This is an Invitation to Bid issued by the Gwinnett County Board of Commissioners for playground equipment replacement at Collins Hill Park in Lawrenceville, Georgia. The project involves demolition of existing playground equipment and installation of new equipment, surfacing, and drainage systems across two playgrounds located at the pavilion area near the park entrance and in the baseball complex. Bids must be received by 2:50 p.m. on March 4, 2022, at the Gwinnett County Purchasing Division, 75 Langley Drive, Lawrenceville, Georgia 30046, with public opening and reading at 3:00 p.m. A pre-bid conference is scheduled for 10:00 a.m. on February 23, 2022, at Collins Hill Park Baseball Playground. Questions regarding the bid must be directed to Jake Scarpone, Purchasing Associate II, no later than 3:00 p.m. on February 24, 2022. The contractor must commence preliminary and submittal work within 10 days of receiving the Notice to Proceed and substantially complete all work, including punch list items and cleanup, within 180 calendar days. The county will charge the contractor $500 per day for every day past the completion date. Bids must be submitted in duplicate, and the contract will be awarded to the lowest responsive and responsible bidder.

All contractors must submit a bid bond, certified check, or cashier's check in the amount of five percent of the total bid. The successful contractor will be required to submit a one hundred percent performance bond and a one hundred percent payment bond, with all bonding companies holding an A.M. Best rating of A-5 or higher and licensed by the Georgia Secretary of State. The bidder must have completed a minimum of three similar projects within the past five years and provide reference contacts; the playground equipment installer must be certified by the manufacturer. The contractor is responsible for all construction layout and control and must provide erosion and sedimentation control throughout the project. Payment will be made via electronic remittance, with progress payments made monthly less ten percent retainage until payments total 50 percent of the contract price. The contractor shall be paid within 30 days of the county's receipt of payment requests, with interest accruing at one-half percent per month if payment is not made within 60 days.

Text of this file

February 9, 2022

INVITATION TO BID

BL020-22

Playground Replacement at Collins Hill Park

The Gwinnett County Board of Commissioners is soliciting competitive sealed bids from qualified contractors for the Playground Replacement at Collins Hill Park for the Gwinnett County Department of Community Services.

Bid submittal date and location

Bids should be typed or submitted in ink and returned in a sealed container marked on the outside with the BL# and Company Name. Bids will be received until 2:50 P.M. local time on March 4, 2022 at the Gwinnett County Purchasing Division, 75 Langley Drive, Lawrenceville, Georgia 30046. Any bid received after this date and time will not be accepted. Bids will be publicly opened and read at 3:00 P.M. Apparent bid results will be available the following business day on our website www.gwinnettcounty.com.

Pre-Bid Conference A pre-bid conference is scheduled for 10:00 a.m. on February 23, 2022 at the Gwinnett County Collins Hill Park Baseball Playground, 2225 Collins Hill Road, Lawrenceville, GA 30046. All contractors are urged to attend.

Project Description Replace playground equipmentin the baseball and pavilion playgrounds at Collins Hill Park.

Safety Protocol During the pre-bid conference and the bid opening, we ask that you wear a mask and practice social distancing.

Instructions on Submitting Questions Questions regarding bids should be directed to Jake Scarpone, Purchasing Associate II, at jake.scarpone@gwinnettcounty.com or by calling 770-822-8722, no later than 3:00 P.M. on February 24, 2022. Bids are legal and binding upon the bidder when submitted. All bids should be submitted in duplicate.

To view plans: a complete set of plans and documents are available for viewing at the Gwinnett County Purchasing office (plans, documents & plan holders list are NOT distributed by Purchasing).

To obtain plans and/or plan holders list: A complete set of plans and documents as a pdf may be obtained at no cost from Gwinnett County Purchasing, Jake Scarpone, 75 Langley Drive, Lawrenceville, GA 30046, phone 770-822-8722, email jake.scarpone@gwinnettcounty.com.

THE PLAN-HOLDERS LIST IS AVAILABLE FROM Gwinnett County Purchasing

Bonding and Insurance All contractors must submit with bid, a bid bond, certified check or cashier's check in the amount of five percent (5%) of the total bid. Failure to submit a bid bond with the proper rating will result in the bid being deemed non-responsive. Successful contractor will be required to meet insurance requirements, submit a one hundred percent (100%) performance bond and a one hundred percent (100%) payment bond. Insurance and Bonding Company should be licensed to do business by the Georgia Secretary of State, authorized to do business in Georgia by The Georgia Insurance Department, listed in the Department of Treasury's Publication of Companies holding Certificates of Authority as Acceptable Surety on Federal Bonds and as acceptable reinsuring companies. The bid bond, payment bond, and performance bond must have an A.M. Best rating of A-5 or higher.

http://www.gwinnettcounty.com/

Gwinnett County, Georgia Page 2 Playground Replacement at Collins Hill Park BL020-22

Facility Access

Gwinnett County does not discriminate on the basis of disability in the admission or access to its programs or activities. Any requests for reasonable accommodations required by individuals to fully participate in any open meeting, program or activity of Gwinnett County Government should be directed to the ADA Coordinator, Gwinnett County Justice and Administration Center, 770-822-8165.

The written bid documents supersede any verbal or written prior communications between the parties.

Award will be made to the contractors submitting the lowest responsive and responsible bid. Gwinnett County reserves the right to reject any or all bids to waive technicalities and to make an award deemed in its best interest.

Bids may be split or awarded in entirety. Gwinnett County reserves the option to negotiate terms, conditions and pricing with the lowest responsive, responsible bidder(s) at its discretion.

Award notification will be posted after award on the County website, www.gwinnettcounty.com and companies submitting a bid will be notified via email.

We look forward to your bid and appreciate your interest in Gwinnett County.

Jake Scarpone Purchasing Associate II http://www.gwinnettcounty.com/

Gwinnett County, Georgia Page 3

SECTION 00010

TABLE OF CONTENTS

Specifications

Section Title

Division 00 – Bid and Contracting Requirements

Invitation to Bid Scope of Work

Special Provisions Bid Schedule Contractor Information Page Non-Collusion Affidavit Corporation Information References List of Subcontractors Bid Bond General Conditions Standard Insurance Requirements Bonding and Contract Requirements Sample Contract Contractor Affidavit and Agreement Code of Ethics Affidavit Sample Payment Bond Sample Performance Bond No-Bid Document General Instructions for Bidders, Terms and Conditions Schedule of Drawings

Division 01 – General Requirements

01500 Temporary Facilities and Controls 01631 Products and Substitutions 01700 Contract Closeout

Division 02 – Site Construction

02070 Selective Demolition 02207 Erosion Control 02791 Playground Surface System 02881 Playground Equipment and Structures

Division 03 – Concrete

03310 Cast-in-Place Concrete

TABLE OF CONTENTS 00010 - 1

Gwinnett County, Georgia Page 4

Appendix A – Equipment List

Appendix B – Product Specifications and Warranty

Appendix C – Reduced Size Plans

Appendix D – Equipment Comparison Format

TABLE OF CONTENTS 00010 - 2

Gwinnett County, Georgia Page 5

END OF SECTION 00010

SECTION 00001

Scope of Work

PART 1 GENERAL

1.01 Scope of Work

A. This project includes demolition of existing playground equipment, surfacing & drainage within the playground areas, and installation of new equipment, concrete ramps, surfacing & drainage for two playgrounds.

B. The project is located in Collins Hill Park, 2225 Collins Hill Rd., Lawrenceville, GA 30046

The playgrounds are located at the pavilion area near the park entrance and in the baseball complex near the large concession building.

C. The parks will be open to the public during construction, so it is required that the public be protected from any hazards associated with the construction site and/or construction staging area(s).

D. Any disturbance of existing ground will require erosion and sedimentation control.

END OF SECTION 00001

SCOPE OF WORK 00001 - 1

Gwinnett County, Georgia Page 6

SPECIAL PROVISIONS

Special Provisions take precedence over the General Conditions of this project manual contract document.

These provisions are in lieu of, in addition to, and clarification of the General Conditions referenced.

1. Individuals, firms and businesses seeking an award of a Gwinnett County contract may not initiate or continue any verbal or written communications regarding a solicitation with any County officer, elected official, employee, or other County representative without permission of the Purchasing Associate named in the solicitation between the date of issuance of the solicitation and the date of the final contract award by the Board of Commissioners. Violations will be reviewed by the Purchasing Director. If determined that such communication has compromised the competitive process, the offer submitted by the individual, firm or business may be disqualified from consideration for award.

1. All references to "Engineer", "Landscape Architect", "Architect", or "Owner" in the General Conditions, drawings or specifications are deemed to mean "Owner's Representative", as designated by the County.

2. METHOD OF AWARD

The Contract will be awarded to the lowest responsive, responsible Bidder submitting the Bid complying with the Contract Documents. The project may be awarded by base bid or base bid plus selected alternates, if applicable, as deemed in the best interest of the County.

3. TIME OF WORK

It is understood that the Contractor’s proposed construction schedule is based on a normal 40 hour, 5-day work week, less recognized holidays. If the Contractor desires to work in excess of this limit, the Contractor shall submit a written request to the County minimum of five days prior to the desired work date. The Contractor shall be responsible for any additional expenses incurred by the County as a result of the extended work hours. No inspections and or exchange of critical information will be done during the days and hours when the County is closed. Any notification received after 4 PM will be considered received at 8 AM the following business day. Emergency situations may be addressed during closed times by calling the contact person listed on the contract drawings or as assigned and provided by the County Project Manager.

4. EROSION, SEDIMENTATION AND POLLUTION CONTROL MAINTENANCE

No payment will be made for any portion of the project for which temporary erosion, sedimentation and pollution controls are not properly maintained. Any fines or delays for non-compliance of erosion control measures levied by any agency will be the responsibility of the Contractor.

5. WEATHER DAYS

The contractor's request for additional time due to inclement weather shall only be granted for the number of days beyond those listed below. The contract number of days was developed with a certain number of inclement weather days expected per month. The burden of proof and documentation for such request shall rest solely upon the contractor. A written request must be submitted with the pay application for the month in which the inclement weather caused delay.

SPECIAL PROVISIONS SP - 1

Gwinnett County, Georgia Page 7

January 10 days July 4 days February 10 days August 2 days March 7 days September 2 days April 6 days October 3 days May 4 days November 5 days June 3 days December 9 days

6. APPROVED VENDORS

All references to vendors and “approved manufacturers” are included for description of quality and content of the designated equipment/materials. Equivalent items may be accepted if they meet all standards of quality and purpose for the intended use, as determined by Gwinnett County.

7. LANGUAGE

There shall be at least one person in a position of responsibility representing the Contractor, on site at all times that is capable of translating from English to the language used by the workforce.

8. SCHEDULE OF VALUES

Contractor, after award of Contract, shall submit a Schedule of Values, identifying costs for meaningful areas of the Work, such that progress payments can be easily evaluated, as determined by the County.

9. CONTRACTOR EXPERIENCE

Bidder should have completed construction of a minimum of three (3) projects of a similar size and scope within the past five (5) years and submit reference contacts on the enclosed form. The Contractor will identify on the Reference Form, by name, the Superintendent for each project. The Superintendent assigned to this project must have directed at least one of the three references. The requirement that the Contractor have a General Contractor’s license has been waived for this project.

However, the playground equipment installer must be certified by the manufacturer.

10. LIST OF SUBCONTRACTORS

Contractor shall submit a full List of Subcontractors with the Bid. Any changes during construction must be approved, in advance, by the County.

11. COORDINATION

The Contractor is responsible for becoming familiar with the requirements of all construction documents, which includes drawings, specifications, bid documents and all addenda. Information affecting the scope of work for all trades and subcontractors will be found throughout all documents.

It is the Contractor’s responsibility to provide all Sub-Contractors all the necessary information and drawings.

12. CONSTRUCTION LAYOUT

The Contractor is responsible for all construction layout and control for the project. The Contractor will proceed with construction layout in such a manner that discrepancies between construction items, existing built features and site conditions that are in conflict with the plans may be examined

SPECIAL PROVISIONS SP - 2

Gwinnett County, Georgia Page 8 by the Owner’s Representative prior to construction of items in conflict. Failure to notify the Owner’s representative of conflicts prior to construction of items will result in all remedial actions being paid for by the Contractor including, but not limited to additional materials, re-inspection fees, testing costs and survey cost by all parties to the project.

END SPECIAL PROVISIONS

SPECIAL PROVISIONS SP - 3

Gwinnett County, Georgia Page 9

FAILURE TO RETURN THIS PAGE AS PART OF YOUR BID DOCUMENT MAY RESULT IN REJECTION OF

BID.

BID SCHEDULE

The Bidder has carefully examined and fully understands the Contract, Plans and Specifications and other Documents hereto attached, and has made a personal examination of the Site of the proposed Work, and has satisfied himself as to the actual conditions and requirements of the Work, and hereby proposes and agrees that if his bid is accepted, he will contract with Gwinnett County according to bidding Documents entitled Playground Replacement at Collins Hill Park and Addenda, as well as the existing conditions of the project, and conditions affecting the Work, the undersigned proposes to furnish all services, labor and materials required by them in accord with said documents, personal observations of the site conditions, for the sum as follows:

Collins Hill Baseball Playground: as indicated on drawings and specifications $

Collins Hill Pavilion Playground: as indicated on drawings and specifications $

Total $

The Undersigned agrees to commence all preliminary and submittal work within 10 days of the date of the Notice to Proceed issued by Gwinnett County Purchasing Office and to commit adequate forces on site to substantially complete all Work including punch list items and clean-up, as determined by the County within 180 calendar days. Gwinnett County will charge the Contractor $500.00 (Five hundred dollars), per day for every day past the completion date of the Contract.

The undersigned acknowledges receipt of the following addenda, listed by number and date appearing on each:

Addendum No. Date Addendum Date

Gwinnett County, Georgia Page 8

FAILURE TO RETURN THIS PAGE AS PART OF YOUR BID DOCUMENT MAY RESULT IN REJECTION.

CONTRACTOR INFORMATION

The undersigned acknowledges receipt of the following addenda, listed by number and date appearing on each:

Addendum No. Date Addendum No. Date

Certification Of Non-Collusion in Bid Preparation

(Signature) (Date)

The County requires that all who enter into a contract for the physical performance of services with the County must satisfy O.C.G.A. § 13-10-91 and Rule 300-10-1-.02, in all manner, and such are conditions of the contract.

In compliance with the attached specifications and O.C.G.A. §36-91-50, the undersigned offers and agrees, if this bid is accepted by the Board of Commissioners within sixty (60) days of the date of bid opening, to furnish any or all of the items upon which prices are quoted, at the price set opposite each item, delivered to the designated point(s) within the time specified in the bid schedule. By submission of this bid, I understand that Gwinnett County uses Electronic Payments for remittance of goods and services. Vendors should select their preferred method of electronic payment upon notice of award. For more information on electronic payments, please refer to the Electronic Payment information in the instructions to bidders.

Legal Business Name

Federal Tax ID

Address

Does your company currently have a location within Gwinnett County? Yes No

Representative Signature

Print Authorized Representative's Name

Telephone Number Fax Number

E-Mail Address

Contact Person (if someone other than the authorized representative listed above) ___________________________________________

Telephone Number Fax Number

E-Mail Address

Gwinnett County, Georgia Page 9

NON-COLLUSION AFFIDAVIT

Now here appeared before the undersigned officer duly authorized by the State of Georgia to administer oaths______________________________________________and after being first duly sworn, depose and say that, they are all the officers, agents, persons or employees who have acted for (Company Name) on the Playground Replacement at Collins Hill Park and that said has not by (himself, themselves) or through any persons, officers, agents or employees prevented or attempted to prevent by any means whatsoever, competition in such bidding; or by any means whatever prevented or endeavored to prevent anyone from making a bid therefore, or induced or attempted to induce another to withdraw bid from said work.

BY:______________________________________

Signature of Affiant

Name – Typed or printed

Title

Sworn to and subscribed before me this _______ day of ______________, 20 .

Notary Public

(Seal)

Note: See OCGA § 36-91-21 (e)

Gwinnett County, Georgia Page 10

CORPORATION INFORMATION

CORPORATE NAME

CORPORATE ADDRESS

MAILING ADDRESS (IF DIFFERENT)

DOING BUSINESS AS (IF DIFFERENT THAN CORPORATE NAME)

CORPORATE OFFICERS: PRESIDENT

SECRETARY

TREASURER

VICE PRESIDENT

REGISTERED AGENT ADDRESS

POWER OF ATTORNEY ADDRESS

DATE OF INCORPORATION

NUMBER OF FULL DAYTIME EMPLOYEES (M-F/8-5)

HAS THE CORPORATION OR ANY OF ITS OFFICERS/AGENTS BEEN INVOLVED IN ANY

LITIGATION IN THE PAST FIVE YEARS? IF SO, PROVIDE DATE AND EXPLANATION

Gwinnett County, Georgia Page 11

REFERENCES

Gwinnett County requests a minimum of three (3) references where work of a similar size and scope has been completed within the past five (5) years.

Note: References should be customized for each project, rather than submitting the same set of references for every project bid. The references listed should be of similar size and scope of the project being bid on. Do not submit a project list in lieu of this form.

1. Company Name

Brief Description of Project

Completion Date

Contract Amount $ Start Date

Contact Person Telephone

2. Company Name

3. Company Name

Company Name

Gwinnett County, Georgia Page 12

LIST OF SUBCONTRACTORS

I do , do not , propose to subcontract some of the work on this project. I propose to Subcontract work to the following subcontractors:

NAME AND ADDRESS

TYPE OF WORK

Company Name

Gwinnett County, Georgia Page 13

BID BOND

KNOW ALL MEN BY THESE PRESENTS: that

(Name of Contractor)

(Address of Contractor) a (Corporation, Partnership or Individual) hereinafter called Principal, and

(Name of Surety)

(Address of Surety) a Corporation of the State of , and a surety authorized by law to do business in the State of Georgia, hereinafter called Surety, are held and firmly bound unto

Gwinnett County Board of Commissioners (Name of Obligee)

75 Langley Drive, Lawrenceville, Georgia 30046 (Address of Obligee)

Thereinafter referred to as Obligee: in the penal sum of

Dollars

($ ) in lawful money of the United States, for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.

WHEREAS, the Principal is about to submit, or has submitted, to Gwinnett County, Georgia, a proposal for furnishing materials, labor, and equipment for:

WHEREAS, the Principal desires to file this Bond in accordance with law in lieu of a certified Bidder's check otherwise required to accompany this Proposal.

NOW, THEREFORE, the conditions of this obligation are such that if the proposal be accepted, the Principal shall within ten days after receipt of notification of the acceptance, execute a Contract in accordance with the Proposal and upon the terms, conditions, and prices set forth in the form and manner required by Gwinnett County, Georgia, and execute a sufficient and satisfactory Performance Bond and Payment Bond payable to Gwinnett County, Georgia, each in the amount of 100% of the total Contract Price, in form and with security satisfactory to said Gwinnett County, Georgia, and otherwise, to be and remain in full force and virtue in law, and the Surety shall, upon failure of the Principal to comply with any or all of the foregoing requirements within the time specified above, immediately pay to Gwinnett County, Georgia, upon demand, the amount hereof in good and lawful money of the United States of America, not as a penalty, but as liquidated damages.

Gwinnett County, Georgia Page 14

PROVIDED, FURTHER, that Principal and Surety agree and represent that this bond is executed pursuant to and in accordance with the applicable provisions of the Official Code of Georgia Annotated, as Amended, including, but not limited to, O.C.G.A. § 36-91-1 et seq., and is intended to be and shall be constructed as a bond in compliance with the requirements thereof.

Signed, sealed and dated this day of , A.D., 20 .

ATTEST:

(Principal)

(Principal Secretary)

By:

(SEAL)

(Address)

(Witness as to Principal)

(Surety)

ATTEST: By:

(Attorney-in-Fact)

Resident or Nonresident Agent

(SEAL)

(Witness as to Surety)

NOTE: If Contractor is Partnership, all partners should execute Bond. Surety Companies executing Bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the Project is located.

Principal Secretary, Principal and Witness as to Principal signature lines must be signed by three different individuals. Additionally, Resident or Nonresident Agent, Witness as to Surety, and Attorney-in-fact must be signed by three different individuals.

Gwinnett County, Georgia Page 15

GENERAL CONDITIONS

FOR GWINNETT COUNTY CONSTRUCTION CONTRACTS

GC-1 FAMILIARITY WITH SITE

Execution of this agreement by the Contractor is a representation that the Contractor has visited the site, has become familiar with the local conditions under which the work is to be performed, and has correlated personal observations with the requirements of this agreement.

GC-2 CONTRACT DOCUMENTS

This agreement consists of Gwinnett County's request for proposals, instructions to bidders, Contractor's proposal, construction contract, Performance Bond, Payment Bond, general conditions, special provisions, specifications, plans, drawings, addenda, and written change orders.

GC-3 DEFINITIONS

The following terms as used in this agreement are defined as follows:

Change Order - a written order to the Contractor, prepared by the Engineer and issued by the County for changes in the work within the general scope of the contract documents, adjustment of the contract price, extension of the contract time, or reservation of determination of a time extension.

County - Gwinnett County, Georgia, a political subdivision of the State of Georgia, acting by and through the Chairman of its Board of Commissioners.

Day - a calendar day of twenty-four hours lasting from midnight of one day to midnight the next day.

Notice to Proceed - written communication issued by the County to the Contractor authorizing it to proceed with the work and establishing the date of commencement and completion of the work.

Substantial Completion - the date certified by the engineer when all or a part of the work, identified in the engineer's certification, is sufficiently completed in accordance with the requirements of the contract documents so that the identified portion of the work can be utilized for the purposes for which it is intended.

Work - all of the services specified, indicated, shown or contemplated by the contract documents, and furnishing by the Contractor of all materials, equipment, labor, methods, processes, construction and manufacturing materials and equipment, tools, plans, supplies, power, water, transportation and other things necessary to complete such services in accordance with the contract documents to insure a functional and complete facility.

GC-4 CODES

All codes, specifications, and standards referenced in the contract documents shall be the latest additions, amendments and revisions of such referenced standards in effect as of the date of the request for proposals for this contract.

GC-5 REVIEW OF CONTRACT DOCUMENTS

Before making its proposal to the County, and continuously after the execution of the agreement, the Contractor shall carefully study and compare the contract documents and shall at once report to the engineer any error, ambiguity, inconsistency or omission that may be discovered, including any requirement which may be contrary to any law, ordinance, rule, or regulation of any public authority bearing on the performance of the work. By submitting its proposal, the Contractor agrees that the contract documents, along with any supplementary written instructions issued by or through the engineer

Gwinnett County, Georgia Page 16 that have become a part of the contract documents appear accurate, consistent and complete insofar as can be reasonably determined. If the Contractor has reported in writing any error, inconsistency, or omission to the County, has properly stopped the effected work until instructed to proceed, and has otherwise followed the instructions of the engineer, the Contractor shall not be liable to the County for any damage resulting from any such error, inconsistency, or omission in the contract documents. The Contractor shall not perform any portion of the work without the contract documents, approved plans, specifications, products and data, or samples for such portion of the work.

GC-6 STRICT COMPLIANCE

No observation, inspection, test or approval of the County or engineer shall relieve the Contractor from its obligation to perform the work in strict conformity with the contract documents.

GC-7 APPLICABLE LAW

All applicable State laws, County ordinances, and rules and regulations of all authorities having jurisdiction over the construction of the project shall apply to this agreement. All work performed within the right of way of the Georgia Department of Transportation shall be in accordance with DOT regulations, policies and procedures. The Contractor shall comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as specified and the Contractor agrees to indemnify and hold harmless the County, its officers, agents and employees, as well as the engineer, against any claim or liability arising from or based on the violation of any law, ordinance, regulation, order or decree affecting the conduct of the work, whether occasioned by the Contractor, his agents or employees.

GC-8 PERMITS & LICENSES

All permits and licenses necessary for the work shall be secured and paid for by the Contractor. If any permit, license or certificate expires or is revoked, terminated, or suspended as a result of any action on the part of the Contractor, the Contractor shall not be entitled to additional compensation or time.

GC-9 TAXES

The Contractor shall pay all sales, retail, occupational, service, excise, old age benefit and unemployment compensation taxes, consumer, use and other similar taxes, as well as any other taxes or duties on the materials, equipment, and labor for the work provided by the Contractor which are legally enacted by any municipal, county, state or federal authority, department or agency at the time bids are received, whether or not yet effective. The Contractor shall maintain records pertaining to such taxes and levies as well as payment thereof and shall make the same available to the County at all reasonable times for inspection and copying.

GC-10 DELINQUENT CONTRACTORS

The County shall not pay any claim, debt, demand or account whatsoever to any person firm or corporation who is in arrears to the County for taxes. The County shall be entitled to a counterclaim and offset for any such debt in the amount of taxes in arrears, and no assignment or transfer of such debt after the taxes become due shall affect the right of the County to offset any taxes owed against said debt.

GC-11 LIEN WAIVERS

The Contractor shall furnish the County with evidence that all persons who have performed work or furnished materials pursuant to this agreement have been paid in full prior to submitting its demand for final payment pursuant to this agreement. In the event that such evidence is not furnished, the County may retain sufficient sums necessary to meet all lawful claims of such laborers and materialmen. The County assumes no obligation nor in any way undertakes to pay such lawful claims from any funds due or that may become due to the Contractor.

Gwinnett County, Georgia Page 17

GC-12 MEASUREMENT

All items of work to be paid for per unit of measurement shall be measured and certified by the Engineer.

GC-13 ASSIGNMENT

The Contractor shall not assign any portion of this agreement or moneys due therefrom without the prior written consent of the County. The Contractor shall retain personal control and shall provide personal attention to the fulfillment of its obligations pursuant to this agreement.

GC-14 FOREIGN CONTRACTORS

In the event that the Contractor is a foreign corporation, partnership, or sole proprietorship, the Contractor hereby irrevocably appoints the Secretary of State of Georgia as its agent for service of all legal process for the purpose of this contract only.

GC-15 INDEMNIFICATION

To the fullest extent permitted by law, the Contractor shall, at his sole cost and expense, indemnify, defend, satisfy all judgments, and hold harmless the County, the engineer, and their agents and employees from and against all claims, damages, actions, judgments, costs, penalties, liabilities, losses and expenses, including, but not limited to, attorney's fees arising out of or resulting from the performance of the work, provided that any such claim, damage, action, judgment, cost, penalty, liability, loss or expense (1) is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless whether such claim is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge or otherwise reduce any of the rights or obligations of indemnity which would otherwise exist as to any party or person described in this agreement. In any and all claims against the County, the engineer, or any of their agents or employees by any employee of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation contained herein shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor under Worker's Compensation Acts, disability benefit acts, or other employee benefit acts.

GC-16 SUPERVISION OF WORK

The Contractor shall supervise and direct the work using the Contractor's best skill and attention. The Contractor shall be solely responsible for all construction methods and procedures and shall coordinate all portions of the work pursuant to the contract subject to the overall coordination of the engineer. All work pursuant to this agreement shall be performed in a skillful and workmanlike manner.

GC-17 RESPONSIBILITY FOR WORK

The Contractor shall not be relieved from the Contractor's obligations to perform the work in accordance with the contract documents by the activities or duties of the engineer, including inspections, tests or approvals required or performed pursuant to this agreement.

GC-18 RESPONSIBILITY FOR ACTS OF EMPLOYEES

The Contractor shall be responsible to the County for the acts and omissions of its employees, subcontractors, and agents as well as any other persons performing work pursuant to this agreement.

All areas within the limits of the Project which are determined by the Engineer to be unnecessarily damaged, due either directly or indirectly to the process of construction, shall be responsibility of the Contractor to correct and repair. This is not a payment item and shall be done without additional

Gwinnett County, Georgia Page 18 compensation.

GC-19 PAYMENT FOR LABOR AND MATERIALS

Unless otherwise provided in this agreement, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the execution and completion of the work.

GC-20 DISCIPLINE ON WORK SITE

The Contractor shall enforce strict discipline and good order among its employees and subcontractors at all times during the performance of the work. The Contractor shall not employ any subcontractor who is not skilled in the task assigned to it. The engineer may, by written notice, require the Contractor to remove from the work any subcontractor or employee deemed by the engineer to be incompetent.

GC-21 HOURS OF OPERATION

All work at the construction site shall be performed during regular business hours, except upon the engineer's prior written consent to other work hours.

GC-22 FAMILIARITY WITH WORK CONDITIONS

The Contractor shall take all steps necessary to ascertain the nature and location of the work and the general and local conditions, which may affect the work or the cost thereof. The Contractor's failure to fully acquaint itself with the conditions which may affect the work, including, but not limited to conditions relating to transportation, handling, storage of materials, availability of labor, water, roads, weather, topographic and subsurface conditions, other separate contracts to be entered into by the County relating to the project which may affect the work of the Contractor, applicable provisions of law, and the character and availability of equipment and facilities necessary prior to and during the performance of the work shall not relieve the Contractor of its responsibilities pursuant to this agreement and shall not constitute a basis for an equitable adjustment of the contract terms. The County assumes no responsibility for any understandings or representations concerning conditions of the work made by any of its officers, agents, or employees prior to the execution of this agreement.

GC-23 RIGHT OF ENTRY

The County reserves the right to enter the site of the work by such agent as it may elect for the purpose of inspecting the work or installing such collateral work as the County may desire.

GC-24 NOTICES

Any notice, order, instruction, claim or other written communication required pursuant to this agreement shall be deemed to have been delivered or received as follows:

(1) Upon personal delivery to the Contractor, it’s authorized representative, or the engineer on behalf of the County. Personal delivery may be accomplished by in-person hand delivery or bona fide overnight express service.

(2) Three days after depositing in the United States mail a certified letter addressed to the Contractor, the County, or the engineer. For purposes of mailed notices, the County's mailing address shall be 75 Langley Drive, Lawrenceville, Georgia 30046. The Contractor's mailing address shall be the address stated in its proposal, and the engineer's mailing address shall be its address listed in the Notice to Begin Work.

GC-25 SAFETY

The Contractor shall take all reasonable precautions for the safety of all persons and property associated with the work, and the Contractor shall erect and maintain, as required by existing conditions and the progress of the work, all reasonable safeguards for the safety and protection of persons in the vicinity of the project.

Gwinnett County, Georgia Page 19

GC-26 BLASTING AND EXCAVATION

The Contractor acknowledges that it is fully aware of the contents and requirements of O.C.G.A. § 25- 9-1 through 25-9-12 concerning blasting and excavation near underground gas pipes and facilities and shall fully comply therewith.

GC-27 HIGH VOLTAGE LINES

The Contractor acknowledges that it is fully aware of the contents and requirements O.C.G.A. § 46-3-30 through 46-3-39 concerning safeguards against contact with high voltage lines, and the Contractor shall fully comply with said provisions.

GC-28 SCAFFOLDING AND STAGING

The Contractor acknowledges that it is the person responsible for employing and directing others to perform labor within the meaning of O.C.G.A. § 34-1-1 and agrees to comply with said provisions.

GC-29 CLEAN-UP

The Contractor shall clean up all refuse, rubbish, scrap materials, and debris caused by its operations to the end that the site of the work shall present a neat, orderly and workmanlike appearance at all times.

GC-30 PROTECTION OF WORK

The Contractor shall be responsible for maintenance and protection of the work until final completion of this agreement and acceptance of the work as defined herein. Any portion of the work suffering injury, damage or loss shall be considered defective and shall be corrected or replaced by the Contractor without additional cost to the County.

GC-31 REJECTED WORK

The Contractor shall promptly remove from the project all work rejected by the engineer for failure to comply with the contract documents and the Contractor shall promptly replace and re-execute the work in accordance with the contract documents and without expense to the County. The Contractor shall also bear the expense of making good all work of other Contractors destroyed or damaged by such removal or replacement.

GC-32 DEFECTIVE WORK

If the Contractor defaults or neglects to carry out any portion of the work in accordance with the contract documents, and fails within three days after receipt of written notice from the County or the engineer to commence and continue correction of such default or neglect with diligence and promptness, the County or the engineer may, after three days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy the County may have, make good such deficiencies and complete all or any portion of any work through such means as the County may select, including the use of a new Contractor. In such case, an appropriate change order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies. In the event the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the County on demand.

GC-33 NEW MATERIALS

The Contractor warrants to the County that all materials and equipment furnished under this contract will be new unless otherwise specified, and the Contractor further warrants that all work will be of good quality, free from faults and defects, and in conformance with the contract documents. The warranty set forth in this paragraph shall survive final acceptance of the work.

GC-34 CONTRACTOR'S WARRANTY

If within one year after the date of substantial completion and final acceptance of the work by the County, or within such longer period of time as may be prescribed by law or by the term of any applicable special

Gwinnett County, Georgia Page 20 warranty required by the contract documents, any of the work is found to be defective or not in accordance with the contract documents, the Contractor shall correct such work promptly after receipt of written notice from the County to do so. This obligation shall survive both final payment for the work and termination of the contract.

GC-35 ASSIGNMENT OF MANUFACTURERS' WARRANTIES

Without limiting the responsibility or liability of the Contractor pursuant to this agreement, all warranties given by manufacturers on materials or equipment incorporated in the work are hereby assigned by the Contractor to the County. If requested, the Contractor shall execute formal assignments of said manufacturer's warranties to the County. All such warranties shall be directly enforceable by the County.

GC-36 WARRANTIES IMPLIED BY LAW

The warranties contained in this agreement, as well as those warranties implied by law, shall be deemed cumulative and shall not be deemed alternative or exclusive. No one or more of the warranties contained herein shall be deemed to alter or limit any other.

GC-37 STOP WORK ORDERS

In the event that the Contractor fails to correct defective work as required by the contract documents or fails to carry out the work in accordance with contract documents, the County, or the engineer, in writing, may order the Contractor to stop work until the cause for such order has been eliminated. This right of the County or engineer to stop work shall not give rise to any duty on the part of the County or the engineer to execute this right for the benefit of the Contractor or for any other person or entity.

GC-38 TERMINATION FOR CAUSE

If the Contractor is adjudged bankrupt, makes a general assignment for the benefit of creditors, suffers the appointment of a receiver on account of its insolvency, or fails to supply sufficient properly skilled workers, materials, fails to make prompt payment to subcontractors or materialmen, disregards laws, ordinances, rules, regulations, or orders of any public authority having jurisdiction, or is otherwise guilty of a material violation of this agreement and fails within seven days after receipt of written notice to commence and continue correction of such default, neglect, or violation with diligence and promptness, the County may, after ten days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy the County may have, terminate the employment of the Contractor and take possession of the site as well as all materials, equipment, tools, construction equipment and machinery thereon. The County may finish the work by whatever methods the County deems expedient.

In such case, the Contractor shall not be entitled to receive any further payment until the work is completed. If the unpaid balance of the contract price exceeds the cost of completing the work, such excess shall be paid to the Contractor. If such costs exceed the unpaid balance, the Contractor shall pay the difference to the County on demand. This obligation for payment shall survive the termination of the contract. Termination of this agreement pursuant to this paragraph may result in disqualification of the Contractor from bidding on future County contracts.

GC-39 TERMINATION FOR CONVENIENCE

The County may, at any time upon 30 days written notice to the Contractor, terminate the whole or any portion of the work for the convenience of the County. Said termination shall be without prejudice to any right or remedy of the County provided herein. In addition, in the event this agreement has been terminated due to the default of the Contractor, and if it is later determined that the Contractor was not in default pursuant to the provisions of this agreement at the time of termination, then such termination shall be considered a termination for convenience pursuant to this paragraph.

GC-40 TERMINATION FOR CONVENIENCE - PAYMENT

Gwinnett County, Georgia Page 21

In the event that the County terminates this agreement for the convenience of the County, the County shall only be liable to the Contractor for those costs reimbursable to the Contractor plus a mark-up of ten percent on the actual fully accounted cost recovered pursuant to this paragraph. In the event that it appears that the Contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed hereunder and an appropriate adjustment shall be made reducing the amount of settlement to reflect the indicated rate of loss. In the event of termination for the convenience of the County, the County shall pay the Contractor the following amounts determined by the engineer:

A. An amount for supplies, services, or property accepted by the County for which payment has not previously been made. The price to be paid for these items shall be equivalent to the aggregate price for such supplies or services computed in accordance with the price specified in this agreement appropriately adjusted for any saving of freight or other charges; and

B. The total of:

(1) The costs incurred in the performance of the work terminated, including initial costs and preparatory expenses allocable thereto, but exclusive of any costs attributable to supplies or services previously paid;

(2) The costs of settling and paying claims arising pursuant to the termination of the work under said contracts or orders which are properly chargeable to the terminated portion of the contract (exclusive of the amounts paid or payable on account of completed items or equipment delivered or services furnished by a subcontractor or vendor prior to the effective date of the notice of termination, which amounts shall be included in the costs payable pursuant to (A); and

(3) The reasonable costs of settlement, including accounting, legal, clerical, and other expenses reasonable and necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts thereunder, together with reasonable storage, transportation, and other costs incurred in connection with the protection or disposition of property allocable to this agreement.

GC-41 TERMINATION FOR CONVENIENCE - PAYMENT LIMITATIONS

In the event of termination for the convenience of the County, the total sum to be paid to the Contractor shall not exceed the contract price as reduced by the amount of payments otherwise made, by the contract price for work not terminated, and as otherwise permitted by the contract. Except for normal spoilage, and except to the extent that the County shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the Contractor the fair value, as determined by the engineer, of property which is destroyed, lost, stolen or damaged so as to become undeliverable to the County or to another buyer.

GC-42 COST TO CURE

If the County terminates the whole or any part of the work pursuant to this agreement, then the County may procure upon such terms and in such manner as the engineer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the County for any excess costs for such similar supplies or services. The Contractor shall continue the performance of this agreement to the extent not terminated hereunder.

GC-43 ATTORNEY'S FEES

Gwinnett County, Georgia Page 22

Should the Contractor default pursuant to any of the provisions of this agreement, the Contractor and its surety shall pay to the County such reasonable attorney's fees as the County may expend as a result thereof and all costs, expenses, and filing fees incidental thereto.

GC-44 CONTRACTOR'S RESPONSIBILITIES UPON TERMINATION

After receipt of a notice of termination from the County, and except as otherwise directed by the engineer, the Contractor shall:

1. Stop work under the contract on the date and to the extent specified in the notice of termination;

2. Place no further orders or subcontracts for materials, services or facilities, except as may be necessary for completion of such portion of the work under the agreement as is not terminated;

3. Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the notice of termination;

4. Assign to the County in the manner, at the times, and to the extent directed by the engineer, all of the rights, title and interest of the Contractor under the orders and subcontracts so terminated, in which case the County shall have the right, at its discretion, to settle or pay any and all claims arising out of the termination of such orders or subcontracts;

5. Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the engineer, to the extent the engineer may require, which approval or ratification shall be final for all purposes;

6. Transfer title and deliver to the entity or entities designated by the County, in the manner, at the times, and to the extent, if any, directed by the engineer, and to the extent specifically produced or specifically acquired by the Contractor for the performance of such portion of the work as has been terminated:

(a) The fabricated or unfabricated parts, work, and progress, partially completed supplies, and equipment, materials, parts, tools, dyes, jigs, and other fixtures, completed work, supplies, and other material produced as a part of or acquired in connection with the performance of the work terminated by the notice of termination; and

(b) The completed or partially completed plans, drawings, information, and other property to the work.

7. Use its best efforts to sell in the manner, at the times, to the extent, and at the prices directed or authorized by the engineer, any property described in Section 6 of this paragraph, provided, however, that the Contractor shall not be required to extend credit to any buyer and further provided that the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the County to the Contractor pursuant to this agreement.

8. Complete performance of such part of the work as shall not have been terminated by the notice of termination; and

9. Take such action as may be necessary, or as the engineer may direct, for the protection and preservation of the property related to the agreement which is in the possession of

Gwinnett County, Georgia Page 23 the Contractor and in which the County has or may acquire an interest.

GC-45 RECORDS

The Contractor shall preserve and make available to the County all of its records, books, documents and other evidence bearing on the costs and expenses of the Contractor and any subcontractor pursuant to this agreement upon three days advance notice to the Contractor.

GC-46 DEDUCTIONS

In arriving at any amount due the Contractor pursuant to the terms of this…

This is the start of the file's text. The full file is on GovTribe.

Other files

File Type Posted
Award Information —
BL020-22 Addendum #1 —
Equipment Comparison Form —
Plans —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .