site Plan Approval for the RV Host Campsites and Day Use Parking Area. No other County permitting is currently included.
20B – NWFWMD Permitting – 1) Attend one (1) pre-application meeting with NWFWMD. 2) Coordinate, prepare and file a completed NWFWMD Permit package. 3) CPH will prepare responses to all Requests for Additional Information (RAI’s) requested by NWFWMD. It is assumed that use of existing pond between sensory trail and RV campground can be used for stormwater treatment.
20C – Gulf County Building Permitting –Permitting with County and State Fire Marshall. Please note that this fee covers submitting the permit package, however a Licensed Contractor will be required to actually pick up the permits. Included in this fee are the following structures; 6 Cabins, Day Use Restroom, Campground Restroom, Staff Residence, 3 Bay Shop, and Pole Barn.
Deliverable:
20A – PDF copies applications and approvals from the County.
20B – PDF copies of Permit applications and Approval from NWFWMD.
20C – PDF copies of applications and Building Permit Approvals from Gulf County and State Fire
Marshall. Contractor will be required to pull permits and provide permit copies.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 20A – Gulf County – Utility and Site Plan Approval Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Project Manager $161.16 8 $1,289.28 CPH, LLC. Project Manager $128.58 24 $3,085.92 CPH, LLC. Senior Design Technician $82.23 20 $1,644.60 CPH, LLC. Administrative $73.14 8 $585.12 Subtask 20B – NWFWMD – Stormwater Permitting Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Project Manager $161.16 16 $2,578.56 CPH, LLC. Project Manager $128.58 24 $3,085.92 CPH, LLC. Senior Design Technician $82.23 20 $1,644.60 CPH, LLC. Administrative $73.14 12 $877.68 Subtask 20C – Gulf County Building Permitting Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost CPH, LLC. Senior Architect $140.31 10 $1,403.10 CPH, LLC. Administrative $73.14 30 $2,194.20
Reimbursable Cost:
Application Fees $5,000 – Allowance for application fees.
jtoole Strikeout
TOTAL TASK 20 $18,388.98
TASK 21: GEOTECHNICAL SERVICES
Description:
CPH will hire a sub-consultant to perform Geotechical Services in order to provide the following items:
21A:
o Building Structural/Foundation Recommendations for 3 Bay Shop Building, Pole Barn, Staff Residence, Day Use Restroom, and Campground Restroom buildings.
o Pavement and Sitework preparation for RV Campground pads and Campground Road.
o Pavement and Sitework preparation for Day Use Parking Lot o Structural Recommendations for Retaining Wall design.
o Structural Recommendations for the proposed 500’ dock.
21B:
o Report of the existing capacities for the structural timber piles at the 6 Cottages to be renovated.
Deliverable:
21A & 21B Final Geotech Report containing all recommendations noted above.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 21A – Geotechnical Services Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost NOVA Staff Engineer $78.03 44 $3,433.32 NOVA Project Manager $96.32 18 $1733.76 NOVA Project Engineer $96.32 42 $4,045.44 NOVA Senior Project Engineer $141.61 15 $2,124.15 NOVA Administrator $58.00 1.5 $87.00
TOTAL TASK 21A $11,423.67
Subtask 21B – PIT Testing and analysis of cottage timber piles Firm Name Position Classification Hourly
Rate Hours Total Fixed Price
Cost PSI Professional Engineer $134.25 12 1,611.00 PSI Chief Engineer 189.00 4 $756.00 PSI Senior Engineer 158.67 4 $634.68 PSI Professional Engineer $134.25 8 $1074.00 PSI Engineer Intern $77.88 8 $623.04 PSI Draftsperson / CAD $75.00 6 $450.00 PSI Clerical $50.70 2 $101.40 PSI Truck Rig Mobilization $500.00 1 $500.00 PSI SPT Truck – M/B 0-50 ft $14.00 105 lf $1,470.00 PSI Temp Casing 3” $10.00 90 lf $900.00 PSI Grout Boreholes $7.00 105 lf $735.00 PSI Trip Charge $40.00 18 $720.00
PSI Single Sieve Grain Analysis $35.00 8 EA $280.00 PSI Natural Moisture Content $12.00 8 EA $96.00 PSI Organic Content $40.00 2 EA $80.00…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .