This document is a Consultant's Task Assignment Notification and Scope of Work issued by the Florida Department of Environmental Protection (FDEP) for engineering services at Hugh Taylor Birch State Park. The contract is with Humiston & Moore Engineers, a coastal engineering firm based in Naples, Florida. The project involves coordination with multiple agencies including the U.S. Army Corps of Engineers (USACE) and the Broward County Department of Environmental Protection.
The scope of work focuses on designing, permitting, and providing construction administration for a seawall cap repair and rock revetment system installation at the park's eastern shoreline. The total fixed-price contract is $85,034.84, broken down into six specific tasks: site visit and assessment, preliminary design and survey, pre-application permitting meetings, environmental resource permitting, final design and permitting, and construction administration. The project timeline spans 540 days, with tasks including site surveys, environmental assessments, regulatory approvals, and on-site construction observation. The work aims to protect the shoreline, reduce boat wake energy impact, and minimize potential environmental disruption, particularly regarding seagrass preservation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN028-T6CO2.pdf | ||
| CN-370000-GC886-CO1.pdf | ||
| CN-370000-CN028-T1.pdf | ||
| CN-370000-CN028-T1CO1.pdf | ||
| CN-370000-CN028-T6CO3.pdf | ||
| CN-370000-CN028-A1.pdf | ||
| CN-370000-CN028-T2.pdf | ||
| CN-370000-CN028-T5CO1.pdf | ||
| CN-370000-CN028-TA4.pdf | ||
| CN-370000-CN028-TA6.pdf | ||
| CN-370000-CN028.pdf | ||
| CN-370000-CN028-T3.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW Page 1 of 4
Scope of Work for Engineering Services
Hugh Taylor Birch Seawall Cap Repair/Revetment System Installation June 6, 2015
Scope of Work
The eastern shoreline of Hugh Taylor Birch State Park is currently protected by a seawall and concrete cap which is in need is repair and maintenance. This scope of work is for the design and permitting of a sloping rock revetment to dissipate boat wake energy to protect the wall and park property, reduce scour at the base of the wall and support other improvements to the wall including the construction of a new seawall cap.
The proposed work area is within tidal waters of the State of Florida and will require authorization from the Florida Department of Environmental Protection (FDEP), the U.S.
Army Corps of Engineers (USACE) and the Broward County Department of Environmental Protection (BCDEP).
This proposal includes the collection of necessary site and nearshore bathymetric data to design the rock revetment. Also included within is the necessary Submerged Aquatic Vegetation (SAV) survey to ensure protection of seagrasses and natural resources. The project area is known to be a reasonable candidate for presence of seagrasses which will complicate and impose limitations on the design. If encountered, the design will be required to avoid and minimize the potential for impacts to seagrasses. The work within this proposal assumes that the final design will be permittable by the local state and federal agencies without the need for mitigation or variances. If mitigation is required, additional services would be necessary beyond the services provided herein to design and monitor the mitigation program.
This proposal also includes construction administration to include monthly site visits and intermediate site visits at construction milestones. It is assumed that construction will take 6 months for the rock placement and cap replacement depending on the final design. As such we propose to provide weekly site visits and monthly progress reports to facilitate construction administration throughout the project. After the first two months, site visits will be reduced to biweekly visits with the assumption that construction process is well established. Should construction take longer than 6 months, a proposal for Additional Services will be filed if deemed necessary.
The timelines are estimates as much of the regulatory review will depend upon the agency personnel and commenting resource natural resource agencies, as deemed necessary depending on the findings of the surveys and design.
5679 STRAND COURT
NAPLES, FLORIDA 34110
FAX: 239 594 2025
PHONE: 239 594 2021
SOW Page 2 of 4
Task 1 Site Visit: Conduct a site visit to review the conditions of the existing revetment and seawall. This visit will be conducted by both a coastal engineer and structural engineer. Site photos and a summary of findings will be prepared. Meeting will be held with surveyor and environmental specialist as well.
Deliverable 1 Upon completion of the site visit, a cover letter, with a summary of findings, site photos and notes from field observations will be provided to
DEP.
Performance Measure Deliverable to be reviewed by Department staff for acceptance.
Schedule 30 days from Task Assignment Execution.
Cost $4,361.36 Fixed Fee.
Task 2 Preliminary Design, Survey and Environmental Assessment: Collect hydrographic surveying data and upland profile data for the purpose of evaluating the existing conditions and develop a set of permit drawings for the development of a revetment and seawall cap repair and potentially sidewalk improvements to address the needs of the Parks Service. Using update bathymetry and a Submerged Aquatic Vegetation (SAV) survey including identification of natural resources, H&M will prepare a set of preliminary permit drawings for review and acceptance by DEP Parks Service for pre-application meetings with the Florida Department of Environmental Protection, the U.S. Army Corps of Engineers, and the Broward County Environmental Protection Department.
Deliverable 2 H&M will provide DEP with a set of preliminary plans including a site plan, 4 typical cross sections, a copy of the survey and environmental assessment including a Submerged Aquatic Vegetation survey.
Schedule 75 days from Task Assignment Execution.
Cost $26,209.33 Fixed Fee.
Task 3 Pre-Application Permitting Meetings: Upon DEP Parks Service acceptance of a plan to review with the local, state and federal agencies, H&M will schedule pre-applications meetings with each to review the most appropriate permitting path with each agency that achieve the design goals of the DEP Parks Service.
SOW Page 3 of 4
Deliverable 3 H&M will provide DEP with a summary of the three meetings (county, state and federal), and what is required from each agency to achieve the design goal of the Department.
Schedule 120 days from Task Assignment Execution.
Cost $8,536.66 Fixed Fee.
Task 4 Environmental Resource Permitting: Upon acceptance of a plans and results of the pre-application meetings, H&M will update the plans accordingly and prepare the necessary applications for the DEP, USACE and Broward County Environmental Protection. Meeting with USACE may not be necessary depending upon the outcome of the DEP meeting since they may potentially cover the project under the DEP review. H&M will respond to any and all requests for additional information based on the input and direction from DEP, the Florida DEP Parks Service, the USACE, and the Broward County Environmental staff. Regulatory application fees, state, federal and local, will be determined during the early phase of the process; payment of the fees will be the responsibility of the Park Service.
Deliverable 4 Copies of all county, state and federal applications, RAI responses and confirmation of complete applications with each agency referenced herein. The deliverable will be followed up with copies of all permits and authorizations once issued by Broward County, the State DEP and the
USACE.
Schedule 240 days from Task Assignment Execution.
Cost $13,142.46 Fixed Fee.
Task 5 Final Design & Permitting: H&M will prepare final construction plans and technical specifications for the proposed improvements and complete the state and federal permitting for the proposed new seawall cap, upland walkway improvements if part of this work1, and revetment restoration.
H&M will attend any preconstruction meeting required by the local, state and federal authorizations for this project.
1 Upland walkway may be handled separately by the Parks Service as this work is upland of the DEP and USACE jurisdiction.
SOW Page 4 of 4
Deliverable Plans and regulatory authorizations: H&M will provide DEP with 100% construction plans and a copy of the authorizations. Included with this package will be a set of final construction plans and a Bid Schedule and Opinion of Probable Costs. Two sets of signed and sealed plans to scale will be provided along with two sets of technical specifications, including the bid schedule. This information will also be provided on a CD.
Schedule 360 days from Task Assignment Execution.
Cost $10,158.56 Fixed Fee.
Task 6 Construction Administration: The project team will arrange pre-construction meeting with County, DEP and others as required. H&M will provide on-site construction observation services on monthly basis and at construction milestones to be determined at the initial construction meeting. On-site construction observation will be conducted for reviewing construction compliance with plans, specifications, and regulatory approvals and to review pay requests and to verify quantities of completed work. We have budgeted weekly meetings for the first two months followed by biweekly meetings for the next four months. The site meetings are intended to coincide with concrete pours for the cap, when feasible. For this reason the frequency of the meetings will vary to coincide with the progress of construction. Following two months of construction, H&M will be on site biweekly which is expected to coincide with every other pour. The initial site concrete cap pour inspection will include structural engineer subconsultant.
Coordination of concrete cylinder tests to be provided by Contractor and progress of construction will be coordinated with our structural engineer subconsultant. Monthly progress reports will be provided to the Department.
Deliverable H&M will provide a one-page monthly summary of construction progress with photos. H&M will provide post project certifications as required by the regulatory authorizations.
Schedule 540 days from Task Assignment Execution assuming 180-day construction period.
Cost $22,626.47 Fixed Fee.
Billing for engineering services as referenced above, will be on a completed task basis in accordance with the DEP approved fee schedule for Humiston & Moore Engineers.
SOW Page 5 of 4
Payment will be made upon completion of each task and submittal/approval by DEP of the deliverable for the amount specified.
Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.