Bid_Specs_Rebid_Event_4245.pdf

PDF 19 MB Posted

Attached to
REBID-PW-(4) Pump Station 6 Medium Voltage Motor
Solicitation number
0000004245
Issued by
Hennepin County, Minnesota

About this file

This is a bid specification document for the City of Minneapolis Department of Public Works, prepared by Barr Engineering Co., for the procurement of medium voltage motor starters for Pump Station 6 (PS6). The project seeks to furnish four synchronous motor starters (two two-section motor control centers) designed to operate at 2400V, 3-phase, 60Hz with a continuous current rating of 600A minimum and a short-circuit rating of 25 kA RMS symmetrical. The equipment must comply with standards established by ANSI, IEEE, NEMA, UL, and NFPA 70, and must be installed by the Owner following delivery. Suppliers must submit initial review and approval submittals within eight weeks of contract execution, with approval expected within two weeks; resubmittals must be completed within three weeks. Equipment delivery is required on or before 60 weeks (420 days) after order acceptance. The supplier must provide on-site startup services, two four-hour training sessions, operation and maintenance manuals, asset registry documentation, spare parts registry, and a 24-month warranty from installation or 30 months from delivery, whichever occurs first.

Only prequalified manufacturers—Rockwell (Allen-Bradley) and Toshiba—are eligible to bid. The supplier must demonstrate a minimum of three similar projects in Minnesota and contiguous states within the past three years and maintain at least three full-time staff capable of providing service support within 24 hours. Invoicing follows a milestone-based schedule: up to 10 percent upon receipt of spare parts, up to 30 percent after submittal approval, up to 60 percent after equipment delivery and preliminary manuals, up to 80 percent after final manuals acceptance, and 100 percent after successful startup and training completion. The project site is located at 4100 Marshall Street NE, Fridley, Minnesota 55421, and is a secure site requiring badged access coordinated in advance with Minneapolis Water Works. The specification emphasizes compliance with the Minneapolis Public Works SCADA Standard Version 7.4, including specific tagging conventions, control philosophies, and protective relay settings for synchronous motor control with automatic power factor correction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4300 MarketPointe Drive, Suite 200

Minneapolis, MN 55435

952.832.2600 barr.com

Project Manual

Minneapolis Water Works – PS6 Starter Replacement

Starter Procurement Package MWW Specification No. 2507

Barr Project No. 23272104.00

Prepared for

City of Minneapolis

Department of Public Works

Minneapolis Water Works

Prepared by

Barr Engineering Co.

July 2026

Division 00

General

City of Minneapolis Table of Contents

Pump Station 6 Starter Replacement 00 01 10-1 Bid Documents

Project Manual

Minneapolis Water Works – PS6 Starter Replacement

City of Minneapolis – Department of Public Works

Starter Procurement Package

TABLE OF CONTENTS

Section Title

Division 00 General

00 01 05 Certification

00 01 10 Table of Contents

Division 01 General Requirements

01 11 00 Summary of Work

01 30 00 Requests for Information

01 33 00 Submittal Procedures

01 78 23 Operations and Maintenance Data

Division 26 Electrical

26 18 39 Medium Voltage Motor Control

Appendix A Minneapolis Public Works – SCADA Standard, Version 7.4

Appendix B PM Request Template

Drawings Synchronous Motor Starters One-Line Diagrams

Synchronous Motor Starters Typical Starter Wiring Schematic

END OF DOCUMENT 00 01 10

City of Minneapolis Certifications

Pump Station 6 Starter Replacement 00 01 05-1

Project Manual

PS6 Starter Replacement – Starter Procurement Package

City of Minneapolis – Department of Public Works

Water Treatment and Distribution Services

CERTIFICATION

I hereby certify that these Specifications were prepared by me or under my direct supervision and that I am a duly Licensed Professional Engineer under the laws of the State of Minnesota.

Mark Ziemer

License Number: 22509

Date: July 13, 2026

END OF DOCUMENT 00 01 05

Division 01

General Requirements

City of Minneapolis Summary of Work

Pump Station 6 Starter Replacement 01 11 00-1

SECTION 01 11 00

SUMMARY OF WORK

PART 1: GENERAL

1.01 CONTRACT DOCUMENTS

A. The Contract Documents are as defined in the Agreement, and generally consist of the Agreement, the Specifications, and the Drawings.

B. It is Supplier’s sole responsibility to thoroughly read and understand these Specifications and request written clarification regarding any portions that they find unclear.

1.02 DEFINITIONS

A. Owner shall be as defined as: City of Minneapolis, Public Works, Division of Water Treatment and Distribution Services, with whom Contractor has entered into the Agreement and for whom the Work is to be provided.

B. Engineer shall be as defined as: Barr Engineering Company, 4300 MarketPointe Drive, Suite 200, Minneapolis, Minnesota, 55435 (Phone: 952-832-2600; Fax: 952-832-2601).

C. Supplier shall be defined as: The company or entity furnishing the equipment, materials, and services in full conformance with the Contract Documents.

1.03 SCOPE OF CONTRACT DOCUMENTS

A. Furnish equipment and materials and provide services as required for the Pump Station 6 (PS6) starter replacement. Such equipment, materials, and services are as defined in the accompanying Specifications and Drawings.

1.04 WORK BY OWNER

A. Owner will perform the following tasks related to the Work:

1. Owner will install the equipment purchased as part of this procurement.

PART 2: PRODUCTS (NOT USED)

PART 3: EXECUTION (NOT USED)

END OF SECTION 01 11 00

City of Minneapolis Requests for Information

Pump Station 6 Starter Replacement 01 30 00-1

SECTION 01 30 00

REQUESTS FOR INFORMATION

PART 1: GENERAL

1.01 DESCRIPTION OF REQUIREMENTS

A. This Section specifies the general methods and requirements of Requests for Information (RFIs).

1.02 REQUESTS FOR INFORMATION

A. When the Manufacturer believes that additional information or clarification of the Contract Documents is necessary, they may initiate a Request for Information (RFI).

B. RFIs may relate to administrative or technical matters. Although response to an RFI may lead to a change in the contract scope, cost, or time, RFIs are not a substitute for documentation requirements of such stipulated in the Contract Documents.

C. A response to an RFI may authorize minor changes to the Contract consistent with the terms of the Contract Documents related to the responsibilities and limitations of authority of the Engineer.

D. A response to an RFI is not an authorization to perform any additional work or modifications that would require a cost change or written amendment to the Contract.

E. RFIs are not a substitute for the Submittals process specified elsewhere in these Specifications.

PART 2: PRODUCTS [NOT USED]

PART 3: EXECUTION

3.01 ORIGINATION

A. The Supplier/Manufacturer shall originate RFIs using a form mutually agreed upon with the Owner and Engineer.

1. RFIs shall be numbered consecutively. In the event that an answered RFI results in a follow-up inquiry on the same item, the follow-up RFI shall maintain the same number as the original, appended with a suffix.

2. Include portions of Specifications, Drawings, or details for which the information is requested.

3. Attach drawings, sketches, photographs or other relevant information.

4. If the question concerns an interpretation of the Contract Documents, enter the Supplier/Manufacturer’s interpretation for review and response by the Engineer.

5. Indicate the date by which a reply is requested.

6. Sign the request portion of the form.

B. Supplier/Manufacturer shall maintain a log of all RFIs including the number, the date originated, date delivered, and date answered.

3.02 PROCESSING

A. Supplier/Manufacturer shall submit all RFIs to Engineer for processing.

B. Technical RFIs will generally be reviewed and answered by Engineer.

City of Minneapolis Requests for Information

Pump Station 6 Starter Replacement 01 30 00-2

C. Administrative RFIs will generally be reviewed and answered by the Engineer in consultation with the Owner.

D. The Engineer will generally respond to RFIs within five calendar days of receipt, depending on the complexity of the inquiry.

3.03 RESPONSES

A. If the RFI contains sufficient clarity, the Engineer will insert a response in the lower portion of the RFI form, sign and date the response, and return the completed form to the Manufacturer.

B. If the RFI does not contain sufficient clarity, the Engineer may request additional information from the Manufacturer.

C. Engineer will distribute copies to the Owner and project files.

D. Engineer will maintain a log of all RFIs including the date received and the date returned to the Manufacturer.

3.04 RECORD INFORMATION

A. Supplier/Manufacturer shall include all clarifications obtained through the RFI process into the record documentation specified elsewhere in these Specifications.

END OF SECTION 01 30 00

City of Minneapolis Submittal Procedures

Pump Station 6 Starter Replacement 01 33 00-1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1: GENERAL

1.01 SUMMARY

A. Section includes:

1. Submittal procedures

2. Shop Drawings

3. Schedule of Submittals

B. Related Sections

1. Section 01 78 23 - Operations and Maintenance Data

2. Section 26 18 39 – Medium Voltage Motor Control

1.02 SUPPLIER/MANUFACTURER’S RESPONSIBILITIES

A. Make submittals as identified herein and elsewhere in these Specifications. Clearly identify all submittals as follows:

1. Date of submission

2. Owner’s project number

3. Project name

4. Manufacturer identification

a. Manufacturer

b. Supplier

c. Manufacturer or supplier representative

5. Identification of the project

6. Reference to Contract drawing(s)

7. Reference to specification section number

8. Reference to applicable standards, such as ASTM or NEMA

9. Indication of Supplier and/or Manufacturer’s approval

10. Identification of deviation from Contract Documents, if any.

11. Reference to previous submittal (for resubmittals)

B. Submittals shall be clear and legible, with text font of sufficient size for clarity of the presented data, and with features and options clearly identified.

1.03 ENGINEER’S RESPONSIBILITIES

A. Engineer will review submittals with reasonable promptness, up to 14 days from receipt of such submittals.

B. If, in the opinion of the Engineer, a submittal is incomplete, that submittal will be returned to the Manufacturer for completion. Such submittals may be returned with comments indicating the deficiencies requiring corrective action.

Pump Station 6 Starter Replacement 01 33 00-2

C. Review of technical submittals will be for general conformance with the design concept and Contract Documents. They shall not be construed to:

1. Permit any departure from the Contract Documents

2. Relieve the Supplier/Manufacturer of responsibility for any errors or omissions in the submittal or the equipment.

3. Approve departures from details furnished by the Engineer, except as otherwise provided for by Engineer in writing.

1.04 SUBMITTAL PROCEDURES

A. Schedule submittals to expedite the project and deliver to the appropriate office of Engineer.

Coordinate submission of related items.

B. Transmit each submittal with a cover letter or form, referencing the project, supplier, pertinent drawing sheet(s), detail number(s) and specification section number, as appropriate.

C. Electronic files will be acceptable, transmitted via email. If file size exceeds capacity of email server, coordinate with Owner for uploading to Owner’s SharePoint site. Discuss the document distribution pathways with Owner and Engineer.

D. Apply Supplier's stamp, signed or initialed certifying that review, verification of products required, field dimensions, and coordination of information, is in accordance with the requirements of the Contract Documents.

E. Identify variations from Contract Documents and product or system limitations, which may be detrimental to successful performance of the completed work.

F. Provide space for Engineer review stamp.

G. Revise and resubmit submittals as required. Identify all changes made since previous submittal.

H. Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report any inability to comply with provisions.

1.05 SCHEDULE OF OPERATIONS

A. Not more than two weeks after Contract award, submit a tabulated schedule showing proposed date(s) for submittal(s), and review time period(s).

B. Provide a time allowance should the first submittal be returned with a resubmittal requirement.

C. Show completed equipment delivery date(s).

1.06 SUBMITTAL OF SHOP DRAWINGS

A. Submit with such promptness as to cause no delay to the work, all shop drawings and schedules required for the work. Engineer will review them with reasonable promptness.

Contractor shall make any corrections required by Engineer and, if so required, resubmit them for review.

B. If the Shop Drawing includes any features or conditions different from the specification, then the manufacturer or Contractor shall include an explanation of the differences and purpose of the changes in a letter near the first page of the submittal.

C. Engineer's approval of such drawings or schedules shall not relieve Supplier/Manufacturer from responsibility for deviations from drawings or specifications, unless they have in writing called Engineer's attention to such deviations at the time of submission, nor shall it relieve them from responsibility for errors in shop drawings or schedules.

D. Resubmittals shall include a memo near the first page confirming changes made and answering any questions raised in the earlier reviews.

Pump Station 6 Starter Replacement 01 33 00-3

E. Provide Electronic Submittals which comply with the following format conditions.

1. Each submittal shall be an electronic file in Adobe Acrobat Portable Document Format (PDF). Document shall be readable by at least the most recent three versions of Adobe Acrobat Reader.

2. Electronic files that contain more than 15 pages in PDF format shall contain internal bookmarking.

3. PDF files shall be set up to print legibly at 8.5-inch by 11-inch, 11-inch by 17-inch, (or 22-inch by 34-inch with prior approval from Owner or Engineer).

4. Submit new, complete electronic files for each resubmittal.

5. Use the following file name format for submittals:

a. Example: _ 432113_01_A_Centrifugal_Pumps.pdf

b. Where:

1) 432113_ - is the specification section number (without spaces if 49 division format). Include an underscore after the section number. If the item is shown on the drawings, but has no directly related specification section, use the low-level number in the most similar division, such as 05 00 00_ for metal work.

2) 01_A_ - is the submittal number within that specification section, and the first version. Include an underscore after the number.

a) Use 2 digits only.

b) Use 01_B_ for resubmittal (then 01_C_, etc.).

3) Centrifugal_Pumps.pdf is a short description. Generally limit file names to about 35 characters or less. Common abbreviations are acceptable and recommended. Underscores between words are preferred.

c. Combine all related pages into each individual Shop Drawing File.

F. Submit factory pump performance testing results as specified. File name should resemble 432113_02_A_Centrifugal_Pump_Curve.pdf

G. Engineer review response for electronic submittals will be summarized in a Memorandum near the first page of the returned file. The comments may or may not be repeated on the related pages within the Shop Drawing.

1.07 SHOP DRAWING CONTENT - EQUIPMENT

A. Shop Drawings shall clearly show configuration, dimensions, and materials of the components of the equipment, accessories, options to be provided, and spare parts. Shop drawings shall be specific to this project and shall be so noted and referenced to the particular piece of equipment and respective process system.

B. Submit preliminary manufacturer's operation and maintenance instructions specific to proposed equipment with the Shop Drawings, to assist in the complete review of the equipment.

1.08 SHOP DRAWING FORMAT FOR MINNEAPOLIS WATER DIVISION

A. All custom shop drawings prepared by an equipment manufacturer or Control System Integrator must follow Minneapolis Water Division (Owner) standards and format. More extensive definitions of the standards will be distributed to successful proposers.

1. All drawings must be formatted to fit Owner title block and borders. Electronic title block and border files will be provided by Owner for companies under contract to do work.

Shop drawings and other preliminary drawings may be submitted using a company's

Pump Station 6 Starter Replacement 01 33 00-4 standard title blocks or Owner title blocks. Final submitted drawings must use Owner title block and sheet border (22 by 34 inches, with title block across bottom).

2. All drawings will include sheet numbering in Owner file system. Cross-referencing between sheets must use Owner sheet numbering system. If the company has their own standard sheet numbering system, those numbers may be used in addition to Owner system.

3. The only exception to the drawing standards will be allowed for equipment that is mass-produced, and commonly can be a "shelf-stocked" item.

B. All projects will have a meeting before drawings are prepared. Each company that will prepare drawings should bring examples of previous drawings. Owner will also bring examples.

Separate meetings will be required for the following types of drawings.

1. Process and Instrumentation Diagram (P&ID)

a. A detailed tagging system has been developed for all components that will be shown on P&IDs as well as other drawings. The tagging method must be used in PLC and SCADA programming.

2. Mechanical, Process, Structural Drawings

a. Cross Section and Detail referencing will follow Owner standards.

3. Electrical Schematic Drawings

a. Owner uses a "Row and Column" drawing format, which is one of the formats developed by the ISA (The Instrumentation, Systems, and Automation Society).

b. All devices and wires on every electrical schematic must be numbered to allow direct referencing back to the specifically related ladder rung on the schematic and the Panel (or PLC) number.

c. The schematic column arrangement will follow Owner standards. PLC diagrams will have similar column numbers for every PLC.

C. All final drawings must be submitted to Owner electronically in a CAD format, using a current version of "MicroStation" by Bentley Systems, Inc. Some AutoCAD versions may be accepted, provided the current version of MicroStation can easily and accurately import from that format.

1.09 EXCESSIVE SHOP DRAWING REVIEWS

A. In accordance with the Articles above, Supplier/Manufacturer is responsible for furnishing shop drawings for review by Engineer. Engineer has deemed that a maximum of two submittals will be reviewed for any one product for any given section under the Contract.

B. Should a third or subsequent reviews be necessary:

1. Owner will compensate Engineer for such additional services.

2. Owner will deduct the amount of such compensation from the payment to Supplier.

C. Compensation to Engineer shall be a normal billing rates plus reimbursable expenses at cost.

1.10 SCHEDULES OF TEST REPORTS

A. All testing shall be accomplished by qualified technicians. If samples area analyzed at an off-site laboratory, use local firms, and follow industry standard protocols for sampling, preservation, and transportation.

B. Test reports shall include clear information about the location and date and time of testing.

C. Electronic files should use file naming coordinated with the naming conventions described for Shop Drawings.

Pump Station 6 Starter Replacement 01 33 00-5

D. Submit all test reports to the Engineer for submission to the Owner in a timely manner that does not hinder work. In general, submit reports within 7 calendar days of the test.

1.11 SCHEDULES OF SUBMITTALS

A. Contractor shall submit the following items to Engineer for review and approval. Also, see the specific section of the Specification for detail requirements.

B. During process of work

1. Shop Drawings

2. Operation & Maintenance (O&M) Instructions

3. Test Results

PART 2: PRODUCTS [NOT USED]

PART 3: EXECUTION [NOT USED]

END OF SECTION 01 33 00

City of Minneapolis Operations and Maintenance Data

Pump Station 6 Starter Replacement 01 78 23-1

SECTION 01 78 23

OPERATIONS AND MAINTENANCE DATA

PART 1: GENERAL

1.01 SUMMARY

A. Section describes the content requirements and submittal procedures for equipment Operation & Maintenance manuals.

1.02 RELATED SECTIONS

A. Section 01 33 00 - Submittal Procedures

1.03 SUBMITTAL SCHEDULE

A. Submit one electronic file of the preliminary operating and maintenance (O&M) instructions with shop drawings for review. Resubmit revised preliminary manuals with corrections and additional requested information prior to shipment of equipment.

B. Submit Asset Registry prior to start-up of the equipment.

C. Submit three (3) final copies and one electronic file of the final operating and maintenance instructions covering all equipment and systems furnished prior to starting operation of the equipment.

D. Submit Spare Parts Registry prior to starting operation of the equipment.

E. If significant changes are made during start-up and testing, submit revised manuals within 30 days of start-up.

F. After Final paper copies are accepted, submit the final electronic files, named as described in a following article.

1.04 ASSET REGISTRY

A. Submit Asset Registry for all equipment components and systems purchased for and installed on the project with an initial value exceeding $5,000, all water quality instruments, and any items that require regularly scheduled maintenance for entry into Owner's capital asset database. The registry shall be completed in a Microsoft Excel spreadsheet and submitted in electronic version.

B. Asset Registry shall include the following information in separate columns:

1. Asset Number

2. Asset Name

3. Asset Attributes:

a. Manufacturer,

b. Serial Number,

c. horsepower,

d. capacity,

e. other significant attributes, depending on equipment type.

4. Asset Purchase Cost

5. Date Asset Placed in Service

Pump Station 6 Starter Replacement 01 78 23-2

6. Estimated Life

7. Asset Replacement Cost

8. Warranty Start Date

9. Warranty End Date

1.05 SPARE PARTS REGISTRY

A. Submit Spare Parts registry for all maintenance materials and spare parts for equipment provided on the project for entry into Owner’s inventory management system. Include data or parts provided with the project as well as manufacturer-recommended preventative maintenance items. The registry shall be completed in a Microsoft Excel spreadsheet and submitted in both paper copy and electronic version.

B. Spare Parts Registry shall include the following information in separate columns:

1. Asset Number and Asset Name for which part is used

2. Part identification

3. Part description

4. Part number / model number / catalog number from Supplier

5. Part number / model number / catalog number from original equipment manufacturer

6. Vendor/Supplier Name

7. Part number/Catalog number (and referenced catalog edition)

8. Unit price

9. Vendor/Supplier internet website address

10. Vendor/Supplier mailing address

11. Vendor/Supplier phone number

12. Vendor/Supplier internet website address

13. Quantity recommended per asset

14. Quantity provided under contract

15. Date part(s) received by Owner

1.06 OPERATION AND MAINTENANCE (O&M) INSTRUCTIONS

A. Operating instructions shall be prepared specifically for each system or type of equipment installed under this contract and shall consider the specific equipment and controls included.

Instructions shall be complete for each separate system covering:

1. Equipment functions, normal operating characteristics, and limiting conditions.

2. Assembly, installation, alignment, adjustment, and checking instructions.

3. Operating instructions for start-up routine and normal operation, regulation and control, shutdown, seasonal variations, special conditions, and emergency conditions.

4. Maintenance instructions and schedules including lubrications, disassembly, repair, and reassembly instructions.

5. Adjustment, alignment, and balancing instructions.

6. Guide to Troubleshooting.

7. Parts lists, and predicted life of parts subject to wear.

Pump Station 6 Starter Replacement 01 78 23-3

8. Outlines, cross-sections, assembly drawings, engineering data, and wiring diagrams.

9. Testing results, performance curves, and balancing reports where applicable.

10. Any other information that is necessary for instruction in the proper operation and maintenance of the equipment.

B. Remove or cross-out all text, tables, references, pictures, and diagrams describing options and components that have not been included as part of the furnished equipment and systems.

C. Include a Table of Contents that clearly shows the arrangement of the information.

D. Include a completed "MAINTENANCE SUMMARY" as a page near the first page of the preliminary and final O&M Manual. This summary should compile all recommended maintenance tasks for the equipment.

E. Final paper copies shall be printed on 20-pound white paper that is punched for mounting in standard 3-ring binders and has a reinforcing strip along the bound edge of every sheet.

Manufacturers printed manuals may be acceptable if punched similarly and non-applicable information is permanently crossed out within the pages of every manual.

F. Final paper copies shall be bound in standard 3-ring binders that allow a front title page and spine title strip. All binders shall be intended for 8.5-inch by 11-inch pages, with a thickness to allow reasonable use. Pages 11-inch by 17-inch shall be folded with the page title visible.

Larger sheets shall be folded to fit into a heavy-duty clear pocket sheet title visible.

G. Include heavy-duty tabs between topics or chapters in the manuals.

H. Front title and spine title shall be placed behind a clear sheet and have the following information at a minimum.

1. "Operating and Maintenance Instructions"

2. Name of project

3. Subject matter covered in the manual (specification section title or more precise)

4. Specification Section number

5. Year of completion

I. Include a binder for every specification section that requires a manual. In cases with limited number of pages, (e.g., plumbing fixtures with less than 1/4-inch thick), verify with Owner before combining multiple sections from a specification division in a single binder. Do not combine sections from different disciplines in a single binder.

1.07 ELECTRONIC OPERATION & MAINTENANCE MANUALS

A. Submit Preliminary and Final Operation & Maintenance (O&M) manuals in a "text searchable" Portable Document Format (_.pdf), compatible with Adobe Acrobat®. Format shall be compatible with the current version of Adobe Acrobat Reader and at least three previous major revisions.

B. Electronic files shall be an exact match with paper copies, including organization, formatting, and bookmarking.

C. Create one PDF document (_.pdf file) for each type of equipment or system. Direct conversion from the native editable document is strongly recommended (i.e. convert from Word or CAD software directly into PDF.) to ensure the accuracy of the text. Optical character recognition (OCR) may be accepted as long as it is confirmed accurate.

D. Drawings and graphics must be an integral part of the PDF document. All pages must be rotated for clear reading on a computer monitor. Graphic resolution must be adequate to allow the image to be clear on screen (including zooming in) and for printing.

Pump Station 6 Starter Replacement 01 78 23-4

E. Create "Bookmarks" in the file for each major section or idea in the Table of Contents. Structure of the bookmarks must promote efficient navigation within the document.

1. Use an outline structure 1 to 3 levels deep, depending on document size.

2. Bookmark names should describe the information contained and must be unique in the left part of the title (so bookmark panel in the Reader can be narrow). Include short numbering if used in the document, but limit the length (e.g., in lieu of "Chapter 3 -" use "3 -"). Include the section title in words along with the numbering.

3. Do not include redundant information in the bookmark names, such as the specification section number.

4. If drawing numbers are not text searchable, then include a bookmark to navigate to every drawing. If drawing Titles are not text searchable, then include the Title in the bookmark with the drawing number.

F. Set the initial (opening) view of PDF files as follows:

1. Page Layout: Single Page

2. Zoom: Full Page

3. Bookmarks: navigation frame open for documents over 15 pages, closed for shorted files.

G. In tables showing multiple options, highlight the item provided or cross-out non-applicable information. Cross-out figures and other items showing features that have not been provided on the project.

1. To make such markings, preferred method is in the native format document, prior to translation to PDF file.

2. Markings using Acrobat Professional editing tools will also be accepted with prior approval from the project manager.

H. Filenames shall use the convention XXXXXX_POM_Name.pdf or XXXXXX_OM_Name.pdf, where XXXXXX is the specification section number and "Name" is a very short description. Use underscore characters in lieu of spaces.

1. Example: 402724_POM_Plug_Valves.pdf - for preliminary review copy

2. Example: 402724_POM2_Plug_Valves.pdf - for resubmittal of preliminary review copy

3. Example: 402724_OM_Plug_Valves.pdf - for Final copy

PART 2: PRODUCTS [NOT USED]

PART 3: EXECUTION

3.01 MANUFACTURER TRAINING FOR OWNER EMPLOYEES

A. Before plant startup, equipment manufacturers shall train Owner's designated personnel in the operation, adjustment, and maintenance of products, equipment and systems. Training shall be provided both in the classroom and in the field, at the equipment or system.

B. Session shall be coordinated with Owner at times convenient for Owner employees. In general, plan for two (2) matching training sessions for each equipment item or system, to accommodate various working shifts.

C. Submit a detailed lesson plan at least two weeks prior to the schedule for training session.

Lesson plans shall include an in-depth outline of the training material, a table of contents, resume of the instructor, concepts to be covered, all operational procedures, maintenance requirements, safety considerations, and recommended spare parts.

Pump Station 6 Starter Replacement 01 78 23-5

3.02 VIDEO RECORDING OF TRAINING

A. One of each training sessions shall be recorded using professional quality video and audio equipment, and submitted for quality control review before Substantial Completion. Submit files in *.mpg4 format. Use multiple files for longer training sessions, with each file containing no more than one hour of the session.

B. Video size shall be 720 lines (720p, 1280x720 or 960x720) or 480 lines (480p, 853x480 or 640x480). Aspect Ratio (horizontal:vertical) shall be 16:9 or 4:3. Video speed shall be 30 fps minimum.

C. Filenames shall use the convention XXXXXX_TRAINx_Name.mp4, where XXXXXX is the specification section number (matching O&M Manual file) and "Name" is a very short description (matching O&M Manual file). Use underscore characters in lieu of spaces. If multiple files are used for a specific equipment item, used TRAIN1, TRAIN2, etc. The numeral is not required if a single file is submitted.

D. Audio shall be recorded using a microphone placed near the presenter, to allow clear audio recording.

E. If the video or audio is considered by Engineer or Owner to be of poor quality, then Contractor will be required to edit or re-do the recording.

F. If audio recording of the training near the equipment is difficult, then Contractor shall submit a text document (*.doc and *pdf) with the full word-for-word transcript of the session.

END SECTION 01 78 23

ATTACHMENTS:

Section 01 78 23 Supplement 1 - Maintenance Summary Form

Division 26

Electrical

City of Minneapolis Medium Voltage Motor Control

Pump Station 6 Starter Replacement 26 18 39 -1

26 18 39

MEDIUM VOLTAGE MOTOR CONTROL

PART 1: GENERAL

1.01 SCOPE

A. The Supplier shall furnish equipment as specified herein and as shown on the Contract Drawings.

B. The Contract Drawings and this Specification are complimentary. Items that are required on either or both of the Contract Drawings and Specification shall be included.

C. The equipment consists of quantity two - two-section synchronous motor starter motor control centers (MCC) as specified herein and on Drawings BE10699-001 and BE10699-002 (a total of four synchronous motor starters).

D. The scope also includes testing, inspection, post-installation startup, training, and warranty as specified herein.

E. The equipment will be installed by Owner.

1.02 REFERENCES

A. The metal-clad switchgear and all components shall be designed, manufactured and tested in accordance with the latest applicable standards of:

1. American National Standards Institute (ANSI).

2. Institute of Electrical & Electronic Engineers (IEEE) (IEEE C37.20.7, Guide for Testing Arc Resistant Medium Voltage Switchgear).

3. National Electrical Manufacturers Association (NEMA) “Medium Voltage Controllers Rated 1501 to 7200V AC ICS 3-2 (formerly ICS 2-324)”.

4. Underwriters Laboratories, Inc. (UL) (High Voltage Industrial Control Equipment 347).

5. National Fire Protection Association NFPA 70 - ”National Electrical Code” (NEC), latest edition.

6. Occupational Safety & Health Act (OSHA).

B. Completed assemblies shall bear applicable UL labels.

C. For informational purposes: Refer to “Appendix A” of this manual for Minneapolis Public Works

– SCADA Standard, Version 7.4

1. Tagging and naming conventions.

2. Note that the control signal for remote start-stop of each starter from the plant control system is 24VDC.

1.03 SUBMITTALS – FOR REVIEW/APPROVAL

A. Submit electronic (.PDF) copies of the following materials in accordance with Section 01 33 00 to the Engineer for approval:

1. Master drawing index

2. Front view elevation with dimensions

3. Floor plan with dimensions

4. Top view with dimensions

Pump Station 6 Starter Replacement 26 18 39 -2

5. Single line diagram

6. Complete schematic diagrams for each cubicle, showing all components, terminals, terminal numbering, wiring and wire numbering.

7. Nameplate schedule and nameplate details

8. Component list

9. Conduit entry/exit locations

10. Assembly ratings including:

a. Short-circuit rating

b. Voltage

c. Continuous current

d. Basic impulse level for equipment over 600 volts

11. Major component ratings including:

a. Voltage

b. Continuous current

c. Interrupting ratings

12. Cable terminal sizes

13. Product data sheets for all products. Where the product data sheet describes multiple products, the specific units shall be highlighted throughout.

B. Make submittals in electronic form to:

1. marshall.hilgemann@minneapolismn.gov

2. mziemer@barr.com

1.04 SUBMITTALS – FOR CONSTRUCTION

A. Submit electronic (.PDF) copies of the following materials to the Engineer for record purposes:

1. Final as-built drawings and information for items listed in Paragraph 1.03 and shall incorporate all changes made during the manufacturing process.

2. Certified production test reports, including operational testing of completed assemblies.

3. Certified test reports for voltage transformers (VTs) and current transformers (CTs).

4. Installation information including equipment anchorage provisions

1.05 SUBMITTALS – FINAL DOCUMENTATION AND OPERATION AND MAINTENANCE DATA

A. Submit electronic (.PDF) copies of the project drawing set. This set constitutes the Manufacturer’s Record Drawings of the equipment as-built including all revisions made necessary from submittal reviews, design modifications (if any), requests for information, and details not indicated on the original Contract Documents but necessary for detailing all aspects of the equipment.

B. Submit Microstation-compatible (.DXF or .DGN) electronic files of all project drawings.

Alternatively, electronic drawing files may be submitted in AutoCAD format. These drawings shall become Owner’s property for use in ongoing documentation and support of the project equipment.

C. Submit four (4) hardcopies and one (1) electronic (.PDF) copy of equipment operation and maintenance manuals, and shall include record drawings, instruction leaflets and instruction mailto:marshall.hilgemann@minneapolismn.gov mailto:mziemer@barr.com

Pump Station 6 Starter Replacement 26 18 39 -3 bulletins for the complete assembly and each major component. All .PDF files must have bookmarks for each major section, linked to the table of contents.

D. Submit final electronic application files for all protective relays, to document settings at project completion.

E. The Manufacturer’s user manual, including user manuals from all third party components.

F. List of recommended spare parts, part numbers, address and contact information for suppliers.

G. Documentation of all factory test results performed as outlined in Part 3 of this specification.

H. Documentation recording the results of the physical inspection performed as outlined in Part 3 of this specification.

I. Supplier shall identify all periodic maintenance tasks that are recommended for all equipment supplied under this Section. Supplier shall complete a “PM Request” form for each task, based on the “PM Request Template” included as an attachment to this Section. Submit completed forms in Adobe (.PDF) and Word (.DOC) format.

1.06 QUALIFICATIONS

A. Supplier shall be regularly engaged in the design, assembly, and support of medium-voltage motor control, protective relaying, automation, and related services.

B. Supplier shall have a minimum of three (3) similar or larger projects in Minnesota and contiguous States within the last three (3) years.

C. Supplier shall demonstrate direct project experience with medium voltage motor starters for brush-type synchronous motors, including automatic power factor correction and development of protective settings for such equipment.

D. Supplier shall have a minimum of three (3) full-time staff that can provide ongoing service and support on the equipment furnished within a maximum period of 24 hours after notice.

E. Only prequalified Manufacturers will be considered for this project, due to standardization of parts and maintenance requirements. Prequalified Manufacturers are:

1. Rockwell (Allen-Bradley).

2. Toshiba.

F. The listing of a Manufacturer as “prequalified” does not release the Manufacturer from any requirements of the Drawings and Specifications. Named Manufacturers shall modify their standard product, if required to meet the Specification, and shall comply with the dimensional limits provided in this Section.

1.07 QUALITY CONTROL

A. The Manufacturer shall request clarification from Engineer should Manufacturer’s instructions conflict with the Contract Documents.

B. The Manufacturer shall comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicated higher standards or more precise workmanship.

C. Work shall be performed by persons qualified to produce workmanship of specified quality.

D. Provide documentation recording the results of factory testing performed as outlined in Part 3 of this specification.

E. Provide documentation recording the results of the physical inspection performed as outlined in Part 3 of this specification.

Pump Station 6 Starter Replacement 26 18 39 -4

1.08 DELIVERY, STORAGE AND HANDLING

A. Equipment shall be handled and stored in accordance with the Manufacturer’s instructions. At all times, the equipment shall be kept within clean and dry conditions.

B. Supplier shall ship the units to the project site and shall fully insure the equipment during shipment.

C. Equipment shall be delivered on a flat-bed truck suitable for off-loading by Owner. Coordinate off-loading details with Owner.

D. The site is a secure site, and badged access is required. Coordinate with Minneapolis Water Works prior to delivery.

E. Deliver equipment to this address:

4100. Marshall St. NE Fridley, MN 55421

1.09 INVOICING

A. Each invoice shall include the Minneapolis purchase order number.

B. Submit invoices according to the following schedule:

1. Not more than 10% of the total contract amount upon receipt of spare parts.

2. Not more than 30% of the total contract amount after submittals have been approved.

3. Not more than 60% of the total contract amount after equipment has been delivered and preliminary O&M Manuals have been submitted, including asset management data and spare parts registry.

4. Not more than 80% of the total contract amount after final O&M Manuals have been accepted, including asset management data and spare parts registry.

5. Invoice for 100% of the total contract amount after successful startup, commissioning, and training is complete, and all specified deliverables and documents have been provided.

C. Email invoices to: submitinvoices@minneapolismn.gov, And CC to: marshall.hilgemann@minneapolismn.gov, mziemer@barr.com

1.10 SCHEDULE

A. Supplier to make delivery of equipment on or prior to 60 weeks (420 days) after order acceptance by City of Minneapolis.. This timeframe is predicated on the understanding that the initial review/approval submittals will be made within eight (8) weeks of executed contract date, to be returned to the supplier within two (2) weeks after receipt. In the event that a resubmittal is required, it shall be made within three (3) weeks, to be returned to the supplier within two (2) weeks after receipt.

PART 2: PRODUCTS

2.01 RATINGS

A. Voltage

1. The controller shall accept nominal plant power of 2400V, 3-phase at 60Hz.

2. The supply input voltage tolerance shall be plus or minus 10 percent of nominal line voltage.

3. The supply frequency tolerance shall be plus or minus 3 percent.

mailto:submitinvoices@minneapolismn.gov mailto:marshall.hilgemann@minneapolismn.gov mailto:mziemer@barr.com

Pump Station 6 Starter Replacement 26 18 39 -5

B. Environmental Ratings

1. Storage ambient temperature range: -20°C to 75°C (-4 to 149°F).

2. Operating ambient temperature range: 0°C to 40°C (32 to 104°F) without derating.

3. The relative humidity range is 0% to 95% non-condensing.

4. Operating elevation: up to 1,000 Meters (3,300 ft) without derating.

2.02 STRUCTURE

A. The structure shall consist of a metal enclosed free-standing dead-front vertical steel assembly.

B. The structure shall also have a structurally sound lifting means and lifting equipment engagement points for ease of installation.

C. The controller(s) shall be designed for front access to allow for installation with no rear access.

Equipment that requires rear or side access for installation shall not be accepted.

D. Enclosure

1. Controller enclosures shall be NEMA Type 1.

2. The enclosure shall be properly sized to dissipate the heat generated by the controller at its full ratings within the limits of the specified environmental operating conditions.

3. LV door latches shall be heavy-duty ¼-turn type units.

4. Medium Voltage doors shall be held closed using 3/8" bolts.

5. All back plates shall be removable.

6. Provide Fluke infrared measurement window positioned to take IR measurements of the incoming main lugs and contactor terminations without opening enclosure

7. Available space in existing electrical room consists of a total width of approximately 20 feet, 8 inches. Coordinate equipment dimensions with Owner as necessary to fit available space.

E. Structure Finish

1. All exterior metal parts (except for low voltage panel and power cell back plates) shall be painted with hybrid epoxy powder paint ANSI 49 medium light gray or manufacturer’s standard color.

2. All mounting plates in the power cell and low voltage compartments shall be painted high gloss white for enhanced visibility.

3. Painting shall be done on a continuous paint line through air-atomized electrostatic spray.

All parts shall be painted before assembly.

4. The preparation shall be Alkaline wash/rinse; iron phosphate rinse; iron-chrome sealer rinse; re-circulated de-ionized water rinse and virgin deionized water rinse.

5. Total paint thickness – 0.002" (0.051 mm) minimum.

6. Baking process shall be by Natural gas oven at 179°C (355°F) minimum.

7. All unpainted steel parts shall be plated with a zinc plate/bronze chromate process for corrosion resistance.

F. Nameplates

1. Provide master nameplate for controller.

2. Provide unit nameplates.

3. Provide legend plates for all pilot devices.

Pump Station 6 Starter Replacement 26 18 39 -6

4. Nameplates plates shall be engraved phenolic with black background and white lettering.

5. Exact nameplate details, sizes and inscriptions shall be determined during the shop drawing process.

2.03 POWER AND GROUND BUS

A. Bus Bracing

1. The horizontal/vertical buswork and the cabling/bus in the main power cell(s) shall be braced and tested in accordance with NEMA ICS 3-2 and UL 347.

2. The bus work and cabling shall be braced to withstand the let-through energy allowed by the largest fuse during a short circuit fault.

3. The horizontal bus fault withstand current rating shall be 25 kA RMS symmetrical for 10 cycles, minimum.

4. The vertical bus fault withstand current rating shall be 25 kA RMS symmetrical for one half cycle.

B. Horizontal Bus

1. The main horizontal power bus shall be located in the center, at the back of the structure, to provide optimum heat distribution, ease of maintenance and splicing. Each main horizontal bus shall power two (2) starters, as indicated on the one-line.

2. In advance of each main bus provide a multimeter as indicated on the one-line diagram;

GE Vernova EPM7000 (Part No. PL7000-XXXXXX-6-5A-C-HI-E1-X, no substitutions.

3. To provide better short-circuit withstand ability and to protect against the accumulation of dust and tracking between phases, the power bus shall be mounted on edge to a molded bus support insulator in a common vertical plane.

4. The power bus shall be made of tin-plated copper and shall have a minimum continuous current rating of 600A. The main power bus will be non-insulated.

5. Access plates shall be provided to the bus compartment from the front or the rear of the structure to allow for installation and regular maintenance of the power and ground bus splice connections.

6. The horizontal buswork, the cabling/bus from the main power cell shall be braced and tested in accordance with NEMA ICS 3-2 and UL 347 (paragraph 30).

C. Vertical Bus

1. Provide vertical power bus risers from the main horizontal power bus to the isolating switch line terminals.

2. The vertical risers shall be tin-plated copper.

3. Cabling from the main horizontal power bus to the isolating switch is not acceptable.

D. Ground Bus

1. A continuous copper ground bus shall be provided along the entire length of the controller line-up.

2. A mechanical lug for #8 to #1/0 AWG or #6 to 250 MCM cable shall be supplied at the incoming end of the line-up.

3. The ground bus shall be 1/4" x 2", bare copper.

Pump Station 6 Starter Replacement 26 18 39 -7

2.04 ACROSS-THE-LINE CONTROLLER

A. Provide the quantity of across-the-line motor starters and/or transformer feeders, as indicated on the Drawings.

B. The structure shall be divided isolated compartments

1. Main power bus and ground bus compartment

2. Power cell compartment

3. Low Voltage compartment

C. Power Cell Compartment

1. Main Isolating Switch

a. The main power cell shall have an externally-operated, 3-pole, gang operated, fixed mounted non-load-break isolating switch.

b. The isolating switch shall isolate the power bus compartment from the power cell by means of a positively driven shutter mechanism to prevent accidental contact with line terminals in the power bus compartment.

c. The main power cell door shall have a viewing window through which the operator can verify the isolating switch position.

d. The isolating switch shall only have the ability to interrupt the no-load (magnetizing) current of the control power transformer(s) (CPT) and/or potential transformers (PT) supplied inside the controller power cell.

e. In the open position, the isolating switch and contactor shall provide a means of grounding appropriate medium voltage power cell components, bleeding off hazardous stored energy, thus providing safe operation and maintenance.

f. One or more N-O and N-C auxiliary contacts shall be arranged to open the secondary circuit of the CPT and/or PT, de-energizing the control circuit. This is to ensure there is no load on the isolating switch when it is opened or closed. The contacts shall also prevent backfeeding through the CPT and/or PT and isolate the power cell when the control circuit is in the TEST mode. It shall only be possible to operate the TEST control circuit when the isolating switch is in the open position.

The auxiliary contacts shall have a NEMA contact rating of 2 x A600 and 2 x P600.

g. The isolating switch shall always remain connected to the external operating handle. The isolating switch shall also be mechanically and electrically interlocked with the main contactor.

h. The external isolating switch operating handle shall have provisions to be padlocked, with up to three (3) padlocks in the open position.

i. The power cell door on each controller shall be interlocked with the isolating switch such that any medium voltage door(s) cannot be opened when the isolating switch is fully closed, and the isolating switch cannot be closed with the door(s) open (without defeating the safety interlock).

2. Interlocking

a. Provide mechanical interlocking (including cable interlocks, horizontal ram interlocks and vertical ram interlocks) to prevent the opening of any power cell door or medium voltage compartment until the non-load-break isolating switch is fully in the open position and power is removed (the external operating handle must be in the “OFF” position).

b. Optional key interlocks, configured to operate with the operating handle or power cell door, shall be available when interlocking is required with another specified

Pump Station 6 Starter Replacement 26 18 39 -8 device, i.e. main breaker, load-break switch, starter, etc.

3. Power Fuses and Fuse Holders

a. The power cell shall be designed to accept bolt-on or clip-on current limiting power fuses.

b. The medium voltage product shall have fixed power fuse holders that are separately mounted in the power cell, not on the contactor, and are located to allow easy inspection and replacement without any disassembly or removal of other components.

c. The power fuses shall provide visual condition indication by way of a spring-actuated blown fuse indicator.

d. The power fuse size shall be selected based on load data provided on the Drawings.

4. Current Transformers

a. The medium voltage power cell shall include current transformers (CTs) as indicated on Drawings. Selection of specific CTs for protection class, accuracy, window coordinated with power conductors, and minimal saturation risk is the responsibility of the supplier. Transformers shall be of sufficient VA capacity to meet the requirements of all the devices connected to them.

b. Each current transformer shall have the primary rating sized appropriately in relation to the full load current rating of the motor or feeder. The secondary of the current transformers shall have a 5 amp output and accuracy suitable for the type and quantity of protection or metering devices connected to it. All current transformer control wiring shall be terminated on the current transformer with locking-type, fork tongue lugs.

c. An appropriate load termination location shall be provided to accommodate lugs with NEMA two-hole mounting, for connection of the load cables.

d. The power cell shall have provisions to locate a toroid (donut) style, ground fault sensing current transformer, when zero sequence sensing is required.

5. Control Power Transformers

a. The control power shall be 120 VAC and shall be obtained from a control power transformer (CPT) located in each controller power cell. Provide additional CPT when voltage sensing is provided by protective relays indicated on Drawings.

b. The dry-type CPT shall be 500 VA in size, providing approximately 350 VA extra capacity for the customer's use when the standard control circuit is supplied.

c. The secondary circuit of the transformer(s) shall be disconnected from the control circuit by means of the isolating switch auxiliary contacts. This is to ensure the isolating switch does not make or break load current, to prevent backfeeding through the transformer(s) and to isolate the…

This is the start of the file's text. The full file is on GovTribe.